United States v. Monongahela Bridge Co.

160 F. 712, 1908 U.S. Dist. LEXIS 89
District Court, W.D. Pennsylvania·Decided January 7, 1908·Published·Cited by 1 cases

Opinion

ARCHBALD, District Judge*

(after stating the facts as above). This is an information, under the act of Congress of March 3, 1899, § 18, 30 Stat. 1153 (U. S. Comp. St. 1901, p. 3545), against the defendant company for a refusal to make the changes ordered by the Secretary of War in its bridge across the Monongahela river at Brownsville, Pa., 50 miles above the city of Pittsburg. This bridge was built in 1832, under a charter from the state of Pennsylvania, and is located on the line of the Old National Pike, laid out by the federal government in 1807, to give better access to the then distant parts of what is now the Middle West. It closes the gap in the road made by the river, the necessities of travel before that being met by a ferry, and after its construction the ends of the road leading to the ferry were relocated, so as to connect with the approaches to the bridge, which was thus adopted and made an integral part of the thoroughfare. It was built at a cost of from $65,000 to $75,000 and is still in good preservation, and if undisturbed would probably last for 20 years more. It is a toll bridge and the net returns amount to about $10,000 a year, but the changes which have been ordered by the Secretary of War will compel the tearing down of the whole structure, with the loss of all that it represents, and the building of a new bridge (if the franchise is to be preserved) at an estimated additional expenditure of $112,000. There is a large and increasing use of the Monongahela by reason of the mineral and other developments on its upper reaches, but it is effected artificially, by means of slack-water navigation, secured by locks and dams, through which it is connected' with the Ohio at Pittsburg and so brought in touch with the general interior system.of waterways of the Ohio and Mississippi basins. At the time the bridge was built, while the river had been declared to be a navigable stream by the Legislatures of both of the states through which it runs, except for flat bottom boats and rafts, and in times of high water, the navigation of it was very limited, and in dry times, according to the weight of the evidence, practically none at all. Not [721] until 1836, some four years after the bridge was built and in use, was the Monongahela Navigation Company incorporated, for the purpose of improving the river by the artificial means now employed, and not until 18-10 or 1841 were the first dams actually built, slack water being extended up as far as Brownsville, on the lower side of the bridge, in 18-!-i. At the same time, even before the bridge was erected, the improvement of the Monongahela by slack-water navigation was undoubtedly in contemplation, surveys to that end having been independently made by engineers of the state and of the national government. Upon this showing the jury were instructed that the right of the Secretary of War, acting under the authority conferred upon him by Congress to require the changes which had been ordered in the bridge, even though it necessitated its entire demolition, was not open to question ;• but that, in view of the serious results to the company, amounting to a deprivation of it of its property, it was protected by the constitutional provision that private property shall not be taken without just com - pensation being first made, which the company could demand before being required to comply, and should therefore be acquitted, unless the stream at the time the bridge was located upon it was in fact navigable, or the artificial improvement of it which has since been prosecuted, by which the changes in the structure of the bridge were made necessary, was reasonably to be apprehended; in either of which cases the company could not ask for compensation and should be found guilty. The jury having found a verdict in favor of the government, the question is as to the propriety of the instructions which were so given.

Preliminary to that, however, two points are raised which require brief consideration: (1) That the verdict as rendered is defective in form and inconclusive; and (2) that nothing was said to the jury as to the right of the defendant to the benefit of a reasonable doubt, to which it was entitled, the case being a criminal one. The first of these seems to have been suggested by the recent case of Pressed Steel Car Co. v. Steel Car Forge Co., 149 Fed. 182, 79 C. C. A. 130. But the two cases are very different. The difficulty there was that the jury failed to declare whether they found for the plaintiff or the defendant, simply stating that they sustained the validity of the contract sued upon and fixed the damages at a sum named. But here they say, in so many words, that they “find a verdict of guilty”; as to which it is not easy to see how anything could be more positive or certain. Nor is the other matter more serious. The obvious answer to it is that not only was there no request for an instruction as to the effect of a reasonable doubt, but that no exception was taken to the failure to give it. Had there been, it would have enabled the court to at once make the necessary correction as would have undoubtedly been done, and without that, the case being a misdemeanor, the omission must be regarded as immaterial. By the neglect to except at the time, the defendants virtually gave the court to understand that to this extent at least the charge was satisfactory, suggesting that the stress laid upon it, now that the case has gone against them, is an afterthought, if not indeed a catching at straws.

Free access — add to your briefcase to read the full text and ask questions with AI

United States v. Monongahela Bridge Co., 160 F. 712, 1908 U.S. Dist. LEXIS 89 (W.D. Pa. 1908).

160 F. 712 (United States v. Monongahela Bridge Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Raffour v. United States
284 F. 720 (Ninth Circuit, 1922)