Universal Marble & Granite, L.L.C. v. Gerner

2014 Ohio 4349
CourtOhio Court of Appeals
DecidedSeptember 30, 2014
DocketWD-13-052
StatusPublished
Cited by1 cases

This text of 2014 Ohio 4349 (Universal Marble & Granite, L.L.C. v. Gerner) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Universal Marble & Granite, L.L.C. v. Gerner, 2014 Ohio 4349 (Ohio Ct. App. 2014).

Opinion

[Cite as Universal Marble & Granite, L.L.C. v. Gerner, 2014-Ohio-4349.]

IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT WOOD COUNTY

Universal Marble & Granite, LLC Court of Appeals No. WD-13-052

Appellant Trial Court No. CVF 1201143

v.

Franz Gerner, et al. DECISION AND JUDGMENT

Appellees Decided: September 30, 2014

*****

V. Robert Candiello, for appellant.

Jon M. Ickes, for appellee.

OSOWIK, J.

{¶ 1} This is an appeal from a judgment of the Perrysburg Municipal Court after a

trial to the bench that found for appellees on appellant’s complaint seeking money

damages for work performed on appellees’ home. For the reasons that follow, the

judgment of the trial court is affirmed. {¶ 2} In April 2012, the parties entered into a written contract pursuant to which

appellant would provide and install a granite countertop and a sink in appellees’ kitchen

for a total cost of $6,128.17. This included application of a granite sealer with what

appellant represented to be a 15-year guarantee for $499.00. Appellees made a down

payment of $2,974.10. After appellant’s agent, David Hernandez, installed the

countertop and sink he noticed that the countertop was off-center when measured against

the cabinet below and the kitchen window. Hernandez asserts that appellees approved

the installation even though it was off-center. It is undisputed that the countertop was

installed improperly. Appellees deny they were told of the problem and state they did not

notice it until after Hernandez left their home. Within minutes of Hernandez leaving

appellees’ home, they called appellant and placed a stop payment on their final check to

the business. When appellant did not return to cure the defect, appellees hired another

contractor to fix the problem at a cost of $3,390.

{¶ 3} On August 3, 2012, appellant filed a complaint in Perrysburg Municipal

Court, Small Claims Division, seeking judgment in the amount of $3,000 representing the

amount due together with interest and cost of this action. Shortly thereafter, the matter

was transferred to the court’s regular docket. On August 22, 2012, appellees filed an

answer and counterclaim demanding judgment against appellant for breach of contract

for failing to complete the work in a workmanlike manner, damaging appellees in the

amount of $3,390 and for statutory treble damages for consumer fraud.

2. {¶ 4} Following a bench trial, the trial court found that the countertop had not

been installed in a workmanlike manner and that appellant was not entitled to recover

from appellees. Further, the court found that appellees were entitled to judgment for their

counterclaim against appellant in the amount of $3,390 to fix the defect. Lastly, the trial

court found that appellant’s sale to appellees of a countertop sealer for $499 that retails

for $48 was unconscionable under R.C. 1345.03(2), and awarded treble damages

amounting to $1,497.

{¶ 5} Appellant sets forth three assignments of error:

Assignment of Error No. 1:

The Trial Court’s finding that Appellant’s installation of Appellees’

Granite kitchen countertops was not performed in a workmanlike manner

giving rise to an award of damages was contrary to law and against the

manifest weight of the evidence.

Assignment of Error No. 2:

The Trial Court’s award of Judgment in favor of the Appellees and

against Appellant in the amount of $3,390.00 was an abuse of discretion

and contrary to law.

Assignment of Error No. 3:

The Trial Court committed reversible error in finding Appellant

committed unconscionable acts in violation of Section 1345.03(2) of the

Ohio Revised Code thereby awarding treble damages, when such findings

3. and award were based solely on lack of authentication and hearsay

evidence.

{¶ 6} In support of its first assignment of error, appellant asserts that two

witnesses testified the countertop was installed pursuant to standard procedure and that,

when the deviation was noted, appellees were informed. Appellant argues that appellees

knew the countertop was off-center but allowed appellant to proceed with the job.

{¶ 7} In reviewing a disputed judgment, this court must be guided by the principal

that judgments supported by some competent, credible evidence must not be reversed as

being against the manifest weight of the evidence. C.E. Morris Co. v. Foley Constr. Co.,

54 Ohio St.2d 279, 279, 376 N.E.2d 578 (1978). Every reasonable presumption must be

made in favor of the judgment. Seasons Coal Co., Inc. v. City of Cleveland, 10 Ohio

St.3d 77, 80, 461 N.E.2d 1273 (1984).

{¶ 8} The record reflects that appellees’ witness Mitch Warnike, who has worked

in the granite and countertop installation business for 28 years, testified that he went to

appellees’ home to look at the countertop. Warnike stated that the countertop was off-

center and that the work was substandard. Audree Hernandez, appellant’s office

manager, testified that she received a call from one of the installers at appellees’ home

who reported to her that there was an issue with the countertop because the sink was not

centered with the base cabinet. Hernandez then received a second call from the installers

and was told appellees were willing to proceed with the installation. Appellee Anne

Gerner testified she was never told there was a problem with the center line of the

4. countertop. Gerner stated she and her husband were not told by the installers that the

whole sink would be off-center, nor did the workmen say that the countertop should be

replaced due to the flaw. She further testified that she approved the installation before

the workmen left based on how the seams looked and that she did not look at the sink

once it was installed. Gerner testified that ten minutes after the installers left, when she

and her husband saw that the sink itself was off-center, she called the store. Gerner

testified that the office worker with whom she spoke said she would talk to someone else

about the issue. She further testified that her husband called the store nine times and

spoke to someone only once. After her husband’s initial conversation, no further calls

were returned and no one from the store came to the house to look at the countertop.

Franz Gerner testified that he watched as the countertop was installed and did not notice

that the sink was off-center until ten minutes after the workers left his home.

{¶ 9} The issue before this court essentially appears to be one involving the

credibility of the two parties, whose testimony did conflict in some respects. The

determination of the disputed issues rests upon the credibility of the witnesses and is to

be decided by the trier of fact who, in this instance, found appellees and their witness

more credible. This court has reviewed the full record of the trial court, including the

testimony at trial and the exhibits admitted into evidence. We will not second guess the

trial court’s decision, which relied heavily on its determination of witness credibility.

Accordingly, we find that the trial court’s judgment was supported by some competent,

5. credible evidence and was not against the weight of the evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Quest Workforce Solutions, L.L.C. v. Job 1USA, Inc.
2018 Ohio 3304 (Ohio Court of Appeals, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ohio 4349, Counsel Stack Legal Research, https://law.counselstack.com/opinion/universal-marble-granite-llc-v-gerner-ohioctapp-2014.