S & D Land Clearing Ex Rel. Mitchell v. D'Elegance Management Ltd.

34 F. App'x 885
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 25, 2002
Docket01-1553, 01-1509, 01-1576, 01-2043
StatusUnpublished
Cited by2 cases

This text of 34 F. App'x 885 (S & D Land Clearing Ex Rel. Mitchell v. D'Elegance Management Ltd.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
S & D Land Clearing Ex Rel. Mitchell v. D'Elegance Management Ltd., 34 F. App'x 885 (4th Cir. 2002).

Opinion

OPINION

PER CURIAM.

D’Elegance Management Limited, Incorporated (D’Elegance) and its counsel, the law firm of Vezina, Lawrence and Piscitelli (VLP) (collectively Appellants), appeal from three orders of the district court in two related cases that arise out of the removal of debris in North Carolina following Hurricane Fran. The two cases, one brought by D’Elegance seeking payment from two bonds issued by Universal Surety of America (Universal) to cover clean-up work performed by D’Elegance (the Bond Case) and the other brought against D’Eleganee by Mike Mitchell d/b/a Malaco and S & D Land Clearing (collectively Malaco) seeking damages with regard to work it did to assist in the clean-up 1 (the Debris *889 Case), reach this court for the second time. See United States for Use and Benefit of S & D Land Clearing v. D’Elegance Ltd., Inc., 217 F.3d 843 (4th Cir.2000) (D'Elegance I) (affirming the district court’s judgment in the Debris Case except for its decision to set aside Malaco’s compensatory damage award); United States for Use and Benefit of D'Elegance, Ltd., Inc. v. Universal Surety of Am., No. 99-2195, 2000 WL 1224164 (4th Cir. Aug.29, 2000) (D'Elegance II) (reversing the district court’s grant of summary judgment in the Bond Case against D’Elegance as to first bond and affirming its grant of summary judgment against D’Elegance as to second). Although these current appeals have not been formally consolidated, they are factually interrelated to such a degree that we conclude it is appropriate to resolve them in a single opinion.

Appellants challenge three orders issued by the district court. First, on March 16, 2001, in the Bond Case, the district court ordered Universal to pay the judgment against it in the amount of $250,000, plus costs in the amount of $5,231.87 and post-judgment interest, into the Office of the Clerk of the Court. Second, on March 21, 2001, in the Debris Case, the district court, on Malaco’s motion, commenced supplemental proceedings to enforce the judgment against D’Elegance and ordered Appellants not to transfer any property of D’Eleganee that was not exempt from execution. Third, on July 3, 2001, the district court denied VLP’s motion for leave to file a Notice of Charging Lien in the Bond Case. Because the district court has not ruled on the ultimate fate of the funds paid by Universal to the Office of the Clerk of the Court, the challenges to the March 16 and July 3 orders are unreviewable as interlocutory. With regard to the appeal from the March 21 order, the district court did not err in allowing supplemental proceedings and the order not to transfer D’Elegance’s property was appropriate under such proceedings.

I.

On September 6, 1996, Hurricane Fran, a category 3 hurricane on the Saffir/Simpson Hurricane Scale, made landfall on the North Carolina coast near Cape Fear. Hurricane Fran, one of the costliest in United States history, killed 34 people and caused over $3.2 billion in property damage.

On September 18, 1996, the U.S. Army Corps of Engineers (the Corps) awarded a contract to Waste Control Services for the removal of debris in eight counties in North Carolina. Waste Control then subcontracted with D’Elegance for the removal of construction and demolition debris (C & D debris) in both Pender and New Hanover Counties. D’Elegance agreed to remove at least 5,000 cubic yards of such debris a day. Waste Control, as required by its contract with the Corps, executed and delivered two payment bonds that would provide coverage for the protection of its subcontractors, with Waste Control as principal and Universal as surety.

D’Elegance in turn subcontracted with Malaco to perform all of D’Elegance’s debris-removal work, misrepresenting to Malaco that the work would involve not only C & D debris but also vegetative debris. 2 Malaco subcontracted with a trucking com *890 pany for enough trucks to meet D’Elegance’s quota of 5,000 cubic yards per day. Once removal began, however, D’Elegance used other haulers, leaving most of Malaco’s debris removal capacity unutilized. The small amount of C & D debris Malaco was allowed to remove was the least profitable. 3 Malaco encountered other difficulties, including D’Elegance’s efforts to hire away Malaco’s truck drivers with promises of higher pay and warnings that Malaco did not have a contract and was not going to get paid. Malaco continued to haul C & D debris until October 29, 1996, at which time Waste Control instructed Malaco to cease work on the project because Malaco was not going to be paid by D’Elegance. Although D’Elegance did pay $55,344 to Malaco and $80,629.33 directly to Malaco’s subcontractors, at the time of the work stoppage, D’Elegance owed Malaco a balance of $62,232.54 for the debris Malaco had removed. On November 4, 1996, D’Elegance offered to pay Malaco if the latter would sign a backdated contract with terms materially different from the original contract, but Malaco declined. This situation left Malaco deeply indebted to its subcontractors. At the same time, Waste Control did not pay the full amount of D’Elegance’s $2,752,684 invoice, leaving a balance of at least $369,623.23.

On March 5, 1997, Malaco initiated the Debris Case by filing a complaint against Waste Control, D’Elegance, and Universal. Malaco claimed, among other things, that D’Elegance had breached its contract with Malaco and had violated North Carolina’s unfair and deceptive trade practices statute. See N.C. Gen.Stat. § 75-1.1 (1999) (Chapter 75). D’Elegance counter-claimed against Malaco for breach of contract, asserting that Malaco had failed to meet the 5,000 cubic yards per-day quota and had failed to pay its subcontractors in a timely fashion. D’Elegance initiated the Bond Case on December 3, 1997, by filing suit against Waste Control and Universal to recover the unpaid balance from its invoice. On February 25, 1998, the district court consolidated the Bond Case and the Debris Case.

The case was tried before a jury in August 1998, and the jury found, with regard to the claims in the Debris Case, in favor of Malaco and against D’Elegance. 4 With regard to the claims in the Bond Case, the district court declared a mistrial, and consequently, the cases were severed on January 27,1999.

On appeal of the Debris Case, this court affirmed the denial of D’Elegance’s motion for judgment as a matter of law, the denial of treble damages, and the registration of the judgment. 5 See D’Elegance 7, at *9. We reversed, however, the district court’s ruling to set aside the jury’s fraud verdict and ordered that the jury’s fraud award should be reinstated and trebled pursuant to Chapter 75. Id. (affirming in part and reversing in part, but not remanding). As a result, D’Elegance became indebted to Malaco for a total of $841,828.00, plus interest: $400,000 in compensatory damages for breach of contract; $300,000.00 in trebled compensatory damages for fraud; *891

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
34 F. App'x 885, Counsel Stack Legal Research, https://law.counselstack.com/opinion/s-d-land-clearing-ex-rel-mitchell-v-delegance-management-ltd-ca4-2002.