Upper Snake River Chapter of Trout Unlimited v. Hodel

706 F. Supp. 737, 19 Envtl. L. Rep. (Envtl. Law Inst.) 20832, 1989 U.S. Dist. LEXIS 1025, 1989 WL 9219
CourtDistrict Court, D. Idaho
DecidedJanuary 24, 1989
DocketCiv. 88-4100
StatusPublished
Cited by3 cases

This text of 706 F. Supp. 737 (Upper Snake River Chapter of Trout Unlimited v. Hodel) is published on Counsel Stack Legal Research, covering District Court, D. Idaho primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Upper Snake River Chapter of Trout Unlimited v. Hodel, 706 F. Supp. 737, 19 Envtl. L. Rep. (Envtl. Law Inst.) 20832, 1989 U.S. Dist. LEXIS 1025, 1989 WL 9219 (D. Idaho 1989).

Opinion

MEMORANDUM DECISION

CALLISTER, District Judge.

The Court conducted hearings on November 8 and 9, 1988, on plaintiffs’ motion for preliminary injunction. At the conclusion of the hearing counsel for all parties stipulated that the Court may consider the case as having been fully submitted on the merits, and that the evidence produced at the hearing, together with the affidavits and pleadings filed by the parties, may be considered by the Court to resolve the entire case without the need for further hearing. The parties have now submitted their final briefing and the matter is ready to be resolved. This written memorandum decision shall constitute the Court’s findings of fact and conclusions of law pursuant to Fed.R.Civ.P. 52.

FINDINGS OF FACT

The subject of this lawsuit centers around the water, or lack thereof, flowing in the South Fork of the Snake River below the Palisades Dam. The plaintiffs, primarily sportsmen, filed suit against the Bureau of Reclamation (BOR) claiming that the BOR is required to complete an Environmental Impact Statement (EIS) in compliance with the National Environmental Policy Act (NEPA), 42 U.S.C. § 4331 et seq., before reducing the flow below Palisades Dam to 1,000 cubic feet per second (cfs) or lower. In addition to the initially named defendants, the Court has allowed a number of defendants to intervene, those being canal companies and irrigation districts.

The Palisades Dam and Reservoir which began operating in 1957 constitutes a portion of the BOR’s Minidoka Project which is a series of dams and reservoirs throughout much of South East and South Central Idaho. The Palisades Dam and Reservoir provides for storage and regulation of water for irrigation, flood control, power production, fish and wildlife, and recreation. Approximately 1,173,000 acres receive all or part of its water source from the Minidoka System. The storage capacity of Palisades is 1,200,000 acre feet while the storage capacity of the entire Minidoka Project is 4,151,490 acre feet. See Defendants’ Exhibit 9.

In years when the precipitation is average or above, there is no cause for alarm. However, because of the unusually dry past, flows released from Palisades Dam were reduced to approximately 750 cfs during the winter months of 1987-1988. As of October 1988, the Palisades Reservoir contained only 200,000 acre feet of water, an unprecedented low due to the two consecutive years of drought conditions. The entire Minidoka System is desperately in need of large quantities of water. On October 26, 1988, the entire system was 89% depleted with only ¼ of the normal supply available. The inadequate amount of water storage and bleak future outlook were in part why the BOR reduced the flows below Palisades to 750 cfs on November 4, 1988. Prior to reducing the flow to 750 cfs, the BOR had consulted with the Idaho Department of Fish and Game.

The South Fork of the Snake River, a “blue ribbon trout stream,” lures fisher *739 men from all over the world to come experience the thrill of catching a cutthroat or brown trout. These trophy fish have continued to thrive even though there has been a number of recorded incidents in which the flows below Palisades Dam were less than 1,000 cfs since the Dam was built in 1957.

The BOR has entered into contracts with various individuals and entities for the storage of water in Palisades Reservoir for delivery during the irrigation season. Certain contract spaceholders have a winter water savings clause in their contracts. This clause is an agreement by the space-holders to forego diversions of water from the Snake River during the period from November 1 through April 30. These spaceholders who forego their use of water are then given a priority interest in the water stored in Palisades Reservoir. See, e.g., Defendants’ Exhibit 10.

In 1950, the BOR reported to Congress in a supplemental report concerning the future operation of Palisades Dam and Reservoir which became part of the authorizing legislation that the anticipated stream flow below the reservoir would be “an average daily flow of 1,000 second feet and a minimum of approximately 500 second feet would be provided below the dam as compared with the present minimum flow of 1,700 second feet.” See Defendants’ Exhibit 7, p. 37, section 18.

It is without controversy that reducing the stream flows below 1,000 cfs will have a negative impact on the downstream fishery. However, controversy does arise as to the extent of that injury. The Court recognizes that the fishery’s injury to a large extent will be upon the juvenile classes. 1 However, the Court is not persuaded to adopt the extent of injury alluded to by the plaintiffs and their expert, Mr. Steve Elle. Furthermore, past reductions in the flow below 1,000 cfs demonstrates that the “blue ribbon fishery” can rejuvenate in time. Even the plaintiffs’ expert Mr. Elle, testified that the fishery could revive in three to five years.

It is likely that the reduced flows below Palisades Dam will have an adverse effect on the quality of the fishery and an economic impact on area outfitters and guides as well as others involved in the tourism industry. However, that economic effect is slight when compared to the potential loss which would result from the failure to store water required for irrigation of crops in the Minidoka Project. The estimated losses which could occur by increasing the outflow start at $235 million and could easily continue upwards. See Defendants’ Exhibits 16 and 17.

CONCLUSIONS OF LAW

The Court issued an order denying plaintiffs’ request for preliminary injunction on November 18, 1988. This memorandum decision sets out in detail the Court’s written findings on that preliminary injunction as well as the case on the merits.

The parties to this cause of action agree that the specific issues before this Court are ones of first impression. Such groundbreaking compels the Court to communicate its reasoning with more precision and understanding.

The standard for obtaining a preliminary injunction in the Ninth Circuit was set forth recently in United States v. Odessa Union Warehouse Co-op, 833 F.2d 172 (9th Cir.1987). There, the court found that the traditional factors considered in determining whether or not to grant a preliminary injunction are: (1) the likelihood of plaintiff’s success on the merits; (2) the possibility of plaintiff suffering irreparable injury if the relief is not granted; (3) the extent to which the balance of hardships favor the respective parties; and (4) in certain cases whether the public interest will be advanced by the provision of preliminary relief. Id. at 174.

*740

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Mo. Ex Rel. Nixon v. Craig
978 F. Supp. 902 (W.D. Missouri, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
706 F. Supp. 737, 19 Envtl. L. Rep. (Envtl. Law Inst.) 20832, 1989 U.S. Dist. LEXIS 1025, 1989 WL 9219, Counsel Stack Legal Research, https://law.counselstack.com/opinion/upper-snake-river-chapter-of-trout-unlimited-v-hodel-idd-1989.