United States v. Marietta Manufacturing Co.

268 F. Supp. 176, 1967 U.S. Dist. LEXIS 8914
CourtDistrict Court, D. West Virginia
DecidedMay 18, 1967
DocketCiv. A. No. 2173
StatusPublished
Cited by4 cases

This text of 268 F. Supp. 176 (United States v. Marietta Manufacturing Co.) is published on Counsel Stack Legal Research, covering District Court, D. West Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Marietta Manufacturing Co., 268 F. Supp. 176, 1967 U.S. Dist. LEXIS 8914 (wvad 1967).

Opinion

CHRISTIE, District Judge:

This is an action by the United States to recover certain costs ($1,567,194.94) allegedly incurred as a result of defendant Marietta Manufacturing Company’s default under contract No. MA-3156, calling for the construction of two ships for the Department of Commerce, Maritime Administration, for the performance of which defendant The Travelers Indemnity Company became surety and guarantor. The excess costs in question were necessitated by Marietta’s alleged failure to timely perform and the reletting of the work to another concern. Plaintiff has presently moved the Court, pursuant to Rule 56(a), Federal Rules of Civil Procedure, 28 U.S.C.A. p. 302, for partial summary judgment on the question of liability. We deny the motion.

FACTUAL BACKGROUND

On November 19, 1962, the Maritime Administration entered into a contract with Marietta for the construction of two hydrographic surveying ships, the consideration for which was $6,822,458.00. Pertinent contract provisions (Articles 29, 30 and 35) are found in the appendix. Delivery was to have been made by November 18, 1964 and March 18, 1965. By an addendum dated July 1, 1963, the delivery dates of the vessels were extended to February 18, 1965 and April 18, 1965.

On October 1, 1963, a strike occurred at Marietta’s yard, lasting until February 8, 1964. After work resumed, progress was slow and on July 24,1964, L. C. Hoffman, Chief, Office of Ship Construction (hereinafter referred to as Chief), advised Marietta by letter that the progress on two ships was unsatisfactory and requested Marietta to submit certain data within fourteen days following receipt of the letter. Under Article 5 of the contract, Marietta was entitled to extensions because of delays caused by strikes. At Marietta’s request, certain extensions were granted, but not for the time requested.

On September 15,1964, J. W. Glick, the then Acting Maritime Administrator, notified Marietta that, due to “inadequate working capital and reduction of labor force” and its lack of diligence, its progress on the contract was unsatisfactory, declared it to be in default and gave it fifteen days from the receipt of the no[178]*178tice within which to remedy the situation. On the same day, however, the Chief advised Marietta that as a result of the strike they would be allowed an extension of 132 days for the delivery of each vessel. Marietta replied to the September 15, 1964 notice of default by telegram on October 2, 1964, stating that the conclusions therein were unjustified and requesting a minimum extension of 455 days to deliver each of the vessels.

By telegram on October 7,1964, Nicholas Johnson, Maritime Administrator, requested Marietta to submit additional data in order that they might have all relevant information before proceeding under Articles 29 and 30 (the default clauses) of the contract. By letter dated October 30, 1964, Marietta declined to send the requested information because of the fact that the stated purpose of the October 7, 1964 telegram was to gather information to proceed under the contract’s default clauses, and further, because the Maritime Administration had had a full-time representative at the yard and was aware of all “facts concerning the causes of delay in production.”

On November 10, 1964, the Chief advised Marietta that 193 days of additional time for delivery of each vessel was being allowed because of the strike. Marietta had requested 455 days. The revised delivery dates were August 30, 1965 and October 28,1965. The letter also notified Marietta that it had 30 days in which to appeal this determination; gave instructions for perfecting appeal a.nd advised that the Administrator was the proper authority to hear it. Strange, however, before time for appeal had expired, the Chief, eight days later, on November 18, 1964, advised Marietta by letter that he had on that day determined (1) that it had not used diligence in the performance of the contract; (2) that its financial condition was such as to render it impossible for it to fulfill its obligations under the contract; and (3) that it had failed to employ sufficient manpower since settlement of the strike. The Chief concluded his letter by saying, “This is my final decision in this matter.” His letter also advised Marietta that it had 30 days under Article 35 of the General Provisions of the contract in which to appeal and that the Administrator was the authority to hear and determine the appeal. Notice of appeal was given by Marietta on December 7, 1964 with regard to the 193-day extension, and on December 16, 1964 with regard to the default. Article 35 provides that such appeals should be addressed to the Administrator and that the contractor shall be afforded an opportunity to be heard before the Administrator or his representative. However, notwithstanding the Chief’s letters notifying Marietta that it had 30 days to appeal both determinations, and notwithstanding Marietta’s clear right under Article 35 to present evidence and to be heard before the Administrator, the Administration, on November 18, 1964 (the same day the Chief had determined Marietta to be in default) advised Marietta by letter that,

“The Chief, Office of Ship Construction, Maritime Administration, under the provisions of Article 35 of the General Provisions of Contract No. MA-3156, has this day determined that certain events of default have occurred under the provisions of Contract No. MA-3156.
“On the basis of a review of this matter, I have determined that ‘events of default’ have occurred * * *.
“Accordingly, under the provisions of Article 30 of the General Provisions of Contract No. MA-3156, the Maritime Administration hereby terminates Contract No. MA-3156 by reason of such events of default.”

Thus, it appears that Marietta was deprived of its rights under Article 35 of the contract to present evidence before, and to be heard by, the Administrator before he acted upon and gave approval to the Chief’s decision that “events of default” had occurred.

Marietta, being aggrieved by this precipitous action by the Administrator, gave timely notice of appeal therefrom. The Chief, on December 29,1964, advised [179]*179Marietta that the November 18 decision of the Administrator, purporting to have been a review of the Chief’s decision of the same date, was a dispute within the meaning of Article 35 of the contract and as such, was subject to review by him (the Chief) and that it would be reviewed by him and a final decision issued on the matter. Thereafter, on January 26,1965, the Chief upheld the November 18 decision of the Administrator and advised Marietta that it might appeal within 30 days to the Administrator. This circuitous and seemingly nonsensical procedure quite understanding^ vexed and frustrated Marietta, and by letter of February 15, 1965, it gave vent to its feelings and intentions in this fashion:

“It was and is our position that Maritime Administration illegally and wrongfully terminated our contract and that its action in so doing constituted a breach of that contract. The position of the parties became fixed as a result of the action taken in the letter of Mr. Johnson dated November 18th, in conjunction with the actions of the Administration in making public announcement thereof and issuing the invitations to bidders. The determination of the merits of our respective positions will ultimately be for the courts.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Marietta Manufacturing Co.
53 F.R.D. 390 (S.D. West Virginia, 1971)
American Maritime Ass'n v. Stans
329 F. Supp. 1179 (District of Columbia, 1971)
S & E Contractors, Inc. v. The United States
433 F.2d 1373 (Court of Claims, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
268 F. Supp. 176, 1967 U.S. Dist. LEXIS 8914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-marietta-manufacturing-co-wvad-1967.