United Sys. of Ark. Inc. v. Beason & Nalley Inc.

2014 Ark. App. 534
CourtCourt of Appeals of Arkansas
DecidedOctober 8, 2014
DocketCV-13-1057
StatusPublished

This text of 2014 Ark. App. 534 (United Sys. of Ark. Inc. v. Beason & Nalley Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United Sys. of Ark. Inc. v. Beason & Nalley Inc., 2014 Ark. App. 534 (Ark. Ct. App. 2014).

Opinion

Cite as 2014 Ark. App. 534

ARKANSAS COURT OF APPEALS DIVISIONS II AND III No. CV-13-1057

Opinion Delivered October 8, 2014 UNITED SYSTEMS OF ARKANSAS, INC. APPEAL FROM THE PULASKI APPELLANT COUNTY CIRCUIT COURT, THIRTEENTH DIVISION V. [NO. CV-2013-689]

HONORABLE COLLINS KILGORE, BEASON & NALLEY, INC., CHAD JUDGE BRALEY, AND DAVID MILLER APPELLEES REVERSED AND REMANDED

JOHN MAUZY PITTMAN, Judge

This is an appeal from a judgment of dismissal with prejudice on the pleadings of

appellant United Systems’ lawsuit against appellees Beason & Nalley, Inc.; its former director

and owner, Chad Braley; and its former consultant, David Miller (collectively referred to

hereafter as Beason & Nalley). Appellant argues that the trial court erred in finding that

grounds for dismissal existed. We agree, and we reverse and remand.

United Systems hired Beason & Nalley in 2008 to prepare Incurred Cost Submission

(ICS) reports that United Systems was required to submit in connection with a subcontract

that United Systems had on a federal government project. United Systems chose Beason &

Nalley for this work because Beason & Nalley held itself out as an expert in U.S. government

contracts and the preparation of reports and documents required in connection with such

contracts. Beason & Nalley prepared the ICS reports, but these reports erroneously deducted Cite as 2014 Ark. App. 534

certain costs that were not deductible pursuant to applicable regulations. United Systems

hired a different firm to correct the errors so that it could submit compliant ICS reports and

sued Beason & Nalley for breach of contract and negligence. Beason & Nalley moved to

dismiss on the pleadings for failure to state a claim, and the motion was granted. Because the

case had previously been dismissed, the second dismissal was with prejudice. See Ark. R.

Civ. P. 41(b).

In reviewing a trial court’s decision on a motion to dismiss under Ark. R. Civ. P.

12(b)(6), we treat the facts alleged in the complaint as true and view them in the light most

favorable to the party who filed the complaint. Hendrickson v. Carpenter, 88 Ark. App. 369,

199 S.W.3d 100 (2004). In testing the sufficiency of the complaint on a motion to dismiss,

all reasonable inferences must be resolved in favor of the complaint, and the pleadings are to

be liberally construed. Id. Our rules require fact pleading, and a complaint must state facts,

not mere conclusions, in order to entitle the pleader to relief. Id. We look to the underlying

facts supporting an alleged cause of action to determine whether the matter has been

sufficiently pled. Id.

Beason & Nalley moved for dismissal on three grounds: first, that United Systems’

claim for contract damages must fail because the damages sought were consequential, and the

contract demonstrated that there was no tacit agreement by Beason & Nalley to be liable for

consequential damages; second, that the indemnity clause of the contract barred United

Systems from bringing any claim against Beason & Nalley with respect to their contract or

its performance; and third, that no action against Beason & Nalley would lie because United

2 Cite as 2014 Ark. App. 534

Systems had admitted that the actions of Keith Reed, United Systems’ chief financial officer,

were the proximate cause for the submission of improper expenses on the ICS reports

prepared by Beason & Nalley. The trial court’s order did not specify the ground or grounds

on which the court based its order of dismissal, but the court nevertheless erred because none

of these arguments provide grounds for dismissal.

