United States v. Hirani Engineering & Land Surveying, PC

CourtCourt of Appeals for the D.C. Circuit
DecidedJanuary 14, 2025
Docket24-7020
StatusUnpublished

This text of United States v. Hirani Engineering & Land Surveying, PC (United States v. Hirani Engineering & Land Surveying, PC) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Hirani Engineering & Land Surveying, PC, (D.C. Cir. 2025).

Opinion

United States Court of Appeals FOR THE DISTRICT OF COLUMBIA CIRCUIT

No. 24-7020 September Term, 2024 FILED ON: JANUARY 14, 2025

UNITED STATES OF AMERICA, FOR THE USE AND BENEFIT OF AMERICAN CIVIL CONSTRUCTION, LLC, APPELLEE

v.

HIRANI ENGINEERING & LAND SURVEYING, PC, APPELLEE

COLONIAL SURETY COMPANY, APPELLANT

Appeal from the United States District Court for the District of Columbia (No. 1:14-cv-00745)

Before: SRINIVASAN, Chief Judge, HENDERSON and PILLARD, Circuit Judges.

JUDGMENT

The court considered this appeal on the record from the United States District Court for the District of Columbia and the briefs filed by the parties. See Fed. R. App. P. 34(a)(2); D.C. Cir. R. 34(j). We accorded the issues full consideration and determined they do not warrant a published opinion. See D.C. Cir. R. 36(d). For the reasons stated below, it is hereby

ORDERED AND ADJUDGED that the judgment of the district court is AFFIRMED.

I.

This appeal is the latest development in the long-running litigation between American Civil Construction (ACC) and two entities it sued for breach of contract, Hirani Engineering & Land Surveying and Colonial Surety Company. 1 The procedural history of this dispute is long and

1 The full history of this litigation is detailed in six prior decisions issued by this court and the district court: United States ex rel. Am. Civil Constr., LLC v. Hirani Eng’g & Land Surveying, P.C. (Hirani I), 263 F. Supp. 3d 99 (D.D.C. 2017); Hirani II, 345 F. Supp. 3d 11 (D.D.C. 2018) (stating district court’s findings of fact and conclusions winding, but for current purposes we need only summarize the most pertinent facts.

Hirani served as the prime contractor on a United States Army Corps of Engineers project to construct a levee flood wall in Washington, D.C. Hirani II, 345 F. Supp. 3d at 21 ¶ 4, 22 ¶ 9. In turn, Hirani hired ACC to work as a subcontractor on the project. Id. at 22 ¶ 13. The total price for ACC’s services under the subcontract, including approved change orders, was $ 3,459,250. Hirani III, 2019 WL 162019, at *4-5 (stating subcontract price including contract “Option 1”). Under the Miller Act, Hirani was required to obtain a payment bond to protect “all persons supplying labor and material in carrying out the work provided for in the contract.” Hirani IV, 26 F.4th at 956 (quoting 40 U.S.C. § 3131(b)(2)). That included its subcontractor, ACC. Hirani, as principal, obtained the payment bond from Colonial, which served as the surety. Hirani II, 345 F. Supp. 3d at 22 ¶ 12.

The construction was beset by delays, unexpected modifications, and technical snafus, and the Army Corps of Engineers eventually terminated Hirani for default, which effectively ended ACC’s participation. Id. at 30 ¶ 92, 32 ¶ 104. See Hirani IV, 26 F.4th at 954. ACC filed suit in district court seeking to collect against Hirani on the subcontract and against Colonial on the Miller Act payment bond. See 40 U.S.C. § 3133(b)(1).

II.

In resolving the breach of contract claim, the district court awarded ACC restitution against Hirani in the amount of $ 425,319.50, which was capped under District of Columbia law based on the contract price, and granted an uncapped award of $ 1,544,957.29 against Colonial under the Miller Act for the full amount of the reasonable value of the labor, services, and materials that it furnished to the project. Hirani III, 2019 WL 162019, at *3-5. The district court explained its rationale for the disparate awards against the two defendants. On the breach of contract claim against Hirani under D.C. law, the district court drew on the Restatement (Third) of Restitution and Unjust Enrichment to conclude that ACC’s recovery for performance-based restitution was limited to the balance of its expectancy under the contract. Id. at *4-5. The court calculated that amount to be $ 425,319.50 (before pre-judgment interest). Id. By contrast, the court determined that a Miller Act award against Colonial was not limited to expectancy. It therefore awarded ACC $ 1,544,957.29 (before pre-judgment interest) under a quantum meruit theory to compensate for the reasonable value of the full extent of ACC’s performance, which involved far more work over a period roughly triple the duration the contract specified. Id. at *3; see Hirani II, 345 F. Supp. 3d at 22 ¶ 15, 24 ¶ 37, 32 ¶ 104; see, e.g., id. at 26 ¶ 54 (“From July 3, 2012, to April 23, 2013, the USACE issued numerous unilateral change orders and constructive change directives to Hirani, who in turn subcontracted the work to ACC to complete these change orders.”).

of law); Hirani III, No. 14-cv-00745, 2019 WL 162019 (D.D.C. Jan. 10, 2019); Hirani IV, 26 F.4th 952 (D.C. Cir. 2022), amending 962 F.3d 587 (D.C. Cir. 2020); Hirani V, 58 F.4th 1250 (D.C. Cir. 2023); and Hirani VI, No. 14- cv-00745, 2024 WL 754630 (D.D.C. Jan. 18, 2024).

2 In a prior appeal, we largely affirmed the district court’s awards. See Hirani V, 58 F.4th at 1251-53. Colonial’s appeal pressed two points: that quantum meruit was inapplicable because there was an express contract from which damages could be calculated and that, in any event, the subcontractor’s quantum meruit award against the surety could not exceed its expectation damages against the prime contractor. Id. at 1251. We rejected both claims of error. We held that, “[e]ven if D.C. contract law caps the subcontractor’s restitution recovery against the prime contractor to expectation damages and does not permit recovery in quantum meruit where there is an express contract, no such limit applies to the claim against the surety under the Miller Act.” Id. That conclusion followed from the “highly remedial nature” of the Act, which the Supreme Court held should be liberally construed to protect subcontractors who work on public projects. See id. at 1252 (quoting Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102, 107 (1944) (formatting altered)). We then remanded the case to the district court to address two narrow issues. First, Colonial had argued that the awards would afford ACC an impermissible double recovery because the district court had calculated the quantum meruit recovery of $ 1,544,957.29 against Colonial to include the expectancy amount of $ 425,319.50 it awarded against Hirani—rather than calculating the quantum meruit award to include only the work performed beyond the contract- based expectancy. Id. at 1252-53. On remand, we instructed the district court to explain whether the two awards would yield a double recovery by clarifying the extent of the overlap between them, if any. Id. at 1253.

Second, we had reversed the district court on one component of the quantum meruit calculation, holding that the Miller Act entitled ACC to compensation for the reasonable value of services provided by the superintendent at the construction site. Id. at 1254. We therefore instructed the district court on remand to calculate the appropriate compensation amount. Id. at 1254-55.

The district court completed the limited tasks we assigned it on remand.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
United States v. Hirani Engineering & Land Surveying, PC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-hirani-engineering-land-surveying-pc-cadc-2025.