UNITED STATES v. MacDONALD CONSTRUCTION COMPANY

417 F.2d 687, 1969 U.S. App. LEXIS 10356
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 21, 1969
Docket19500_1
StatusPublished
Cited by2 cases

This text of 417 F.2d 687 (UNITED STATES v. MacDONALD CONSTRUCTION COMPANY) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
UNITED STATES v. MacDONALD CONSTRUCTION COMPANY, 417 F.2d 687, 1969 U.S. App. LEXIS 10356 (8th Cir. 1969).

Opinion

417 F.2d 687

UNITED STATES for the Use of PLANET CORPORATION, a Michigan Corporation, Appellant,
v.
MacDONALD CONSTRUCTION COMPANY, a Missouri Corporation, and The Travelers Indemnity Company, a Connecticut Corporation, Appellees.

No. 19500.

United States Court of Appeals Eighth Circuit.

October 21, 1969.

Kenneth Laing, Jr., of MacLean, Seaman & Laing, Lansing, Mich., for appellant; Terrence L. Croft, of Coburn, Croft, Kohn & Herzog, St. Louis, Mo., on the brief.

Ralph C. Kleinschmidt, of Evans & Dixon, St. Louis, Mo., for appellee Travelers Indemnity Co.

William C. Dale, Jr., of Biggs, Hensley, Curtis & Biggs, St. Louis, Mo., for appellee MacDonald Const. Co.

Before MATTHES, GIBSON and BRIGHT, Circuit Judges.

FLOYD R. GIBSON, Circuit Judge.

This is an appeal in a Miller Act (40 U.S.C. § 270b) case by the plaintiff Planet Corporation against defendants MacDonald Construction Company and The Travelers Indemnity Company. MacDonald was the prime contractor for the United States for the construction of the monumental Gateway Arch in St. Louis, Missouri. Travelers was surety for MacDonald. Planet subcontracted with MacDonald to perform all of the work required in Section 10 of the Specifications of the prime contract with the United States.

The dispute centers on electrical installations, wirings and controls that Planet claims were furnished by it over and beyond the requirements of its subcontract with MacDonald. An amended claim is made for $88,000. The case was tried to the Court,1 The Honorable James H. Meredith, who in an unreported decision held the subcontract was unambiguous and denied any extra compensation to Planet, and entered judgment accordingly. Planet filed a timely appeal. We affirm.

Since a resolution of the issues raised in this case depends upon an interpretation and construction of the subcontract and related contracts, it is necessary to set out at length the factual situation.

Planet for a consideration of $725,700 subcontracted with MacDonald in August 1962 to complete all of the work required by Section 10 of the prime contract. Section 10 covered the furnishing and installation of the passenger-conveyance trains for the Arch. The passenger-conveyance trains consisted of two trains of eight cars or capsules each, with five passenger seats in each capsule. One train ran in each leg of the Arch from the base of the Arch to the observation area at the top of the Arch, a distance of some 700 feet. Each train has terminals at both the bottom and top of the Arch. Each terminal has eight entrance doors, one for each capsule, which in turn has an electrically operated capsule door. The trains operate electrically by means of cables and hoist motors and all doors, door operating mechanisms, speed and safety mechanisms, switching, starting, stopping, leveling and power mechanisms operate by electricity as do all train components throughout the full distance of the trains' run. Control connections are made with the components of the system throughout the entire traverse of the trains' run.

The subcontract provided in Article 1:

"(A) General

"It is the intent of this Sub-Contract that the subcontractor complete all work required by that section of Contract Specifications entitled `Section 10 — Passenger Conveyances — trains' and/or as shown on the contract drawings, as said drawings refer to Passenger Conveyances trains.

"(B) Subcontractors Responsibility

"1) Subcontractor shall furnish all labor, material, hoisting facilities and/or equipment required to install complete all of the work described in A above.

"2) This Sub-Contract shall include any and all electrical work required to complete the installation of the passenger train system in complete accordance with the intent of the contract plans and specifications."

The plans and specifications for the construction project were made part of the subcontract and Section 10 of the Specifications provided that the work under Section 10 should conform with referenced requirements of the Standard Elevator and Electric Dumbwaiter Specifications of the General Service Administration (SEEDS).

Paragraph 10-1.1 of Section 10 required the train contractor (Planet) to furnish materials, labor and equipment, and perform "all operations and services required to furnish, fabricate, deliver, install, complete, and test, adjust, place in first class acceptable operating condition" the two passenger trains.

Paragraph 10-4.4 provides that the electrical feeders and wiring shall be as specified in Article 2 of SEEDS. Paragraph 2-1 of Article 2 of SEEDS provides:

"Unless otherwise specified the electric feeders for elevator2 power service and elevator signal service will be terminated at the elevator controller and signal panels in the elevator machine room and the electric feeder for car lighting service will be terminated at a junction box located in hoist-way near midpoint of travel, all as indicated in the project drawings or specified in project specifications. The contractor shall extend wiring from these points to all points of the elevator equipment as required."

Another pertinent provision of SEEDS is paragraph 2-6:

"Conductors — The Contractor [Planet] shall furnish and install all wires and cables necessary for the proper connection and operation of all equipment installed under the elevator contract. * * *."

Also involved in a consideration of Planet's claim is Section 12 of the prime contract. The performance of Section 12 of the prime contract was subcontracted to a third party, Sachs Electric, and admittedly Planet has no responsibility under that Section. Under Section 12-4.2 relating to Elevator and Train Wiring, the contractor (Sachs Electric),

"* * * shall extend the 460-volt 3-phase 3-wire power service to the Machine Room of each elevator and train, install a circuit breaker disconnect and run the power wiring to and connect to the control panels. All wiring, controls and equipment from this point on will be furnished and installed under sections 9 and 10 of the Specification. * * *."3

And under the provisions of 12-1.1d contractor Sachs Electric was to provide "Installation of power wiring and control wiring for all power requirements including elevators and trains."

The District Court in its findings of fact and conclusions of law defined the disputed wiring as "the wiring necessary to operate and run the train extending from the control panels installed by Planet at the top to the control panels at the bottom of the Arch of each train." Planet agrees with this definition of the disputed wiring and contends this is precisely the wiring which falls within the ambit of Section 12 rather than Section 10.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Rich Co., Inc.
439 F.2d 895 (Eighth Circuit, 1971)

Cite This Page — Counsel Stack

Bluebook (online)
417 F.2d 687, 1969 U.S. App. LEXIS 10356, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-macdonald-construction-company-ca8-1969.