United States v. Murdock MacHine and Engineering Company of Utah, Logan A. Bagley, Trustee for Murdock MacHine and Engineering Company of Utah

81 F.3d 922
CourtCourt of Appeals for the Tenth Circuit
DecidedJune 5, 1996
Docket95-4071
StatusPublished
Cited by75 cases

This text of 81 F.3d 922 (United States v. Murdock MacHine and Engineering Company of Utah, Logan A. Bagley, Trustee for Murdock MacHine and Engineering Company of Utah) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Murdock MacHine and Engineering Company of Utah, Logan A. Bagley, Trustee for Murdock MacHine and Engineering Company of Utah, 81 F.3d 922 (10th Cir. 1996).

Opinion

BALDOCK, Circuit Judge.

Cases governed by the Bankruptcy Act of 1898, 11 U.S.C. §§ 1-1103 (1976) (repealed) (“the Act”) and the former Bankruptcy Rules, 11 U.S.C. appx. (1976) (superseded in 1983), are, like cowboys, a vanishing breed. We deliver in this case one of the final parting shots under the Act and former Rules. 1 We hold that in proceedings under Chapter VII of the Act, the United States government enjoys sovereign immunity from the automatic stays imposed by former Rules 401 and 601 because Congress did not waive the government’s sovereign immunity in the Act. Accordingly, we reverse the decision of the district court and remand.

I. Background

A. Contract Awards & Terminations

In June 1971, the government awarded Murdock Machine and Engineering Company of Utah (“Murdock”) a multi-year, $10.6 million, fixed-price contract to supply anti-submarine rocket launchers (“ASROC launchers”) to the Department of the Navy (“the ASROC contract”). Murdock did not timely produce the ASROC launchers, however, due to financial and production problems. Concerned with the production delay, the Navy Procuring Command (“NPC”) and Naval Sea Systems Command (“NAVSEA”) met with Murdock, and agreed to provide Murdock a $2.5 million government-guaranteed loan from the Commercial Security Bank of Ogden, Utah (“Murdock’s Bank”). NAVSEA also assured Murdock that it could apply for additional financial assistance under the extraordinary contractual relief provisions of Public Law No. 85-804, 50 U.S.C. §§ 1431-36 (“P.L.85-804”) if the $2.5 million guaranteed loan proved to be insufficient. See 50 U.S.C. §§ 1431-36 (granting agency head authority to provide extraordinary relief to a contractor when a contract is deemed essential to the national defense).

The government then awarded Murdock five additional fixed-price contracts — the contracts at issue in this appeal — including an: (1) Army contract for supply of Rocket fin and nozzle assemblies; (2) Army contract for construction of delay plungers; (3) Air Force contract for construction of practice bombs; (4) Navy contract for construction of Zuni launchers; and (5) Navy contract for construction of A/B dispensers (hereinafter collectively referred to as “the Non-ASROC contracts”). Each contract contained a standard “default” clause and “disputes” clause. See 48 C.F.R. §§ 52.249-8, 52.249-2. The default clause provided that if the government’s default termination was proper, the government could recover from the contractor its excess costs of reprocurement, unliq- *926 uidated progress payments, and other damages. The default clause provided farther, however, that if the government’s default termination was improper, (e.g., if the contractor’s default was excusable because it was beyond its control), the government would not be entitled to recover the above and, in turn, the government could potentially be liable to the contractor under the “termination for convenience” clauses of the Non-ASROC contracts. 2 The disputes clause provided that:

(A) Except as otherwise provided in this contract, any dispute concerning a question of fact arising under this contract which is not disposed of by agreement shall be decided by the Contracting Officer.... The decision of the Contracting Officer shall be final and conclusive unless, within thirty days from the date of receipt of such copy, the Contractor mails or otherwise furnishes to the Contracting Officer a written appeal addressed to the Secretary [or his duly authorized representative — the Armed Services Board of Contract Appeals (“ASBCA”) ].

With the funds from the guaranteed loan, Murdock continued performance on the AS-ROC contract and began performance on the Non-ASROC contracts. Murdock again encountered financial and production problems, and in August 1974 submitted a Request for Extraordinary Contractual Relief under P.L. 85-804. In its Request, Murdock explained that its total probable completion costs for the ASROC contract would be $20 million and asked the Navy to convert the $10.6 million fixed-price ASROC contract into a cost-reimbursement contract with a $22 million ceiling. 3 NAVSEA recommended that the Navy Contract Adjustment Board (“NCAB”) grant Murdock P.L. 85-804 relief. 4 In April 1975, NCAB granted Murdock P.L. 85-804 relief and converted the ASROC contract to a cost-reimbursement contract with a $22 million ceiling.

Thereafter, NAVSEA learned that it could obtain ASROC launchers from another source. NAVSEA immediately informed Murdock and NCAB that it was withdrawing its recommendation for P.L. 85-804 relief. The Navy then informed Murdock that it would not convert the ASROC contract to a cost-reimbursement contract and that Mur-dock had ten days to cure its delinquent ASROC delivery schedule or face default termination. Murdock apparently did not cure, and on May 16,1975, a Navy contract officer terminated the ASROC contract for default. The Navy authorized Murdock’s bank to call the guaranteed loan, and cut off progress payments to Murdock.

Seven days after the Navy terminated the ASROC contract, on May 23, 1975, Murdock filed a voluntary petition for relief under Chapter VII of the Act in the District of Utah. 5 By operation of law, the automatic stay provisions of Rules 401(a) and 601(a) immediately went into effect. See Bankruptcy Rules 401(a), 601(a) (“The filing of a petition shall operate as a stay.”). After the bankruptcy court adjudicated Murdock a bankrupt, but prior to the running of the sixty-day period allowed under § 70(b) of the Act for the Trustee to assume or reject exec-utory contracts, the Army, Air Force, and *927 Navy unilaterally terminated the Non-AS-ROC contracts for default. See Bankruptcy Act of 1898, § 70(b) (“The trustee shall assume or reject an executory contract ... within sixty days after the adjudication.”). Murdock timely appealed the Navy’s default termination of the ASROC contract to the ASBCA. Murdock did not, however, appeal the government’s terminations of the Non-ASROC contracts to the ASBCA.

While Murdock’s appeal of the Navy’s default termination of the ASROC contract was pending before the ASBCA, between September and November 1975, the government filed proofs of claim against Murdock’s bankruptcy estate. Claim 559A sought $3,865,-673.65 for unliquidated progress payments and excess reprocurement costs under the Non-ASROC contracts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
81 F.3d 922, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-murdock-machine-and-engineering-company-of-utah-logan-a-ca10-1996.