United States v. Joseph G. Moretti, Inc.

331 F. Supp. 151, 3 ERC 1052, 1 Envtl. L. Rep. (Envtl. Law Inst.) 20443, 3 ERC (BNA) 1052, 1971 U.S. Dist. LEXIS 11784
CourtDistrict Court, S.D. Florida
DecidedSeptember 2, 1971
DocketCiv. 71-1176
StatusPublished
Cited by12 cases

This text of 331 F. Supp. 151 (United States v. Joseph G. Moretti, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Joseph G. Moretti, Inc., 331 F. Supp. 151, 3 ERC 1052, 1 Envtl. L. Rep. (Envtl. Law Inst.) 20443, 3 ERC (BNA) 1052, 1971 U.S. Dist. LEXIS 11784 (S.D. Fla. 1971).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

MEHRTENS, District Judge.

This cause having come before this Honorable Court on the motion of the Petition, United States Attorney, for the United States of America, and after considering of pleadings in this matter, evidence presented at a hearing before this Court on July 30, 1971 where testimony was taken and a preliminary injunction entered against the defendants, Joseph G. Moretti, Inc. and Joseph G. Moretti, Jr., and at a further hearing held between August 18 and August 20, 1971 the purpose of which was to decide whether the preliminary injunction entered on July 30, 1971 was to become permanent, and being otherwise fully advised in the premises, the Court makes the following Findings of Fact and Conclusions of Law:

FINDINGS OF FACT

This action was brought pursuant to Sections 403 and 406 of Title 33, United States Code, on application of the United States of America, Petitioner, for injunctive relief restraining the defendants, Joseph G. Moretti, Inc. and Joseph G. Moretti, Jr., from further conducting dredge and fill work in Florida Bay at Hammer Point, Key Largo, Florida, from selling or conveying real property at that location, and for further relief the Court might find appropriate. A hearing on the Government’s motion for a preliminary injunction was held on July 30, 1971, where testimony was taken and the Court issued an order restraining the defendants from conducting any further dredge and fill work in Florida Bay at Hammer Point and from selling and conveying any land filled in at that location below the mean high water mark as it formerly existed.

Beginning on August 18 and ending August 20, 1971, a hearing as to whether the preliminary injunction entered on July 30, 1971 should become permanent and whether the United States was entitled to further relief was held. At that hearing, testimony was taken from the following witnesses: Mr. James T. Glass, Professional Engineer; Dr. Frederick Bond, a resident of Key Largo; Mr. A. L. McKnight, former Chief of Operations, United States Army Corps of Engineers, Jacksonville, Florida; Mr. Lee Purkerson, Biologist, United States Environmental Protection Agency; Mr. Joseph Carroll, United States Department of Interior; Mr. Alexander Sprunt, Audubon Society, Tavanier, Florida; Mr. Lynn Peyton, State of Florida Department of Air and Water and Pollution Control; Mr. Gilbert Bird, United States Department of Interior. Also, numerous photographs were exhibited, and documents, together with several of these photographs were introduced into evidence.

The defendant, Joseph G. Moretti, Inc., is a construction company which *154 owns a tract of land located at Hammer Point, Key Largo, Florida, which it has developed into a trailer park. This development has involved digging of canals in Florida Bay, filling in parts of the upland and bay portions of this property, the placing of large rocks or “rip-rap” to create a bulkhead at the bay-front edges of the property and canals. During this construction work, various pieces of heavy equipment, including draglines and bulldozers were employed, together with the use of dynamite and other equipment normally associated with the removal and placement of large quantities of earth and rock fill. The defendant, Joseph G. Moretti, Jr., is the vice-president of Joseph G. Moretti, Inc., and the individual of that corporation who has been and is presently responsible for the Moretti Company’s activities at their Hammer Point development in Key Largo.

At the time the Moretti Company began construction work at their Hammer Point, Florida Bay, Key Largo site, Florida Bay was and continues to exist as a navigable water of the United States. Florida Bay connects directly to the Gulf of Mexico and also at various points with the Atlantic Ocean.

