Urban Council on Mobility v. Minnesota Department of Natural Resources

289 N.W.2d 729, 1980 Minn. LEXIS 1288
CourtSupreme Court of Minnesota
DecidedJanuary 25, 1980
Docket50636, 50685
StatusPublished
Cited by18 cases

This text of 289 N.W.2d 729 (Urban Council on Mobility v. Minnesota Department of Natural Resources) is published on Counsel Stack Legal Research, covering Supreme Court of Minnesota primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Urban Council on Mobility v. Minnesota Department of Natural Resources, 289 N.W.2d 729, 1980 Minn. LEXIS 1288 (Mich. 1980).

Opinion

SCOTT, Justice.

This appeal involves an order of the Commissioner of Natural Resources, dated December 15, 1978, which denied the application of the Minnesota Department of Transportation (DOT) for a permit to construct a portion of Interstate Freeway I-35-E by bridging Blackhawk Lake in Eagan, Minnesota, and, instead, provided that the DOT be granted a permit to construct the required freeway segment around the east side of the lake. The district court reversed the commissioner’s decision and ordered that the DOT be allowed to construct a part of I-35-E on a bridge located across Black-hawk Lake. We reverse the district court and reinstate the decision of the commissioner.

Interstate 35, as planned, runs from Laredo, Texas, to Duluth, Minnesota. Just south of the Twin Cities, in Burnsville, Minnesota, the freeway divides, with I-35-W proceeding through Minneapolis and I— 35-E traveling through St. Paul. The two routes come together north of the Twin Cities in Forest Lake, Minnesota. The interstate is completed from the southern Iowa border to Duluth, with two exceptions: (1) a five-mile segment of I-35-E in St. Paul (not involved in this case), and (2) a 13-mile length of I-35-E running from its southernmost point in Burnsville to Highway 110 in Mendota Heights, which includes the crossing of Blackhawk Lake in Eagan.

The 13-mile Burnsville to Mendota Heights portion of I-35-E was planned in late fall, 1958. Three alternate routes were then proposed — all three crossed Blackhawk Lake. A location hearing was held in Burnsville on August 24, 1959, at which time the alternative routes were presented. One of the proposed alternatives was selected and approved by the Bureau of Public Roads (now Federal Highway Administration [FHWA]) in January 1960.

*731 In August, 1971, after the holding of a public design hearing, the DOT received approval from the FHWA for the design of a portion of the subject freeway. However, when requested in December 1971 to approve the design of the remaining part, which includes Blackhawk Lake, the FHWA recommended that an Environmental Impact Statement (EIS) be prepared on the entire 13-mile segment to comply with the National Environmental Policy Act of 1969.

The DOT began work on the EIS in September 1973. Since the alternative of going around the lake was not recognized by the DOT until the late fall of 1975, the initial reports compiled for the EIS did not include reference to that possibility. However, the draft EIS, completed in June 1976, and the final EIS issued in May 1977 do contain analyses of both alternatives. The final EIS prepared by the DOT selected the alternative of bridging Blackhawk Lake. The EIS states:

The selection of either alternative * * * would be satisfactory from an engineering standpoint and either would be consistent with the regional (Metropolitan Council) land use desires for the area. Both could be designed to provide a safe freeway and both would cost' about the same.
[Bridging the lake] was selected because of the strong local preference for it. That preference is reflected in the long history of land use planning and development that has been predicated on [that alternative].
The local desires thus outweigh the negative environmental impacts of crossing Blackhawk Lake.

In May 1978 the DOT, pursuant to Minn. Stat. § 105.42 (1978), applied to the Department of Natural Resources (DNR) for a permit to cross Blackhawk Lake. On June 8 and 15, 1978, a notice of hearing was published in the Dakota County Tribune. Various parties moved to intervene, and were allowed to do so by the hearing examiner. The Cities of Eagan and Burnsville, the Urban Council on Mobility (UCOM) and the Dakota County Development Association (DCDA) intervened on the side of the DOT, urging the DNR to grant the requested permit. Associated Families (AF), a partnership of seven families which owns approximately 80 acres of land on the north side of the lake, and the Minnesota Pollution Control Agency (PCA) intervened in opposition to the issuance of the permit. The DNR staff also appeared in opposition to the DOT’s proposed action.

