U.S. Minerals & Mining, Inc. v. Licensed Processors, Ltd.

551 N.E.2d 661, 194 Ill. App. 3d 428, 141 Ill. Dec. 474, 1990 Ill. App. LEXIS 159
Appellate Court of Illinois·Decided February 7, 1990·No. 5-88-0285·Published·Cited by 18 cases

Opinion

JUSTICE WELCH

delivered the opinion of the court:

The defendant and counterplaintiff, Licensed Processors, Ltd. (LPL), appeals from the judgment order entered January 4, 1988, and the post-trial order entered April 18, 1988, by the circuit court of Williamson County, Illinois. The judgment rescinded LPL’s contract with the plaintiff and counter defendant, U.S. Minerals & Mining, Inc. (USM), as requested by USM, but granted neither party status quo ante damages. In a cover letter to both parties enclosing the post-trial orders of April 18, 1988, denying LPL’s motion for modification of the judgment to grant it status quo ante damages, the court clarified that while restoration to the status.quo is generally the rule following rescission, if both parties have received benefits from- the contract prior to its termination, the court will only award damages if it finds unjust enrichment, and none had been shown in this case.

LPL also appeals from a post-trial order entered the same day which denied its petition for attorney fees and costs under section 2— 611 of the Illinois Code of Civil Procedure (Ill. Rev. Stat. 1987, ch. 110, par. 2 — 611), wherein the court specifically found that there had not been a sufficient showing of bad faith to sustain LPL’s section 2— 611 request. We note that the appellant has submitted for our review only a partial report of proceedings and none of the trial exhibits, except as they might also have appeared as exhibits in the common law record.

On appeal LPL raises the following issues:

(1) whether the trial court erred in failing to award damages to LPL when it rescinded the contract between LPL and USM; and

(2) whether denial of LPL’s section 2 — 611 petition for attorney fees and costs was against the manifest weight of the evidence and contrary to law.

USM owned the leasehold interest in certain coal mining property known as the Burning Star 1 Mine. USM removed and sold coal from the property during 1983 and 1984. In the spring of 1984 USM discovered that a certain amount of refuse carbon which had accumulated in slurry ponds could not be recovered by normal methods. USM contacted Gary Spiller of LPL with regard to its ability to clean and process this waste carbon so that it too could be sold. In August 1984, the parties entered into an agreement concerning the recovery and processing of the waste carbon. Relevant portions of the August 14, 1984 agreement provided that LPL would build and own the recovery plant and its equipment, which would be built on USM’s leasehold. The contract further provided that USM would acquire and own the dredge and pipeline which would carry the waste carbon to LPL’s plant for processing. The carbon, once cleaned and dried, would be carried off for sale by USM. LPL would receive compensation from USM of $3.32 per ton plus a premium of 20% of every ton sold at a price in excess of $10.90 per ton. These payments were to be made by USM out of the sale proceeds of each recovered coal shipment.

The contract also recited the assumption of the parties that LPL was an expert in the construction and operation of this type of coal-refuse processing plant. Although the contract specified that LPL would segregate coal according to size, and process “clean” coal, it did not specify the size of the finished product, the specific quality, i.e., minimum B.T.U. requirement, the amount required to be processed, or the minimum volume of slurry to be introduced, other than to say a “fixed rate of flow.” Archie Henderson, who was president of LPL as well as an attorney-at-law, drafted the agreement. The court, finding the contract ambiguous, considered parol evidence in defining some of the parties’ obligations under the contract. As far as the size of the coal to be processed, the court found it to be +28 mesh and that “clean coal” meant carbon with a B.T.U. rating of 10,400 or more, based on the contract price of $10.90 per ton. The court further found that both parties relied on a projected slurry feed of 250 to 260 tons per hour for LPL to produce 200 tons per hour of processed coal.

LPL borrowed $300,000 in connection with the purchase and construction of the plant, the total cost of which was $371,000. This loan was secured by LPL’s stock.

