U.S. Automatic Sprinkler Co. v. Reliable Automatic Sprinkler Co.

719 F. Supp. 2d 1020, 72 U.C.C. Rep. Serv. 2d (West) 191, 2010 U.S. Dist. LEXIS 58879, 2010 WL 2484279
CourtDistrict Court, S.D. Indiana
DecidedJune 11, 2010
Docket1:07-cv-0944-SEB-TAB
StatusPublished
Cited by2 cases

This text of 719 F. Supp. 2d 1020 (U.S. Automatic Sprinkler Co. v. Reliable Automatic Sprinkler Co.) is published on Counsel Stack Legal Research, covering District Court, S.D. Indiana primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
U.S. Automatic Sprinkler Co. v. Reliable Automatic Sprinkler Co., 719 F. Supp. 2d 1020, 72 U.C.C. Rep. Serv. 2d (West) 191, 2010 U.S. Dist. LEXIS 58879, 2010 WL 2484279 (S.D. Ind. 2010).

Opinion

ORDER GRANTING MOTIONS FOR SUMMARY JUDGMENT

SARAH EVANS BARKER, District Judge.

This cause is before the Court on Defendant The Reliable Automatic Sprinkler Company’s Motion for Summary Judgment [Docket No. 91], filed on May 1, 2009; and Defendant Ferguson Fire & Fabrication, Inc.’s Motion for Summary Judgment [Docket No. 93], filed on May 1, 2009. Plaintiff U.S. Automatic Sprinkler Co. has brought this cause of action against Defendants alleging breaches of the implied warranties of merchantability and fitness for a particular purpose, in connection with leaks that occurred in numerous fire protection systems Plaintiff installed at a project in Greenwood, Indiana, in 2003. For the reasons detailed in this entry, Defendants’ motions are GRANTED. 1

*1023 Factual Background

1. Leaks at The Quadrangle Project

Plaintiff U.S. Automatic Sprinkler Co. (“U.S. Automatic”) is a fire protection contracting company. Dep. of Agan at 14. In 2003, U.S. Automatic designed and installed a sprinkler system in a commercial warehouse in Greenwood, Indiana, known as the Quadrangle Project. In connection with this work, U.S. Automatic purchased approximately 4,800 Model K-22 sprinkler heads from Defendant The Reliable Automatic SprinMer Company’s (“Reliable”). Compl. ¶¶ 8, 18. U.S. Automatic also purchased a similar number of welded female pipe fittings on prefabricated steel pipes (“weld-o-lets”) from The Clark Group, Inc., corporate predecessor to Defendant Ferguson Fire & Fabrication, Inc. f/k/a The Clark Group, Inc. (“Ferguson”). 2 Compl. ¶ 24. The ordinary purpose of commercial sprinkler systems like those installed at the Quadrangle Project, and the sprinkler heads and weld-o-lets used in such systems, is to provide fire protection performance under water-pressurized conditions without leaks over an extended period of time. Dep. of Agan at 171; Beukema I at 137. 3

U.S. Automatic installed these components at the Quadrangle Project using its usual tools and techniques, which, over the course of many previous installations, had never resulted in significant leaks or related problems. Aff. of Agan ¶ 8. During this installation, however, some of U.S. Automatic’s technicians reported to Bruce Agan, President and majority shareholder of U.S. Automatic, that joining the sprinkler heads to the weld-o-lets had resulted in irregular tightening. Dep. of Agan at 149. Reliable typically requires its customers to use a wrench expressly designed for K-22 sprinklers, but U.S. Automatic did not utilize such a wrench, nor did it measure the amount of torque properly necessary to join these specific components. Id. at 96, 102; Beukema II at 25.