Direct or Consequential Damages

The distinction between direct and consequential damages was recently discussed in

Hobson v. Entergy Arkansas, Inc., 2014 Ark. App. 101, at 12–13:

The purpose of damages in a contract action is to place the injured party in the same position he would have been in had the contract been performed. Howard W. Brill, Law of Damages § 17:1 (5th ed. 2004); Acker Constr., LLC v. Tran, 2012 Ark. App. 214, 396 S.W.3d 279. The law makes a distinction between the general damages suffered in a breach-of-contract case and consequential damages. General damages are those that necessarily flow from the breach. Brill, supra § 4:2. Consequential damages refer to damages that are only indirectly caused by the breach—instead of flowing directly from the breach, they result from some of the consequences of the breach. Id.; Acker, supra.

Here, United Systems sought damages of $29,976.11 against Beason & Nalley, that

being the amount that United Systems paid another firm to correct the errors in the ICS

reports prepared by Beason & Nalley. There is no more natural and direct result of the

failure to perform under a contract than the reasonable cost of obtaining substituted

performance. Damages that seek to compensate a plaintiff for the value of the performance

promised are direct rather than consequential. 24 Richard A. Lord, Williston on Contracts §

64:12 (4th ed. 2002) (citing Schonfeld v. Hilliard, 218 F.3d 164 (2d Cir. 2000)). Beason &

3 Cite as 2014 Ark. App. 534

Nalley’s claim that the damages sought were other than direct is unsupported by either logic

or authority.

Indemnity Clause

It is possible to contract to indemnify an indemnitee for the indemnitee’s own

negligence, but a high standard is generally required before a contract will be so interpreted.

Restatement (Third) of Torts: Apportionment of Liability § 22 (2000).

[However,] agreements tending to erode common-law liability or relieving the contracting parties from penalties imposed for their improper conduct are not favored. The law expresses this disfavor either by indulging in a presumption against the parties’ intention to contract for immunity against the consequences of their own negligence, or by requiring that such a provision for immunity in a contract must be expressed in clear and unequivocal language to be valid and effective.

8 Richard A. Lord, Williston on Contracts § 19:19 (4th ed. 1998). In Arkansas, a party’s intent

to contractually obligate itself to indemnify another party for that second party’s own

negligence must be expressed in clear and unequivocal terms and to the extent that no other

meaning can be ascribed. Arkansas Kraft Corp. v. Boyed Sanders Construction Co., 298 Ark. 36,

764 S.W.2d 452 (1989).

The contract at issue contains the following indemnification clause:

United Systems of Arkansas, Inc. shall indemnify and hold harmless Beason & Nalley, Inc., and its personnel from and against any claims, liabilities, costs and expenses (including, without limitation, attorney’s fees and the time of Beason & Nalley, Inc.’s personnel involved) brought against, paid or incurred by Beason & Nalley, Inc. at any time and in any way arising out of or relating to Beason & Nalley, Inc.’s services under this proposal, except to the extent finally determined to have resulted from the gross negligence or willful misconduct of Beason & Nalley, Inc. personnel.

The language employed in this clause is broad. However, in jurisdictions adhering to the

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deck House, Inc. v. Link
249 S.W.3d 817 (Court of Appeals of Arkansas, 2007)
Pollard v. Union Pacific Railroad
54 S.W.3d 559 (Court of Appeals of Arkansas, 2001)
Wal-Mart Stores, Inc. v. Coughlin
255 S.W.3d 424 (Supreme Court of Arkansas, 2007)
Arkansas Kraft Corp. v. Boyed Sanders Construction Co.
764 S.W.2d 452 (Supreme Court of Arkansas, 1989)
Hendrickson v. Carpenter
199 S.W.3d 100 (Court of Appeals of Arkansas, 2004)
Kansas City Power & Light Co. v. Federal Construction Corp.
351 S.W.2d 741 (Supreme Court of Missouri, 1961)
Hobson v. Entergy Arkansas, Inc.
2014 Ark. App. 101 (Court of Appeals of Arkansas, 2014)
J.B. Hunt, LLC v. Thornton
2014 Ark. 62 (Supreme Court of Arkansas, 2014)
Acker Construction, LLC v. Tran
396 S.W.3d 279 (Court of Appeals of Arkansas, 2012)
Schonfeld v. Hilliard
218 F.3d 164 (Second Circuit, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
2014 Ark. App. 534, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-sys-of-ark-inc-v-beason-nalley-inc-arkctapp-2014.