United States v. Newport News Shipbuilding & Dry Dock Co.

130 F. Supp. 159, 1955 U.S. Dist. LEXIS 3345
District Court, E.D. Virginia·Decided January 7, 1955·No. No. 152·Published·Cited by 4 cases

Opinion

HOFFMAN, District Judge.

Libellant, United States of America (as owner of the Steamship P & T Pathfinder, hereinafter referred to as “Pathfinder” or “vessel”, ex U. S. S. Dupage and otherwise known as USMC Hull No. •389), has instituted this action for indemnity, civil and maritime, against the respondent, Newport News Shipbuilding and Drydock Company, seeking to recover the sum of $14,691.53, plus interest and costs, alleged to be due by reason of claims paid by libellant to third parties arising out of cargo damage sustained on the first voyage of the vessel following its reconversion by respondent pursuant to a written contract with libellant.

There is little or no dispute with respect to the material facts of the case. Libellant rests its case on the exhibits attached to the libel, a stipulation filed October 5, 1954, admitted as evidence, and libellant’s Ex. No. 2 which is a “position description” relating the duties of one A. Claude, Chief, Inspection and Performance Division of the United States Maritime Commission, an agency of libellant. Respondent relies upon the testimony of Carl B. Penney, respondent’s assistant manager of ship repairs, together with the following exhibits briefly described:

Def. No. 1 — A letter from Pope & 'Talbot, Inc. (operators of the vessel under a service agreement from libellant), dated 9/5/47, relating to work performed following respondent’s delivery of the vessel to libellant, with attached sheet referring to Item No. 8 covering the corrective repair to that part of the vessel alleged to have been the primary cause of the damage here involved.

Def. No. 2 — A letter dated 3/19/48 from the Maritime Commission to respondent making claim in the sum of $543.87 covering corrections accepted by respondent as its responsibility, including Item No. 8 in the sum of $27 indicating repairs to that part of the vessel alleged to have been the primary cause of the damage here involved.

Def. No. 3 — A certificate of delivery of the vessel by respondent to libellant as of 5/5/47, said certificate of accep[161] tance by libellant containing the following language:

“Said vessel is hereby accepted under and pursuant to the terms of said contract for the reconversion of .said vessel, without waiver of any of the terms and conditions of same. Attached hereto is' a -list of items Ziot completed in accordance with the terms of said contract at the time of delivery”. (None)

Def. No. 4 — Certificate of Maritime Commission indicating delivery of vessel to Pope & Talbot, Inc., as of 5/5/47.

Def. No. 5 and No. 5A — Letter dated 9/29/48 from Maritime Commission to respondent indicating respondent’s reimbursement to Pope & Talbot, Inc. on guarantee liability, stating in part as follows:

“We therefore consider that you have no further guarantee liability on these vessels, and we are closing our records accordingly”.

Def. No. 6 — Letter dated 9/17/48 from respondent to Maritime Commission stating that respondent had reimbursed the owners for items of contractor’s guarantee liability.

From the testimony and exhibits adduced the facts appear to be substantially as hereinafter set forth. Following the termination of World War II the libellant sought to reconvert certain troop ships into cargo vessels. The respondent was awarded the contract for the Pathfinder, as well as three other vessels. Delivery for the purpose of reconversion was on December 13,1946, for completion within 90 days. The time limit was subsequently extended by agreement and no delay is involved herein. In accordance with the plans and specifications, respondent became obligated to remove and “blank-off” a 1%-inch waste line on the starboard side of the vessel. Respondent, in the course of reconversion, removed the 114-inch waste pipe, but failed to seal the line or “blank-off” the same by the insertion of a flange or welded insert. There were apparently between 150 to 200 similar pipes to be “blanked-off” on this particular job. While respondent denies any negligence or failure to complete the contract as per the plans and specifications, it admits that it has no evidence to contradict libellant’s evidence as revealed by the stipulation, and further concedes that it has no affirmative evidence indicating any tampering with the line or pipe following delivery by respondent to libellant on May 5, 1947. The Court therefore finds that the respondent failed to complete the contract as per the plans and specifications, and was negligent in such failure.

At the time of the delivery of the vessel on May 5, 1947, it was inspected by the respondent, the American Bureau of Shipping Inspectors, the U. S. Coast Guard Inspectors, the Maritime Commission Inspectors, and inspectors of Pope & Talbot, Inc., to whom the vessel was delivered by the Maritime Commission on the same day. Admittedly, no inspector noted the defect referred'to in the preceding paragraph.

Respondent urges that its liability was limited to the cost of repairs, i. e., $27, in accordance with Art. 19 of the contract between libellant and respondent, and that, further, the libellant had a duty of inspection. Respondent also urges that the Maritime Commission released respondent from all contractual liability (Def. Ex. 3, 5 and 5A) and hence cannot recover anything for its indemnity claim.

The pertinent portions of the contract are set forth as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Newport News Shipbuilding & Dry Dock Co., 130 F. Supp. 159, 1955 U.S. Dist. LEXIS 3345 (E.D. Va. 1955).

130 F. Supp. 159 (United States v. Newport News Shipbuilding & Dry Dock Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Parfait v. Swiftships, LLC
E.D. Louisiana, 2025
Daniel Construction Co. v. Welch Contracting Corp.
335 F. Supp. 303 (E.D. Virginia, 1971)