U.S. Automatic completed installation of the sprinklers into the weld-o-lets in late December of 2003. Dep. of Agan at 105. Upon finishing, U.S. Automatic began to test the sprinkler systems (there were eleven in total) by filling each system with water and bringing each to normal city water pressure, which process resulted in approximately 200 instances of leaking from the threaded connections between the sprinkler heads and weld-o-lets. Id. These leaks prompted U.S. Automatic to shut the systems down, drain them, and perform one of two remedial measures on each system: either removing the sprinkler heads, cleaning the joints, and reinstalling the components or simply tightening the sprinkler heads with an additional 180 degree turn. Id. at 108.

Following these measures, U.S. Automatic began hydrostatic testing of the fire protection systems by filling them with water and slowly increasing the water pressure until it was greater than the standard operating pressure for the system. Id. at 111. By early January 2004, all eleven systems at the Quadrangle project had successfully passed this hydrostatic testing. Id. at 114. Two weeks later, however, additional leaks began to develop, which U.S. Automatic attempted to fix *1024 by again applying the above measures. This cycle continued for several months, until it became obvious that these remedial steps would not yield a permanent solution. Aff. of Agan ¶ 11.

At some point between January and March of 2004, Ross Maxwell of The Clark Group, Inc. (predecessor company of Ferguson, who provided the weld-o-lets to U.S. Automatic) recommended to Agan that he try sealing the joints with an anaerobic sealant. Dep. of Maxwell at 41; Dep. of Agan at 125, 126. The use of such a sealant was not immediately chosen by U.S. Automatic as a remedial measure in part because it was considered an expensive, time consuming, and uncommon installation repair method. Aff. of Agan ¶ 12. In March 2005, however, U.S. Automatic did apply this sealant to one of the eleven sprinkler systems, which succeeded in preventing further leaks. Dep. of Agan at 122. Four months later, at the request of the general contractor for the Quadrangle Project, U.S. Automatic applied this successful procedure to all the remaining ten systems. Id.

II. Investigations of the Leaks and Their Causes

U.S. Automatic suspected throughout this process that the leaking had been caused by problems with the components provided by Reliable and Ferguson. In an effort to investigate and pursue this theory, U.S. Automatic engaged Dr. George Langford, an experienced metallurgist, to determine what, in his expert opinion, caused the leakage in the sprinkler systems at the Quadrangle Project. Aff. of Langford ¶¶ 4, 5. Based on measurements of what he viewed as the faulty components that had been installed at the project, Dr. Langford opined that the variability of the helix angle of the thread on the Reliable sprinkler heads was a contributing factor to the leaks. Id. at ¶ 5. He further concluded that, in certain instances, the Clark weld-o-lets were “out of round,” or misshapen in such a way as to have also likely contributed to the leaks. Id. at ¶ 8.

An analysis of the components was also conducted by Reliable when U.S. Automatic returned three allegedly faulty sprinkler heads to them soon after the first leaks developed. Dep. of Agan at 132. Reliable conducted three tests on the threads of these components, which included measuring those threads with a specialized gauge, subjecting them to pressure tests, and measuring the threads with an optical comparator. Beukema II at 16, 74; Beukema I at 100. According to John Beukema, who oversaw this testing in his role as Reliable’s Director of Engineering in 2004, all three sprinkler heads passed these tests within standard tolerances. Beukema I at 95; Beukema II at 18; Beukema I at 20.

Based on these tests, Beukema concluded that the Reliable sprinklers that had been installed at the Quadrangle Project would have formed a leak-tight seal if the proper sealant had been applied and if the female connection (here, the weld-o-let) was free from defect. Beukema II at 135, 139.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Conagra Foods, Inc.
90 F. Supp. 3d 919 (C.D. California, 2015)
Archer Daniels Midland Co. v. ECO, Inc.
821 F. Supp. 2d 1083 (S.D. Iowa, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
719 F. Supp. 2d 1020, 72 U.C.C. Rep. Serv. 2d (West) 191, 2010 U.S. Dist. LEXIS 58879, 2010 WL 2484279, Counsel Stack Legal Research, https://law.counselstack.com/opinion/us-automatic-sprinkler-co-v-reliable-automatic-sprinkler-co-insd-2010.