Processing of the carbon refuse began in December 1984, upon completion of the plant construction. From the beginning the operation was plagued with problems. The dredge and pumping operation was beset with equipment failure, inconsistent slurry composition (the contract required a mixture of between 22% to 35% solids), and down time for cleaning, repairing, and moving equipment at the recovery site. Because USM was unable to deliver a constant rate of slurry flow for the LPL plant to process, the projected production of 200 tons per hour was never realized. Over the 13 months of operation, the average production was only 50 tons per hour. The court did not fault USM for not supplying the constant flow or particular consistency of slurry mixture to LPL’s plant, charging instead that LPL, as the expert, should have foreseen the dredge and pumping problems and that the delivery requirements were unrealistic.

The parties held numerous discussions and attempted to remedy some of the problems over the next 13 months. However, on October 30, 1985, LPL shut down the processing plant. On November 4, 1985, USM filed suit against LPL claiming damages or rescission of the contract based on fraud, misrepresentation, or breach of contract. LPL reopened the plant shortly thereafter, and the parties continued to negotiate the contract problems.

In February 1986, LPL again shut down the operation. On the 18th of that month, LPL received notice from USM to remove the plant from its property. LPL did remove the plant in April 1986, but only after USM had disconnected the feed pipe from the dredge and built another processing plant nearby. LPL moved the plant to West Virginia, where it was used by a corporation partly owned by LPL’s president. LPL did not receive any compensation for the use of the plant by the West Virginia company. LPL defaulted on its loan payments in January 1987, and in order to avoid foreclosure sale of its security, LPL sold the plant and paid the loan in full.

The trial of this matter lasted 13 days, and in the course thereof, the court heard testimony of 17 witnesses and admitted 67 exhibits into evidence. Prior to the end of the defendant’s case, the court directed a verdict for the defendant on the fraud counts of the plaintiffs complaint. However, the court allowed an amendment of USM’s complaint in which it sought rescission of the contract based on mutual mistake. On that amended count the court ordered rescission of the contract but found that as both parties had benefitted during the contract term, no restoration of the status quo for LPL was required. The court further found that USM would not be unjustly enriched by rescission and that the status quo had effectively been reached on February 16, 1986, when production ceased. The court further found for LPL on one count of its counterclaim and entered judgment against USM in the amount of $3,290, representing unpaid premiums due LPL under the contract.

LPL contends that the court committed an error of law when it determined that the “status quo ante” date was February 17, 1986, rather than August 14, 1984.

Free access — add to your briefcase to read the full text and ask questions with AI

U.S. Minerals & Mining, Inc. v. Licensed Processors, Ltd., 551 N.E.2d 661, 194 Ill. App. 3d 428, 141 Ill. Dec. 474, 1990 Ill. App. LEXIS 159 (Ill. Ct. App. 1990).

551 N.E.2d 661 (U.S. Minerals & Mining, Inc. v. Licensed Processors, Ltd.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Vandenberg v. Brunswick Corporation
2017 IL App (1st) 170181 (Appellate Court of Illinois, 2017)
People v. Gilbert
2013 IL App (1st) 103055 (Appellate Court of Illinois, 2013)
McCarty v. Weatherford
838 N.E.2d 337 (Appellate Court of Illinois, 2005)
Krklus v. Stanley
833 N.E.2d 952 (Appellate Court of Illinois, 2005)
Webster v. Hartman
722 N.E.2d 266 (Appellate Court of Illinois, 1999)
People v. Ross
Appellate Court of Illinois, 1999
Palanti v. Dillon Enterprises, Ltd.
707 N.E.2d 695 (Appellate Court of Illinois, 1999)
Lempa v. Finkel
663 N.E.2d 158 (Appellate Court of Illinois, 1996)
Barter v. Slayback
600 N.E.2d 538 (Appellate Court of Illinois, 1992)
Hudlin v. City of East St. Louis
591 N.E.2d 541 (Appellate Court of Illinois, 1992)