United States v. Murphy Oil USA, Inc.

155 F. Supp. 2d 1117, 2001 WL 874145
Procedural entryThis page is a short order in United States v. Murphy Oil USA, Inc.. Read the opinion of the Court — 143 F. Supp. 2d 1054
District Court, W.D. Wisconsin·Decided August 8, 2001·No. 00C0409-C·Published

Opinion

OPINION AND ORDER

CRABB, Chief Judge.

Plaintiff United States of America is suing defendant Murphy Oil USA, Inc. for alleged violations of environmental laws. Primarily, plaintiff alleges that defendant made major modifications to the sulfur recovery unit at its Superior, Wisconsin oil refinery without obtaining permits required under the Clean Air Act, 42 U.S.C. §§ 7401-7671q, without complying with performance standards applicable to the work and without employing the best available control technology. Defendant denies any failure to comply. It maintains that all of the improvements it made to its sulfur recovery unit were motivated by the need to meet state and federal air quality standards and were undertaken in close cooperation with the Wisconsin Department of Natural Resources, the authority responsible for issuing Clean Air Act permits in Wisconsin. Plaintiff does not dispute defendant’s assertion that its projects were intended to improve its pollution control efficiency or that defendant followed the state’s directives. Rather, plaintiff contends that defendant avoided compliance by withholding critical information from regulators that would have indicated that its proposed modifications would trigger application of various regulations and permit requirements. Plaintiff is suing for the withholding of the information as well as for the penalties and injunctive relief available upon a showing that an operator modified a regulated pollution source without compliance with the provisions of the act. Besides the alleged Clean Air Act violations, plaintiff has alleged that certain acts and omissions of defendant violated various provisions of the Clean Water Act, 33 U.S.C. §§ 1251-1387, and the Resource Conservation and Recovery Act, 42 U.S.C. §§ 6021-6039e.

Before trial, the case was pared down slightly as a result of motions for partial summary judgment that led to findings in favor of plaintiff on some of its claims and in favor of defendant on one of its affirmative defenses, see Opin. and Order entered on May 18, 2001. It was trimmed further after plaintiff withdrew some of the 24 claims it had alleged originally, including all of the claims it had raised under the Emergency Planning and Community Right-to-Know Act, 42 U.S.C. §§ 6991-6991h. Trial to the court proceeded on the remaining claims and affirmative defenses June 7-16, 2001.

The bulk of trial time was devoted to plaintiffs four remaining Clean Air Act claims. The first is that defendant made major modifications to the sulfur recovery unit at its oil refinery in 1987-88 and in 1991-93 and that each project resulted in a net emissions increase of sulfur dioxide of more than 40 tons a year, obligating defendant to obtain a Prevention of Significant Deterioration permit. Plaintiff seeks an order prohibiting defendant from continuing to operate the sulfur recovery unit without obtaining a Prevention of Significant Deterioration permit and a civil penal *1122 ty for making modifications to the sulfur recovery unit without the required permit.

In claim two, plaintiff seeks to enjoin defendant from operating its sulfur recovery unit without using best available control technology and to collect a civil penalty from defendant for making modifications to the unit without complying with this requirement of the Clean Air Act.

Plaintiffs third claim is that defendant did not provide all the relevant information plaintiff needed in order to determine whether the modifications defendant proposed to make in 1993 (routing its No. 2 distillate unifier into the sulfur recovery unit) would result in a significant increase in emissions from the sulfur recovery unit. Defendant admits that it withheld certain consultant reports but denies that anything in these reports was relevant, in the sense that it would have affected the permitting authority’s decision making. If defendant is correct, plaintiff will be prevented by operation of the applicable statute of limitations, 28 U.S.C. § 2462, from pursuing its demand for penalties against defendant on the first and second claim as they relate to the modifications that defendant made to the distillate unifier in 1992-93 because I have held that the statute of limitations may be tolled only if plaintiff proves that defendant made affirmative efforts to withhold relevant documents, that is, that defendant withheld documents knowingly and intentionally. (Plaintiff does not argue that defendant withheld relevant information in connection with the modifications it made before 1992; it concedes that the statute of limitations bars it from seeking penalties against defendant for making those modifications without obtaining a Prevention of Significant Deterioration permit.)

Plaintiffs third claim involves information provided by engineering consultants defendant hired at various times to suggest ways of making the sulfur recovery plant operate more efficiently. The information at issue includes the following: 1) reports prepared in 1987 by Sulfur Operations Support, a consulting firm, that include the consultants’ statement about the efficiency of the sulfur recovery unit before construction began in 1987, projected rates of efficiency after construction and references to the need for a larger combustion chamber; 2) reports from a firm known as Western Research that describe four stack tests and a material balance or performance test the firm conducted during 1989; and 3) reports from Becker, Losier & Associates that were prepared in 1989 and 1992 and discuss estimated recovery efficiency. Plaintiff contends that in addition to the consultants’ reports, defendant should have given the permitting authority information relating to a questionable stack test. The withholding of information claim can be reduced to two questions: whether the reports contain information that would have affected the permitting authority’s decision making and whether defendant would have had reason to know that it should have submitted the reports.

Plaintiffs fourth claim is based on its contention that since the completion of defendant’s modifications in the early 1990’s, the sulfur recovery unit has had the capacity to process more than 20 long tons a day of sulfur, that is, the unit’s “throughput” capacity has exceeded 20 long tons a day of sulfur. If plaintiff is correct, the unit has been subject to New Source Performance Standards, which would require defendant both to limit its sulfur dioxide emission concentration from the sulfur recovery unit to the standard set out in 40 C.F.R. § 60.104(a)(2) and to install an emissions control system to limit the sulfur dioxide concentration. Defendant denies that its sulfur recovery unit can process more than 20 long tons a day of sulfur and *1123 contends that even if the unit has done so on a few occasions, it was never designed to do so and cannot do so safely without risk of harm to its component parts.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Murphy Oil USA, Inc., 155 F. Supp. 2d 1117, 2001 WL 874145 (W.D. Wis. 2001).

155 F. Supp. 2d 1117 (United States v. Murphy Oil USA, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related