United States v. Sabine Shell, Inc. And Badon Construction Co.

674 F.2d 480, 12 Envtl. L. Rep. (Envtl. Law Inst.) 20859, 17 ERC (BNA) 1671, 1982 U.S. App. LEXIS 19612, 17 ERC 1671
CourtCourt of Appeals for the Fifth Circuit
DecidedApril 30, 1982
Docket81-3368
StatusPublished
Cited by19 cases

This text of 674 F.2d 480 (United States v. Sabine Shell, Inc. And Badon Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Sabine Shell, Inc. And Badon Construction Co., 674 F.2d 480, 12 Envtl. L. Rep. (Envtl. Law Inst.) 20859, 17 ERC (BNA) 1671, 1982 U.S. App. LEXIS 19612, 17 ERC 1671 (5th Cir. 1982).

Opinion

ALVIN B. RUBIN, Circuit Judge:

Two of the parties to a consent decree with the Government seek to avoid enforcement of a provision in that decree requiring them to restore, in accordance with the Government’s plan, marshland that they have altered. Alternatively, they seek approval of their own plan on the basis that it is a better one, and they also seek discovery of the Government’s files to enable them to establish that their plan is better. The district court rejected these attempts to escape the consequences of the decree and enforced it. We affirm.

I

The United States brought an action against Sabine Shell, Inc. (“Shell”) and the contractor it employed, Badon Construction Co. (“Badon”), under 33 U.S.C. §§ 403, 1311, and 1319(d) (1976 & Supp. Ill 1979), seeking (1) an injunction prohibiting them from dredging, filling, and constructing levees in Sabine Lake and in adjoining marshland without the permit required for such activity; (2) an order compelling the restoration of these areas; and (3) civil penalties. Shell had obtained permission from John W. Mecom and Four M Properties, Ltd., to dredge a canal to an inland lake, to search there for shell deposits, and to deposit the spoil on the surface of the property owned by Mecom and Four M. Shell had engaged Badon to supply the labor and equipment for the task.

*482 The parties later signed a proposed consent decree, which was signed by the district judge, and then, on May 4, 1976, filed in the district court. The decree required Shell and Badon either to obtain a permit for the work or to restore the surface area to its pristine condition. Shell and Badon would not be required to do any restoration until they had applied for a permit. If, however, the permit were denied, Shell and Badon would “in a timely and expeditious manner secure approval of a restoration plan from the Department of the Army.”

Shell applied for a permit on May 10. Despite the Government’s insistence on expedition as a term of the consent decree, the Department of the Army did not act on the application until seventeen months later, when, in October 1977, it denied the application. Meanwhile, according to an affidavit submitted by Shell and Badon, in December 1976 Mecom and Four M conveyed title to this property to The John W. Mecom Company, a Texas corporation. In fashion almost as dilatory as the Army’s, Shell took nine months to submit a restoration plan, filing it both with the Army and the Clerk of Court in August 1978. The beat then began to quicken, but not precipitately, for the Government waited only seven months, until February 7,1979, to file its opposition to that plan in the record and suggest a plan of its own. On February 15, Shell and Badon filed a motion to stay submission and execution of the Government’s restoration plan. On May 28, 1981, after further court proceedings and attempts by the parties to reach an agreement on a restoration plan, the district court granted the Government’s motion to enforce the May 1976 consent decree. Shell and Badon appealed.

II

Shell and Badon filed their motion to stay the submission and execution of the Government’s restoration plan on the grounds, inter alia, that the Government’s plan , would require them to enter property owned by a third party, which they no longer had permission to do. They averred that, although the previous owners of this property had agreed to the initial work, the permits from the owners had expired. Moreover, as noted above, they offered evidence that these owners had since conveyed the title to this property to The John W. Mecom Company. To buttress their argument, Shell and Badon submitted an affidavit from an officer of that corporation stating that it has terminated Shell and Ba-don’s right to enter its property and will refuse to permit any further activity on it.

This issue is presented in a different light on appeal. Shell and Badon now contend that the Government should have joined the property owners as indispensable parties under Fed.R.Civ.P. 19(a). They question whether the district court may order the licensee of former property owners to restore the surface of the property without joining the present owner as a party defendant.

Shell and Badon failed to present this neat procedural question to the district court. Their failure, however, does not bar us from considering it on appeal. McCulloch v. Glasgow, 620 F.2d 47, 51 (5th Cir. 1980); Kimball v. Florida Bar, 537 F.2d 1305, 1307 (5th Cir. 1976); Haby v. Stanolind Oil & Gas Co., 225 F.2d 723, 724 (5th Cir. 1955) (per curiam). Nevertheless, we conclude that their contention lacks merit. Equitable considerations govern the disposition of a litigant’s argument that someone is an indispensable party. Toney v. White, 476 F.2d 203, 207 (5th Cir.), modified and aff’d en banc on other grounds, 488 F.2d 310 (5th Cir. 1973); Britton v. Green, 325 F.2d 377, 382 (10th Cir. 1963); Texas & N.O.R.R. v. City of New Orleans, 22 F.R.D. 84, 87 (E.D.La.1958). The equitable considerations in this case go against Shell and Badon.

In the proceedings below, Shell and Ba-don never tried to join the property owners as parties. Moreover, in the pretrial order, 1 they stated: “There are no claims of other parties.” When they proposed the consent *483 decree, it was apparent that any restoration would require reentry to the property and would affect its surface; 2 yet they did not raise the “absent property owners” issue in any way until three years later, when they filed their motion to stay submission and execution of the Government’s restoration plan. Furthermore, the property owners themselves, patently aware of this litigation, never intervened either at the district or appellate court level. Presumably the property owners do not believe that the disposition of this suit will “impair or impede” their ability to protect their interests. Fed.R.Civ.P. 19(a)(2)(i).

Finally, Shell and Badon’s failure to raise the issue of joinder until this appeal militates against a finding in their favor. Geis-ser v. United States,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Massachusetts v. Wampanoag Tribe of Gay Head
98 F. Supp. 3d 55 (D. Massachusetts, 2015)
United States v. San Juan Bay Marina
239 F.3d 400 (First Circuit, 2001)
Continental Casualty v. Rudd
Fifth Circuit, 1996
Flanagan v. Ahearn (In re Astestos Litigation)
90 F.3d 963 (Fifth Circuit, 1996)
In Re Asbestos Litigation
90 F.3d 963 (Fifth Circuit, 1996)
Burka v. Aetna Life Insurance
894 F. Supp. 28 (District of Columbia, 1995)
C.E. Alexander & Sons, Inc. v. DEC International, Inc.
811 P.2d 899 (New Mexico Supreme Court, 1991)
Giambelluca v. Dravo Basic Materials Co.
131 F.R.D. 475 (E.D. Louisiana, 1990)
Arnold v. Bl Intermediate Unit 17
843 F.2d 122 (Third Circuit, 1988)
Arnold v. BlaST Intermediate Unit 17
843 F.2d 122 (Third Circuit, 1988)
United States v. Edwards
667 F. Supp. 1204 (W.D. Tennessee, 1987)
Cooper v. Allustiarte
786 F.2d 910 (Ninth Circuit, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
674 F.2d 480, 12 Envtl. L. Rep. (Envtl. Law Inst.) 20859, 17 ERC (BNA) 1671, 1982 U.S. App. LEXIS 19612, 17 ERC 1671, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-sabine-shell-inc-and-badon-construction-co-ca5-1982.