United States v. Lemons

125 F. Supp. 686, 1954 U.S. Dist. LEXIS 2741
CourtDistrict Court, W.D. Arkansas
DecidedNovember 10, 1954
Docket580
StatusPublished
Cited by13 cases

This text of 125 F. Supp. 686 (United States v. Lemons) is published on Counsel Stack Legal Research, covering District Court, W.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Lemons, 125 F. Supp. 686, 1954 U.S. Dist. LEXIS 2741 (W.D. Ark. 1954).

Opinion

JOHN E. MILLER, District Judge.

On March 18, 1954, plaintiff filed its complaint against defendants, alleging that it was the holder of a promissory note in the principal amount of $896.84, which note, payable to Arkansas Home Building & Repairing Company, had been executed by defendants and delivered to the said Arkansas Home Building & Repairing Co., and that said note had been duly endorsed and negotiated; that at the time of the filing of the complaint the balance due on said note was $786.32, plus interest. Plaintiff prayed judgment against defendants for the principal sum of $786.32, plus interest in the sum of $76.39 as of March *687 15, 1954, plus interest thereafter at the rate of 6% per annum, together with costs.

On April 27, 1954, defendants filed their answer in which they admitted executing the note payable to Arkansas Home Building & Repairing Company, but denied that said note was delivered or that Arkansas Home Building & Repairing Company was authorized to negotiate said note. Defendants denied that plaintiff was a holder in due course and alleged that the note was not endorsed or negotiated to plaintiff before maturity for value without notice of defendants’ defense; that the note was executed upon the consideration that Arkansas Home Building & Repairing Company would furnish certain labor and materials in repairing defendants’ home, and that there was a failure of consideration since the work contracted for was not completed and the work performed was not done in a workmanlike manner.

Defendants further alleged that Arkansas Home Building & Repairing Company was never authorized to negotiate the note, and denied that they were indebted to plaintiff in any sum.

On June 23, 1954, plaintiff filed and served upon defendants a request for admissions, attaching thereto the promissory note in question, together with the F.H.A. Title I Completion Certificate, Form FH-2, dated June 18, 1952, and purportedly signed by defendant.

The defendant, Theodis Lemons, responded to this request on June 29, 1954, admitting that the said note and Completion Certificate were signed by defendants, but alleging that said signatures were secured by fraud on the part •of Arkansas Home Building and Repairing Company. More specifically, defendants alleged that the note and completion certificate were signed by them in blank at the time the contract (for the repair work) was executed on June 5, 1952, upon the consideration and promise of agents of Arkansas Home Building and Repairing Company to prepare another contract, which would include the repairs that had been agreed upon and which had been omitted from the contract dated June 5, 1952; that upon the execution of said corrected contract, the amount of the note and the amount of the monthly installment payments was to be filled in by Arkansas Home Building and Repairing Company; that said corrected contract was never submitted to the defendants for their signature, and the repairs agreed upon were only partially completed.

The defendants also admitted that they made no payments on the note, but denied that they were in default.

A pre-trial conference was had on September 20, 1954, and upon the request of defendants they were granted permission “to amend their answer to deny that they executed the note involved in this cause * * *.”

Pursuant to the permission granted by the Court, on September 27, 1954, defendants filed an amended and substituted answer in which they denied executing or signing the note and the completion certificate and alleged that their signatures were placed on said documents without their knowledge or consent. Defendants also denied that plaintiff was a holder in due course.

Upon the issues thus joined the case was tried to the Court, without a jury, on October 19, 1954, and at the conclusion of the trial the case was submitted and taken under advisement by the Court. And now the Court, having considered the pleadings, request for admissions and answers thereto, exhibits, deposition of E. R. Livoni and ore tenus testimony of the witnesses, makes and files herein its findings of fact and conclusions of law, separately stated.

Findings of Fact.

1.

The plaintiff is the United States of America. The defendants are citizens of Arkansas and reside in the Hot Springs Division of the Western District.

*688 2.

During the first week in June, 1952, an agent of Arkansas Home Building & Repairing Company came to defendants’ home, which is located about six miles from Hot Springs, Arkansas, and discussed with defendants the condition of their home and repairs that were needed. The agent took various- measurements of the house, but no details were agreed upon at that time. The agent returned on June 5, 1952, and again discussed the repairs with defendants. On this occasion defendants entered into a contract with Arkansas Home Building & Repairing Company for certain work to be performed on defendants’ house, the price of the work to be $780. Both defendants signed the contract, and they also signed a Title I, F.H.A. Credit Application.

Work was started on the house and the work called for by the contract was performed, although defendants were under the impression that additional work was supposed to have been performed.

But the contract, which defendants admittedly executed, provided that “No other work to be done except what is stated in the contract.” And it further provided that it was “To be paid for by you according to the following terms: 36 monthly payments of $24.91 each will pay for job in full, including principal and FHA interest.”

3.

On June 18, 1952, a promissory note in the amount of $896.84, payable to Arkansas Home Building & Repairing Company, was executed, along with a Title I, F.H.A. Completion Certificate. At the trial both defendants denied signing the note and completion certificate, as well as the credit application. And Robert E. Jones, Assistant Cashier of the Arkansas Trust Company, who admittedly was not a handwriting expert but who had observed defendants’ signature in connection with banking transactions, testified that he could not say for sure but he doubted that the note and completion certificate were signed by defendants. However, in the sworn response to plaintiff’s request for admissions defendants admitted signing the note and completion certificate, and predicated their defense upon fraud and failure of consideration. In view of defendants’ admissions, considered along with all the circumstances and facts appearing in the evidence, the Court is unable to find that the signatures on the note and completion certificate are-forgeries.

4.

On June 19, 1952, said note was negotiated to Allied Building Credits, Inc., for the consideration of $780. Then, on February 25, 1953, the said note was-assigned to plaintiff.

5.

The note was to be paid in 36 monthly installments of $24.91 each, the first installment to be paid August 1, 1952. The defendants made no payments on the note.

6.

The note contains an acceleration clause permitting the holder thereof to. declare the note due and payable upon defendants’ failure to pay an installment when due.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Branch Banking & Trust Co. v. Deutz-Allis Corp.
120 F.R.D. 655 (E.D. North Carolina, 1988)
General Electric Co. v. Paul Forsell & Son, Inc.
394 A.2d 1101 (Supreme Court of Rhode Island, 1978)
Woodrow v. Johns
232 N.W.2d 688 (Michigan Court of Appeals, 1975)
Murnan v. Joseph J. Hock, Inc.
335 A.2d 104 (Court of Appeals of Maryland, 1975)
U. S. Industries, Inc. v. Borr
157 N.W.2d 708 (North Dakota Supreme Court, 1968)
Rosado v. Superior Court of Puerto Rico
94 P.R. 117 (Supreme Court of Puerto Rico, 1967)
Rosado v. Tribunal Superior de Puerto Rico
94 P.R. Dec. 122 (Supreme Court of Puerto Rico, 1967)
Jackson v. Hearn Brothers, Inc.
212 A.2d 726 (Supreme Court of Delaware, 1965)
McSparran v. Hanigan
225 F. Supp. 628 (E.D. Pennsylvania, 1963)
Nicholson v. Bailey
182 F. Supp. 509 (S.D. Florida, 1960)
United States v. Wimbley
125 F. Supp. 691 (W.D. Arkansas, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
125 F. Supp. 686, 1954 U.S. Dist. LEXIS 2741, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-lemons-arwd-1954.