Late in December of 1970, the United States Army Corps of Engineers at Jacksonville, Florida, received information of the Moretti Company’s development and work which included dredging canals and filling in certain bottom lands and on December- 30, 1971, the Army Engineers at Jacksonville, by telegraph, advised the Joseph G. Moretti, Inc. they had learned of the dredge and fill work being conducted at Florida Bay and that no record of a Department of the Army permit for such project was found to have been issued. The Army Corps of Engineers advised Moretti that such operations were unlawful in the absence of a permit and directed the Moretti Company to immediately discontinue any operations and not to resume until after they had submitted an application to the Corps of Engineers and received necessary Department of the Army permit.

There was, subsequent to this, several communications between the Moretti Company and the Corps of Engineers where the Corps of Engineers further advised the Moretti Company of the necessity of obtaining a permit before further work was done at this project if that work was to be done in the navigable waters of the United States.

Late in February of 1971, the Army Engineers at, Jacksonville received an application for a permit for the Joseph G. Moretti Company submitted by Bailey, Glass and Post, an engineering firm. This application was prepared by Mr. James T. Glass, a professional engineer at that time with the firm Bailey, Glass and Post. Mr. Glass, through the study of aerial photographs of Hammer Point, Key Largo, and personal examination of' the construction site, prepared a diagram of the proposed Moretti Company project. On this diagram, the mean high tide line, or mean high water mark, was indicated as it existed immediately before work was commenced.

This was determined by the use of aerial photographs and on-site inspections. Where that mean high water mark had been disturbed at the time the application and diagram were prepared, aerial photographs were used to make an approximate determination of where the mean high water mark had existed. Where this area was inhabited by mangrove stands which had been removed during the construction work, the outer or bayward edge of the mangroves, as illustrated by the photographs, was used in preparing the sketch of the high water mark, as shown in the diagram submitted by Glass.

Under those circumstances, therefore, the mean high water mark as shown in the application for a permit submitted by Glass, reflects the lowest or most bayward position of the mean high water mark possible according to information available when the sketch was prepared. In fact, the mean high water mark may have been considerably higher than indicated but it could not have been *155 further into the bay than shown on the sketch.

Much of the work for which a permit was requested had already been completed by the Moretti Company. In that respect, the application for a permit was characterized as “after the fact”.

After the application was received by the Army Engineers at Jacksonville, Florida, and pursuant to statutory requirements, the Corps of Engineers publicly advertised the application and requested comments from concerned parties. Further, it contacted the United States Department of Interior, the Environmental Protection Agency and various state agencies soliciting their comments on the application. During the month of April, 1971, and in response to its public notices, the Corps received various letters from private citizens protesting the application for a permit by the Moretti Company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Martin
517 F. Supp. 211 (D. South Carolina, 1981)
United States v. Joseph G. Moretti, Inc.
423 F. Supp. 1197 (S.D. Florida, 1976)
United States v. Joseph G. Moretti, Inc.
526 F.2d 1306 (Fifth Circuit, 1976)
United States v. Kaiser Aetna
408 F. Supp. 42 (D. Hawaii, 1976)
United States v. Sexton Cove Estates, Inc.
389 F. Supp. 602 (S.D. Florida, 1975)
United States v. Cannon
363 F. Supp. 1045 (D. Delaware, 1973)
United States v. Stoeco Homes, Inc.
359 F. Supp. 672 (D. New Jersey, 1973)
United States v. Lewis
355 F. Supp. 1132 (S.D. Georgia, 1973)
Potomac Sand & Gravel Co. v. Governor
293 A.2d 241 (Court of Appeals of Maryland, 1972)
United States v. Underwood
344 F. Supp. 486 (M.D. Florida, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
331 F. Supp. 151, 3 ERC 1052, 1 Envtl. L. Rep. (Envtl. Law Inst.) 20443, 3 ERC (BNA) 1052, 1971 U.S. Dist. LEXIS 11784, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-joseph-g-moretti-inc-flsd-1971.