United States v. Rapoca Energy Co.

751 F. Supp. 565, 1990 U.S. Dist. LEXIS 16122, 1990 WL 188739
CourtDistrict Court, W.D. Virginia
DecidedNovember 7, 1990
DocketCiv. A. 89-0035-A
StatusPublished
Cited by2 cases

This text of 751 F. Supp. 565 (United States v. Rapoca Energy Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Rapoca Energy Co., 751 F. Supp. 565, 1990 U.S. Dist. LEXIS 16122, 1990 WL 188739 (W.D. Va. 1990).

Opinion

MEMORANDUM OPINION

GLEN M. WILLIAMS, Senior District Judge.

The United States of America brought this action at the request of the Secretary of the Interior (hereinafter “the Secretary”), to recover abandoned mine reclamation fees under the provisions of the Surface Mining Control and Reclamation Act of 1977, 30 U.S.C. Section 1201 et seq. (hereinafter “the Act”), and the implementing regulations. Jurisdiction of the court is pursuant to 30 U.S.C. Section 1232(e) and 28 U.S.C. Section 1345. Both parties have filed motions for summary judgment under Rule 56 of the Federal Rules of Civil Procedure.

I.

Defendant, Rapoca Energy Company (hereinafter “Rapoca”), conducted surface coal mining and reclamation operations subject to the Act and commercially produced coal in Buchanan, Dickenson and Wise Counties, Virginia. Rapoca produced coal during the third and fourth calendar quarters of 1982 and during all calendar quarters of 1983, 1984, 1985 and 1986.

Section 402(a) of the Act, 30 U.S.C. Section 1232(a), requires all coal mine operators subject to the provisions of the Act to pay to the Secretary a reclamation fee of thirty-five cents per ton of coal produced by surface coal mining. Rapoca calculated this fee on the basis of “clean coal” and paid that sum to the Secretary. Plaintiff alleges that the calculations should have been made on the basis of “raw coal” and that, therefore, Rapoca did not pay the appropriate reclamation fee within thirty days following the conclusion of each of the calendar quarters. Plaintiff claims that, after crediting the amounts paid, Ra-poca still owes the Secretary the sum of $26,391.78 in delinquent reclamation fees, plus pre-judgment interest, late-payment penalties and administrative costs.

The Office of Surface Mining, United States Department of the Interior (hereinafter “OSM”), conducted a reclamation fee compliance audit of Rapoca’s Blackwatch Division for the period from July 1, 1982 to December 31, 1986 and of its Nora Division for the period from January 1, 1983 to December 31, 1986. In its audit report dated April 1, 1988, OSM stated, inter alia, that Rapoca did not compute its reclamation fees on the “actual gross weight” of the coal “prior to [its] sale or transfer” as required under 30 C.F.R. Section 870.12. In one instance, the report contends that during a period when Rapoca’s cleaning operation was temporarily suspended it computed its fees on the basis of the “clean coal” on which “Rapoca was paid” rather than on the “raw coal transferred”. In another instance, the report asserts that Rapoca “calculate[d] the clean tonnage by multiplying raw production by an estimate of the percentage recovered during the *567 preparation process.” The amounts calculated by Rapoca, according to the report, "do not represent the actual amounts sold.” The report claims that the gross weight of the amounts sold should have been the basis of the reclamation fees. It is these two instances to which Rapoca objects and which form the basis of Plaintiffs claim that Rapoca owes delinquent reclamation fees. As previously stated, plaintiff filed a motion for summary judgment, but Rapoca filed a cross-motion for summary judgment only on the first instance concerning the time when its cleaning operation was suspended.

During the last quarter of 1984 and the first three quarters of 1985, Rapoca temporarily suspended its preparation and cleaning operations. Rapoca shipped its “raw coal” to its customers’ cleaning facilities. The customers then cleaned the coal and paid Rapoca on the basis of “clean coal” although the records reflect that the amount of “clean coal” was only an estimation. In an affidavit submitted by Rapoca from Tom Wells, comptroller of Rapoca, Wells stated that during the period when Rapoca temporarily suspended its cleaning operations, “Rapoca determined the actual weight of the coal for which it was paid after cleaning based on a comparison of its coal sampling, daily weigh reports, coal purchase recap sheets and invoices or paid receipts from the customer. Based on this analysis, Rapoca was reasonably confident of the quality and nature of the coal it sold to its customers after cleaning because the clean tons arrived at and paid for by these customers was consistent with the quality of coal Rapoca knew each of the subject mines should be producing at that time.” He further indicated that it was not the practice in the industry to record the “actual” weights at a customer’s coal cleaning facility. This affidavit and the records show that Rapoca does not have documents that actually reflect the amounts of coal remaining after its customers cleaned the “raw coal” shipped to them by Rapoca. Rather, Rapoca and its customers used various items of data such as those outlined by Wells in his affidavit to calculate rather than actually weighing the tons of “clean coal” upon which Rapoca received payment. This sequence of events comprise the first instance outlined in the audit report.

The facts of the second instance in the audit report entail Rapoca’s calculating clean tonnage by multiplying its raw production times an estimate of the percentage of impurities recovered during the cleaning process. Simply stated, Rapoca was cleaning its own coal and subtracting from its clean tonnage the amount of moisture it estimated to be added to the coal during the cleaning operation. Rapoca then calculated its reclamation fees based on this revised tonnage of “clean coal”.

The court finds that all of these recited facts are material and not in dispute. Under Rule 56, summary judgment is appropriate when there are no genuine issues of fact. See Moore’s Federal Practice Section 56.04 at 56-60 (2d ed. 1990). For the reasons articulated below, the court grants summary judgment for the plaintiff.

II.

The controversy involving the coal mined by Rapoca when its cleaning operations were suspended concerns 30 C.F.R. Section 870.12. 1 This section provides that the rec *568 lamation fee to be paid by the operator “shall be determined by the weight and value at the time of initial bona fide sale, transfer of ownership, or use by the operator.” According to the section, “[t]he initial bona fide sale, transfer of ownership, or use shall be determined by the first transaction or use of the coal by the operator immediately after it is severed.... ” In calculating the weight of each ton, the “actual gross weight” is to be used and “[ijmpurities that have not been removed prior to the time of initial bona fide sale, transfer of ownership, or use by the operator ... shall not be deducted from the gross weight.” 2 The issue to be determined on this tonnage dispute turns upon the “time of initial bona fide sale”.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wyoming Board of Land Commissioners v. Antelope Coal Co.
2008 WY 60 (Wyoming Supreme Court, 2008)
SG Coal Co. v. Lujan
808 F. Supp. 1258 (W.D. Virginia, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
751 F. Supp. 565, 1990 U.S. Dist. LEXIS 16122, 1990 WL 188739, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-rapoca-energy-co-vawd-1990.