US Fid. & Guar. Co. v. WELCO CONST. & UTIL. CO.

463 F. Supp. 510
CourtDistrict Court, D. South Carolina
DecidedDecember 14, 1978
DocketCiv. A. No. 77-728
StatusPublished

This text of 463 F. Supp. 510 (US Fid. & Guar. Co. v. WELCO CONST. & UTIL. CO.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
US Fid. & Guar. Co. v. WELCO CONST. & UTIL. CO., 463 F. Supp. 510 (D.S.C. 1978).

Opinion

463 F.Supp. 510 (1978)

UNITED STATES FIDELITY AND GUARANTY COMPANY, Plaintiff,
v.
WELCO CONSTRUCTION & UTILITIES CO., INC., William E. Lawrence, Sr., and William E. Lawrence, Jr., and the Newberry County Water and Sewer Authority, Defendants,
v.
Arthur PODMORE and J. Walter Hamm, Defendants in Cross Complaint.

Civ. A. No. 77-728.

United States District Court, D. South Carolina, Columbia Division.

December 14, 1978.

*511 James L. Bruner, Jackson L. Barwick, Jr., Belser, Baker, Belser, Barwick & Toal, Columbia, S.C., David W. Robinson, II, Columbia, S.C., for plaintiff.

Joseph W. Hudgens, Pope & Schumpert, Newberry, S.C., for Arthur Podmore and J. Walter Hamm, Newberry County Water & Sewer Authority.

George Anthony Smith, Smith, Currie & Hancock, Atlanta, Ga., Herbert W. Hamilton, Whaley, McCutchen & Blanton, Columbia, S.C., for defendants Welco Constr. & Utilities Co., William E. Lawrence, Sr. and William E. Lawrence, Jr.

ORDER ON MOTION OF DEFENDANT NEWBERRY COUNTY WATER & SEWER AUTHORITY TO DISMISS THE COMPLAINT AND CROSS-CLAIM FOR LACK OF JURISDICTION

HEMPHILL, District Judge.

Motion of defendant Newberry County Water and Sewer Authority, (hereinafter called the Authority) to realign the parties and dismiss the cause for lack of jurisdiction, filed October 11, 1978, begs decision of this court. After review of memoranda submitted by the various parties, a hearing was held at Columbia, South Carolina, on November 15, 1978.

This action was originally lodged in the United States District Court for the District of South Carolina on April 22, 1977 by plaintiff, a Maryland corporation, and admitted surety on a Payment and Performance Bond to defendant Welco Construction & Utilities Company, Inc., (hereinafter Welco), a South Carolina corporation, previously admittedly engaged to construct, under a contract, the water line from U. S. Highway 76 in Newberry County, South Carolina, to and in the Town of Pomaria, Newberry County, South Carolina, for the use and benefit of the defendant Authority.

The complaint recites the residence of the parties, and alleges that although its principal, Welco, performed in a satisfactory manner, as accepted by the Authority, the obligations of the contract, that the defendant Authority claimed later that the contract was not performed as agreed upon, and under pretense that the contract was not complete, it first called upon the plaintiff, as surety, to complete the contract, later rejected the contractor that the plaintiff had hired to perform the necessary completion; thereafter, upon authority of the plaintiff, defendant completed a punch list of incomplete items with a contractor of the Authority's own choosing, leaving the sum of approximately $46,000 retainage in the Authority's hands. Plaintiff alleges that the Authority, although authorized by plaintiff and Welco to pay certain retainage claims, nevertheless failed and refused to apply the retainage sums in the hands of the Authority to satisfy the claims of Welco's creditors with the result that the claims have now been made against plaintiff as surety. The complaint further alleges that claims have been made against the plaintiff in the sum of $92,000 which plaintiff may be called upon to pay by virtue of Welco's alleged default. Defendants Lawrence are made parties to the suit by virtue of an admitted Master Surety Agreement, in which defendants Welco and the Lawrences agreed to save harmless and keep plaintiff indemnified against all claims, demands and suits arising out of a failure of performance. The prayer of the complaint asks for enforcement of the amounts due under the surety agreement, to require defendant Welco and defendants Lawrence to exonerate and indemnify plaintiff, and asking judgment against them for any losses sustained. The relief sought against the Authority was for an accounting as to all sums due and owning arising out of the contract or its alleged default. Plaintiff also asks for costs and disbursement for such other relief as the court might find proper.

