Univ. of Md. v. MFE Inc./NCP Architects, Inc.

691 A.2d 676, 345 Md. 86, 1997 Md. LEXIS 21
CourtCourt of Appeals of Maryland
DecidedMarch 10, 1997
Docket24, Sept.Term, 1996
StatusPublished
Cited by9 cases

This text of 691 A.2d 676 (Univ. of Md. v. MFE Inc./NCP Architects, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Univ. of Md. v. MFE Inc./NCP Architects, Inc., 691 A.2d 676, 345 Md. 86, 1997 Md. LEXIS 21 (Md. 1997).

Opinion

WILNER, Judge.

This appeal concerns a dispute between the University of Maryland and a joint venture of architects (which' we shall hereafter refer to, collectively, as MFE) arising out of a procurement contract for architectural services. We granted *89 certiorari to consider the narrow question of whether delivery to MFE of the procurement officer’s final decision by facsimile transmission (FAX) sufficed to commence the 30-day period allowed for filing an appeal to the State Board of Contract Appeals (BCA). In the course of our research on that issue, however, we discovered a more significant problem: the BCA had no subject matter jurisdiction over the claim.

BACKGROUND

The relevant facts are undisputed. In September, 1981, the parties entered into a contract calling for MFE to provide plans and specifications for the renovation and expansion of the McKeldin Library on the University’s College Park campus. On May 4,1993—nearly 12 years later and after completion of the construction based on those plans and specifications—the University gave written notice to MFE that it was asserting a claim in the amount of $2,470,792 for certain delay and additional construction costs allegedly incurred by the University as the result of errors and omissions in MFE’s designs. Insofar as we can tell from the record, the University was not then holding any money owing to MFE under the contract. It was not attempting, therefore, to set off its claim against funds otherwise due to MFE but rather was seeking to have MFE affirmatively pay the amount of the claim to the University. The letter informed MFE that it could file a response within 30 days.

By letter dated June 4, 1993—the thirty-first day, as we count it—MFE, through its attorney, filed a response denying liability. 1 The attorney sent the response to the University “Via Facsimile and Overnight Mail” on her law firm’s stationery, which included the firm’s FAX number.

By letter dated October 28, 1993, addressed to the attorney, the Director of the University’s Department of Procurement and Supply informed MFE that the State was entitled to *90 indemnification for costs aggregating $2,043,735 due to MFE’s design errors and omissions. The letter stated that it constituted the final action of the procurement officer and that the decision could be appealed to the BCA in accordance with Code of Maryland Regulations (COMAR) 21.10.04.06. The letter concluded with the statement, “If you decide to take such an appeal, you must mail or otherwise file a written notice of appeal with the Appeals Board within 30 days from the date you receive this decision.”

The 15-page letter was sent to the attorney by FAX transmission from the Contract Litigation Unit of the Attorney General’s Office on October 29, 1993. The transmission produced a Transmission Result Report showing, among other things, a date of October 29, 1993, a time of 11:25 a.m., 15 pages, and a “Result” of “OK.” After the transmission was completed, a secretary in that unit called the attorney’s office and was informed by someone named Tina that the FAXed document had been received. She then wrote on the Transmission Result Report: “Called 10/29/93—11:35 a.m.—spoke to Tina. It was received.”

Not content to rely solely upon the FAX transmission, the Assistant Attorney General also sent a copy of the decision to the attorney by Federal Express on October 29. On December 8, 1993, upon a tracer request, one Deborah Constable, listed by Federal Express as being with the State Department of Transportation but identified otherwise as being a secretary in the Attorney General’s office, was informed by Federal Express that its records showed that the document was delivered to an L. Garett on November 1, 1993. The identity of Mr. or Ms. Garett is not revealed in the record before us, but it is undisputed that the document was, in fact, delivered to someone in the attorney’s office on November 1. That document, being a copy of the one FAXed on October 29, also ended with the statement that it constituted the final action of the procurement officer, that it could be appealed to the BCA in accordance with COMAR 21.10.04.06, and that, to take such an appeal, it was necessary to file a written notice with the BCA within 30 days “from the date you receive this decision.”

*91 On November 29, 1993, the attorney sent a notice of appeal to the BCA. The notice was sent by first class mail and was received by the BCA on November 30. On December 30, the University moved to dismiss the appeal on the ground that it was untimely. The University argued that the time for appeal commenced to run on October 29, when the Director’s final decision was transmitted to the attorney by FAX, and that the time elapsed on November 28.

The BCA agreed with the University and dismissed the appeal. It noted that the pertinent COMAR regulation (21.10.04.04D) requires that the procurement agency’s final decision be “furnished to the contractor by certified mail, return receipt requested, or by any other method that provides evidence of receipt” and held that the FAX transmission in this instance constituted a method that provided evidence of receipt. It observed that the record left no doubt that MFE had actual possession of the final decision on October 29 and that transmission of copies by FAX “has become an everyday event in the ordinary course of business” and was “accurate, reliable and meets all of the substantive tests as a method of furnishing the final decision to the contractor.”

Both the Code and COMAR require that an appeal from a final agency decision denying a contract claim be filed within 30 days after receipt of the notice of final action. Rejecting MFE’s claim that the appeal should be regarded as having been filed when the notice was dropped in the mailbox on November 28, the BCA held that the appeal was actually filed on November 30 and was therefore two days late. On March 7, 1994, the BCA dismissed the appeal for lack of jurisdiction. It confirmed that ruling on June 30, when it denied MFE’s motion for reconsideration.

The Circuit Court for Baltimore County, on judicial review, reversed the BCA ruling, holding that the combination of FAX and telephone follow-up did not suffice to constitute a furnishing of the final agency decision by “any other method that provides evidence of receipt,” as required by COMAR 21.10.04.04D. The court concluded that the regulation did not *92 contemplate delivery by FAX because that method of transmission was not used when the regulation was adopted.

DISCUSSION

State procurement is governed by statute and regulation, and we therefore turned to them to determine whether the transmission of a final agency procurement decision by FAX suffices to commence the time for noting an appeal to the BCA. To our surprise—and no doubt to the surprise of the parties, as neither of them has raised the issue—we discovered that the administrative BCA procedure created by statute does not apply to a claim such as this one—an attempt by a State agency to force a former contractor to pay over money not then being held by the agency under the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Center, LLC v. Lexington Charles Ltd. Partnership
92 A.3d 400 (Court of Appeals of Maryland, 2014)
Salisbury University v. Joseph M. Zimmer, Inc.
20 A.3d 838 (Court of Special Appeals of Maryland, 2011)
Laurel Racing Ass'n v. Video Lottery Facility Location Commission
975 A.2d 894 (Court of Appeals of Maryland, 2009)
University System of Maryland v. Mooney
966 A.2d 418 (Court of Appeals of Maryland, 2009)
Heery International, Inc. v. Montgomery County
862 A.2d 976 (Court of Appeals of Maryland, 2004)
Sefac Lift & Equipment Corp. v. Mass Transit Administration
788 A.2d 192 (Court of Appeals of Maryland, 2002)
State v. Maryland State Board of Contract Appeals
773 A.2d 504 (Court of Appeals of Maryland, 2001)

Cite This Page — Counsel Stack

Bluebook (online)
691 A.2d 676, 345 Md. 86, 1997 Md. LEXIS 21, Counsel Stack Legal Research, https://law.counselstack.com/opinion/univ-of-md-v-mfe-incncp-architects-inc-md-1997.