A three-week hearing, generating about 3,000 pages of transcript, was held in the months of June and July, 197$. The essential question litigated was whether I-35-E should cross Blackhawk Lake by way of a bridge (designated alternative A — 1) or whether the freeway should be routed around the east end of the lake (designated alternative A — 2). Each alternative is about three miles long and the traffic volume under either alternative is anticipated to be, in the year 2000, about 71,000 vehicles per day.

In an extensive 33-page report dated November 9, 1978, the hearing examiner compared routes A-l and A-2, and concluded that A-2 is the preferable alternative. Specifically, with respect to A-2, the report states that “a feasible and prudent alternative is available which does not have material detrimental aspects.” Consistent with his findings and conclusions, the hearing examiner recommended that the Commissioner of Natural Resources deny the DOT’s requested permit.

On December 15, 1978, the commissioner adopted as his own the findings and conclusions of the hearing examiner, with the following exception:

Contrary to the hearing examiner’s finding * * * that the environmental effects which would be caused by construction of the freeway along route A-2 are not “material,” I specifically find such effects to be material as the effects always will be when associated with a project of such scope. However, said effects as a whole, will be significantly reduced by construction along route A-2 than along route A-l, and no other more *732 feasible and prudent route has been shown to exist.

Consequently, the commissioner denied the DOT permission to route I-35-E across Blackhawk Lake and ordered that a permit would be granted for the construction of route A-2, subject to DNR approval of final plans and specifications. 1

UCOM petitioned for judicial review of the agency order in accordance with Minn. Stat. § 15.0424 (1978), and AF intervened in the proceeding. By a decision issued September 13, 1979, the district court reversed the commissioner’s order and ruled that the DOT was entitled to a permit to construct a bridge across Blackhawk Lake. The court reasoned that (1) the commissioner’s decision was not supported by substantial evidence; and (2) the permit for route A-2 was improperly granted 2 because no permit application had been made for A-2 and an EIS in final form on route A-2 had not been presented. In ruling on the substantial evidence question, the court relied heavily upon the delay which would be encountered should route A-2 be selected over A-l. AF subsequently moved for a new trial on the ground that newly discovered evidence shows that the time difference between the A-l and A-2 alternatives is only about two months. AF’s motion was denied.

AF now appeals to this court from the trial court’s order reversing the commissioner and the order denying a new trial. The following have been granted permission by this court to appear as amici curiae

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Restorff
932 N.W.2d 12 (Supreme Court of Minnesota, 2019)
McElhaney v. City of Moab
2017 UT 65 (Utah Supreme Court, 2017)
Buchwald v. University of Minnesotsa
573 N.W.2d 723 (Court of Appeals of Minnesota, 1998)
State Ex Rel. Schaller v. County of Blue Earth
563 N.W.2d 260 (Supreme Court of Minnesota, 1997)
In Re the Insurance Agent License of Thomas Casey, Sr., P.A.
540 N.W.2d 854 (Court of Appeals of Minnesota, 1996)
McGuire v. County of Scott
525 N.W.2d 583 (Court of Appeals of Minnesota, 1994)
Contested Cases of Rem-Canby, Inc. v. Minnesota Department of Human Services
494 N.W.2d 71 (Court of Appeals of Minnesota, 1993)
In Re Occupational License of Hutchinson
440 N.W.2d 171 (Court of Appeals of Minnesota, 1989)
In Re the Real Estate Salesperson's License of Perron
437 N.W.2d 92 (Court of Appeals of Minnesota, 1989)
Cable Communications Board v. Nor-West Cable Communications Partnership
356 N.W.2d 658 (Supreme Court of Minnesota, 1984)
Roach v. Commissioner of Department of Natural Resources
356 N.W.2d 432 (Court of Appeals of Minnesota, 1984)
Department of Natural Resources v. Todd County Hearings Unit
356 N.W.2d 703 (Court of Appeals of Minnesota, 1984)
City of Moorhead v. Minnesota Public Utilities Commission
343 N.W.2d 843 (Supreme Court of Minnesota, 1984)
Bennion v. Utah State Board of Oil, Gas & Mining
675 P.2d 1135 (Utah Supreme Court, 1983)
Whaley v. Anoka-Hennepin Independent School District No. 11
325 N.W.2d 128 (Supreme Court of Minnesota, 1982)
Kroll v. Independent School District No. 593
304 N.W.2d 338 (Supreme Court of Minnesota, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
289 N.W.2d 729, 1980 Minn. LEXIS 1288, Counsel Stack Legal Research, https://law.counselstack.com/opinion/urban-council-on-mobility-v-minnesota-department-of-natural-resources-minn-1980.