United States v. Harkins Builders, Incorporated

45 F.3d 830, 1995 U.S. App. LEXIS 1443
CourtCourt of Appeals for the Fourth Circuit
DecidedJanuary 25, 1995
Docket94-1136
StatusPublished
Cited by2 cases

This text of 45 F.3d 830 (United States v. Harkins Builders, Incorporated) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Harkins Builders, Incorporated, 45 F.3d 830, 1995 U.S. App. LEXIS 1443 (4th Cir. 1995).

Opinion

45 F.3d 830

63 USLW 2462

UNITED STATES of America, for the use and benefit of Global
Building Supply, Incorporated; United States of America,
for the use and benefit of Superior Supply Associates,
Incorporated, Plaintiffs-Appellees,
v.
HARKINS BUILDERS, INCORPORATED, Defendant-Appellant,
and
WNH Limited Partnership; Thomas P. Harkins, Incorporated;
Toledo Drywall, Incorporated; Today Contractors,
Incorporated; The Federal Insurance
Company, Defendants.

No. 94-1136.

United States Court of Appeals,
Fourth Circuit.

Argued Sept. 28, 1994.
Decided Jan. 25, 1995.

ARGUED: Stephen Lewis Best, Sr., Fairfax, VA, for appellant. Robert Keith Richardson, Odin, Feldman & Pittleman, P.C., Fairfax, VA, for appellees.

Before NIEMEYER and LUTTIG, Circuit Judges, and PHILLIPS, Senior Circuit Judge.

Affirmed in part, reversed in part, and remanded by published opinion. Judge NIEMEYER wrote the opinion, in which Judge LUTTIG joined. Senior Judge PHILLIPS wrote a separate dissenting opinion.

OPINION

NIEMEYER, Circuit Judge:

We are presented with the question of first impression whether a judgment creditor, pursuing a garnishment proceeding against a garnishee who owed money to the judgment debtor under a contract, is bound by a mandatory arbitration clause in that contract.

Global Building Supply, Inc., and Superior Supply Associates, Inc. (hereafter collectively, "Global Supply") supplied drywall materials to drywall subcontractors, Toledo Drywall, Inc. and Today Contractors, Inc. (hereafter collectively, "Toledo Drywall").1 When Toledo Drywall failed to pay for the materials, Global Supply obtained a judgment against it in federal court in the amount of $278,520. In an effort to collect the judgment, Global Supply initiated a garnishment proceeding against Harkins Builders, Inc. to attach monies owed by Harkins to Toledo Drywall under a contract between them. As garnishee, Harkins confessed assets but alleged that the amount it owed to Toledo Drywall should be reduced by setoffs totalling $50,853 allegedly owed by Toledo Drywall to Harkins under their contract. Moreover, Harkins argues that any dispute about these setoffs must be resolved through arbitration, as also provided in the contract.

The district court rejected the contention that resolution of the amount of money owed by Harkins to Toledo Drywall and subjected to garnishment must be accomplished through arbitration. After determining the amount subjected to garnishment, the court entered judgment in the garnishment proceeding in favor of Global Supply against Harkins in the total amount of $116,340, without specifically addressing the major portion of Harkins' claimed setoffs. On Harkins' appeal, we affirm the district court's ruling that the amount subjected to garnishment should not be determined by arbitration, but we remand the case for resolution of the legal and factual questions raised by Harkins' setoff claim.

* Harkins was the general contractor for the construction of an apartment complex in Prince William County, Virginia. The complex was being constructed by WNH Limited Partnership for the Department of the Navy to house naval personnel. The drywall work on the project was performed by Toledo Drywall, which purchased its materials from Global Supply. When Toledo Drywall failed to pay Global Supply for the materials, Global Supply obtained a judgment against Toledo Drywall in federal court in the amount of $278,520 plus interest, costs, and attorneys fees.

To enforce the judgment, Global Supply sought to attach monies owed by Harkins to Toledo Drywall for work performed on the project. Global Supply filed a garnishment proceeding against Harkins, demanding that the money which Harkins owed to Toledo Drywall be paid directed to Global Supply in partial satisfaction of the judgment. Harkins acknowledged that it owed Toledo Drywall $119,823, but asserted that, under its contract with Toledo Drywall, it was entitled to setoffs for attorneys fees and expenses incurred by Harkins in respect of Toledo Drywall's defaults in failing to pay its suppliers. While Global Supply stipulated that Harkins was entitled to a setoff of $3,484 incurred by Harkins in bonding off certain mechanic's liens, it contended that Harkins is not entitled to a setoff of the remaining $47,369 in attorneys fees incurred by Harkins in defending mechanic's liens proceedings and Miller Act2 claims arising from Toledo Drywall's defaults. Harkins contended that by reason of an arbitration clause in the contract between it and Toledo Drywall, any dispute over the setoff should be resolved by arbitration.

The district court rejected the contention that the dispute over the amount subjected to garnishment should be determined in arbitration and found that Harkins owed Toledo Drywall $116,340, representing the $119,823 owed less the $3,484 stipulated setoff. On the remaining $47,369 setoff claim asserted by Harkins, the magistrate judge, who heard the case in the first instance, stated, "For reasons I've articulated I'm going to sustain the objections of the creditor." The magistrate judge, however, gave no other reasons in his opinion for denying the setoffs claimed by Harkins, and his recommendations were adopted by the district judge without further comment.

II

In seeking to enforce its federal money judgment against Toledo Drywall, Global Supply's rights are governed by Federal Rule of Civil Procedure 69(a), which provides in relevant part:

Process to enforce a judgment for the payment of money shall be a writ of execution.... The procedure on execution, ... in proceedings on and in aid of execution shall be in accordance with the practice and procedure of the state in which the district court is held....

Since the judgment in this case was obtained in the Eastern District of Virginia and its enforcement was initiated in that district, Virginia's practice and procedure is borrowed by federal rule for the purpose of enforcing the judgment through a writ of execution. Even though we look to state law to determine the practice and procedure to be followed in the execution of a judgment, we do so in furtherance of federal law, giving effect to rules entitling parties to enforce federal judgments in federal courts. Consequently, any aspects of the assimilated practices and procedures that are uniquely designed to enforce state judgments are not assimilated, nor is any aspect that may be inconsistent with the federal policy of affording judgment creditors the right to a writ of execution to enforce money judgments in federal courts. See generally 12 Charles A. Wright & Arthur R. Miller, Federal Practice and Procedure Sec. 3012, at 69 (1973) (substantial compliance with state procedural provisions is sufficient).

Under Virginia law, a money judgment is enforced by the issuance of a writ of fieri facias and delivery of the writ to a "proper officer" of the court for enforcement. See Va.Code Ann. Sec. 8.01-466 (1992).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stephens v. Benanti
E.D. Tennessee, 2024

Cite This Page — Counsel Stack

Bluebook (online)
45 F.3d 830, 1995 U.S. App. LEXIS 1443, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-harkins-builders-incorporated-ca4-1995.