The Answer and Cross-claim of the Authority, filed May 19, 1977, admits the contract with Welco, alleges that Welco abandoned the contract prior to completion and that at the time of the abandonment there remained incomplete work amounting to the sum of approximately $49,771.75 which was required to be expended by the Authority *512 to complete and repair the uncompleted work of Welco. Defendant Authority admits that upon plaintiff's agreement that defendant agreed to go ahead and complete the contract, which it did, and states that Welco incurred claims of over $100,000; it further alleges that it furnished to plaintiff all the records relating to disbursements, etc., and no further accounting is necessary. For a second defense, the Answer states that the complaint fails to state a claim under Rule 12, Federal Rules of Civil Procedure. The cross-claim of the Authority against the co-defendants Welco, as principal, and plaintiff as surety is for a total recovery of $61,905.30, consisting of the amount expended by the Authority in correcting and completing the contract of Welco in the sum of $43,855.30, and the amount of $18,050 by way of liquidated damages for failure by Welco to complete the contract within the contracted time.

The Answer of Welco, filed May 23, 1977, admits the existence of the contract with the Authority, the existence of the bond, the existence of the Master Surety Agreement, and in general the controversy allegations of defendant Authority's Answer. It further alleges that it owes plaintiff nothing and asserted in two counts a cross-claim against the Authority. The first count seeks recovery of the balance due it under the contract in the sum of $49,071.75 and $42,000 for additional work performed beyond that required under its contract, as demanded by the Authority, plus interest and cost. Count 2 of the cross-claim alleges fraud on the part of the Authority and asked for $1,000,000 damages. The defendants Lawrence are parties to the answer and cross-claim of Welco.

On June 3, 1977, plaintiff filed a reply to the counterclaim of the defendant Authority, generally denying the same and demanding strict proof thereof.

On June 3, 1977, defendants Welco and Lawrence filed an amended answer and counterclaim, and on June 8, 1977, demanded a jury trial. On June 9, 1977, defendants Welco and the Lawrences filed an answer to the cross-claim of the Authority. On June 15, 1977, the defendant authority answered the cross-claim of Welco and the Lawrences. On June 16, 1977, defendants Welco and the Lawrences filed a second amended answer and cross-claim against the Authority, which second amended cross-claim was answered by the Authority on June 22, 1977.

In April, 1977, Welco and the Lawrences were permitted to add Arthur Podmore and J. Walter Hamm as defendants in their capacities as manager and chairman of the Authority, respectively, in support of a third count in their cross-complaint for fraud in certain alleged representations as to available water supply. Such amendment, however, did not enlarge the parties since both Podmore and Hamm were sued in their representative capacities as officers of the Authority.[1]

Depositions of various officials of the Authority, Welco, William E. Lawrence, Sr., William E. Lawrence, Jr., and employees and representatives of U.S.F. & G.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Meyer v. Construction Company
100 U.S. 457 (Supreme Court, 1879)
Pacific Railroad v. Ketchum
101 U.S. 289 (Supreme Court, 1880)
City of Indianapolis v. Chase National Bank
314 U.S. 63 (Supreme Court, 1941)
Indianapolis v. Chase Nat. Bank
314 U.S. 63 (Supreme Court, 1941)
State Farm Mut. Automobile Ins. Co. v. Hugee
115 F.2d 298 (Fourth Circuit, 1940)
Indianapolis v. Chase National Bank
314 U.S. 714 (Supreme Court, 1941)
Ready Truck Lines, Inc. v. United States
314 U.S. 715 (Supreme Court, 1941)
Wood v. Deskins
141 F. 500 (Fourth Circuit, 1905)

Cite This Page — Counsel Stack

Bluebook (online)
463 F. Supp. 510, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-fid-guar-co-v-welco-const-util-co-scd-1978.