United States v. Neosho Construction Company, Incorporated

599 F.2d 930, 26 Cont. Cas. Fed. 83,388, 1979 U.S. App. LEXIS 14338
CourtCourt of Appeals for the Tenth Circuit
DecidedMay 31, 1979
Docket77-1881
StatusPublished
Cited by2 cases

This text of 599 F.2d 930 (United States v. Neosho Construction Company, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Neosho Construction Company, Incorporated, 599 F.2d 930, 26 Cont. Cas. Fed. 83,388, 1979 U.S. App. LEXIS 14338 (10th Cir. 1979).

Opinion

599 F.2d 930

26 Cont.Cas.Fed. (CCH) 83,388

The UNITED STATES of America for the Use and Benefit of
OLMSTED ELECTRIC, INC., a corporation, Plaintiff-Appellee,
v.
NEOSHO CONSTRUCTION COMPANY, INCORPORATED and the Travelers
Indemnity Company, Defendants-Appellants.

No. 77-1881.

United States Court of Appeals,
Tenth Circuit.

Argued and Submitted Nov. 14, 1978.
Decided May 31, 1979.

John L. Richeson, Ottawa, Kan. (Anderson, Byrd & Richeson, Ottawa, Kan., on brief), for plaintiff-appellee.

Larry G. Pepperdine, Topeka, Kan. (Fisher, Patterson, Sayler & Smith, Topeka, Kan., and David H. Heilman, Council Grove, Kan., on brief), for defendants-appellants.

Before McWILLIAMS, DOYLE and LOGAN, Circuit Judges.

McWILLIAMS, Circuit Judge.

This is a Miller Act case and the issue is whether the supplier gave timely notice to a general contractor of its claim against a subcontractor. The supplier brought suit against the general contractor and its surety under the provisions of the Miller Act for materials which it had furnished a subcontractor and for which payment had not been received. Both the supplier and the general contractor moved for summary judgment.

It was the general contractor's position that, under the undisputed facts, the supplier's action was barred because of the failure of the supplier to give timely notice as required by 40 U.S.C. § 270b(a). It was the supplier's position that it had given the general contractor the notice required by that statute. The trial court granted the supplier's motion for summary judgment and denied the motion of the general contractor. Judgment was then entered in favor of the supplier and against the general contractor and its surety in a stipulated amount. The general contractor and its surety seek reversal of that judgment.

Neosho Construction Company entered into a contract with the Corps of Engineers whereby Neosho, as the general contractor, agreed to construct certain projects at Melvern Lake, in Kansas. Neosho, as the principal, and Travelers Indemnity Company, as surety, executed a payment bond to the United States.

Neosho entered into a subcontract with Donald Eugene Masten whereby Masten agreed to perform certain electrical work on the Melvern project. Masten, in turn, over a considerable length of time, purchased electrical supplies for the project from Olmsted Electric, Inc. Specifically, Olmsted's first sale of materials to Masten for use on the Melvern job was on September 24, 1973. Periodic purchases were made and periodic payments were made from September, 1973, until September, 1974, so that, as of September, 1974, Masten's account with Olmsted was current. However, between August 30, 1974, and April 18, 1975, Olmsted made some fourteen sales to Masten of electrical supplies which were used on the Melvern Lake project, and for which Olmsted did not receive payment.

Sometime in June, 1975, Masten ordered a "fuse disconnect" from Olmsted which was to be used on the Melvern project. Olmsted in turn placed an order for a fuse disconnect from its manufacturer. It would appear that Masten was experiencing severe financial problems and that at about this point in time apparently ceased working on the Melvern Lake project. Masten later took bankruptcy. Be all that as it may, on July 21, 1975, one Ron Montieth, an employee of Neosho, in a telephone conversation with Lee Olmsted, President of Olmsted Electric, Inc., verified that the fuse disconnect had in fact been ordered by Masten, and inquired about the possible delivery date for the disconnect.* As a follow-up to their telephone conversation, Lee Olmsted wrote Ron Montieth on that same day, stating that he would call Montieth when the disconnect was received. In that same letter, Olmsted advised Montieth that, as of that date, Masten owed Olmsted $26,065.23 and acknowledged that Montieth had told him that Neosho had paid Masten in full.

By letter of July 28, 1975, Montieth replied to Olmsted's letter of the 21st. In that reply, Montieth stated that "(t)he purpose of my telling you that Don Masten was not due any money from Neosho Construction Company, Inc., was to warn you so that you could prevent the possible over extension of credit to Don's Electric Service." In that same letter, Montieth also stated that Neosho was not assuming any liability for Masten's indebtedness to Olmsted and asked that he be advised as soon as the fuse disconnect was received.

On August 13, 1975, a Neosho employee picked up the fuse disconnect at Olmsted's shop. The sales slip for the disconnect was made out to Neosho, and about a week later Neosho paid Olmsted the sum of $332.50, the amount of the invoice covering the disconnect.

On September 24, 1975, Olmsted gave Neosho notice under 40 U.S.C. § 270b(a). That statute provides as follows:

(a) Every person who has furnished labor or material in the prosecution of the work provided for in such contract, in respect of which a payment bond is furnished under section 270a of this title and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which such claim is made, shall have the right to sue on such payment bond for the amount, or the balance thereof, unpaid at the time of institution of such suit and to prosecute said action to final execution and judgment for the sum or sums justly due him: Provided, however, That Any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or Furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. Such notice shall be served by mailing the same by registered mail, postage prepaid, in an envelope addressed to the contractor at any place he maintains an office or conducts his business, or his residence, or in any manner in which the United States marshal of the district in which the public improvement is situated is authorized by law to serve summons. (Emphasis added.)

Paraphrasing the statute above quoted, a supplier or materialman who has a contractual relationship with a subcontractor but none with the prime contractor, shall have a right of action on the payment bond for his claim against the subcontractor Provided he gives written notice in the manner described in the statute within ninety days from the date the supplier furnished or supplied the last of the material for which such claim is made. As above noted, Olmsted gave written notice to Neosho on September 24, 1975. Attached to the notice was a ledger sheet reflecting deliveries of materials by Olmsted to Masten for which payment had not been made.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
599 F.2d 930, 26 Cont. Cas. Fed. 83,388, 1979 U.S. App. LEXIS 14338, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-neosho-construction-company-incorporated-ca10-1979.