United States v. George A. Fuller Co.

300 F. 206, 1924 U.S. Dist. LEXIS 1425
CourtDistrict Court, D. Kansas
DecidedMay 23, 1924
DocketNo. 2485
StatusPublished
Cited by2 cases

This text of 300 F. 206 (United States v. George A. Fuller Co.) is published on Counsel Stack Legal Research, covering District Court, D. Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. George A. Fuller Co., 300 F. 206, 1924 U.S. Dist. LEXIS 1425 (D. Kan. 1924).

Opinion

POLLOCK, District Judge.

This action at law arises out of the building of the cantonment in this state known as Camp Funston. The government entered into what is termed a cost plus contract with defendant for the doing of the construction work of this cantonment. This contract is in writing, attached to and forming part of the plaintiff’s cause of action. The theory of damages on which the plaintiff in its amended petition relies is this:

That in certain respects defendant was guilty of waste, wrongs, and negligence. These examples of alleged negligence and wrongdoing, pleaded in quite general language, are not counted upon by plaintiff for the purpose of showing what specific or special damage thereby accrued to the plaintiff as a result of the same, but, on the contrary, any such purpose in the pleader is expressly denied, as will he seen by the following excerpts from the amended pleading;

“That the said course of fraudulent, reekless, wanton, wasteful, and negligent conduct was persisted in and adhered to by the defendant in the respects mentioned throughout its operations under said contract; that, because said course of conduct was unknown to the plaintiff at the time, and because the plaintiff has been unable, after diligent and persistent effort, to secure fuller or more detailed information, it is impossible for the plaintiff at this time to state in greater detail the said course of conduct; that the whole of said course of conduct and all the said losses and damages resulting therefrom have been at all times and still are peculiarly within the knowledge of the defendant, and that defendant at all times has had and still has definite and detailed knowledge of all the facts and circumstances connected therewith; and that throughout its operations under said contract the defendant, fully knowing its said course of conduct, and fully acquainted with the said losses and damages occasioned thereby, persisted therein and neglected and failed to correct or change its said course of conduct.
“Plaintiff avers that all such negligent, wasteful, inefficient, wrongful, and fraudulent acts and course of conduct of defendant, as hereinbefore set out, were without the knowledge or the consent of the plaintiff, and plaintiff is advised, believes, and alleges that they were without the consent of the contracting officer, or any officer of the plaintiff on the project authorized to act in the premises for the plaintiff, or whose duty it was to protect the interests of the plaintiff; and plaintiff further avers that no one was or could so act for plaintiff as to authorize, condone, accept, or pay for any materials which were not necessary, or any materials which were unnecessarily wasted, or any claims made for labor which was not in good faith performed, or for [208]*208the excess In such claims when made at a different and higher rate than that which should have been paid for the work actually performed.
“Plaintiff avers that all the matters and acts of negligent and fraudulent misconduct of defendant, as in this petition alleged, contributed to make the total excessive cost of the project; that no record was kept by defendant, or by plaintiff (and no duty was on plaintiff so to do), that can or will show the effect of and (lamage to plaintiff from any of such items, or of any particular character of such misconduct, for the reason that same consisted of a course of continuous conduct, made up of continuously recurrent and innumerable acts, which occurred as aforestated throughout the entire area of that large project, which was several square miles in extent, and which persisted throughout substantially all of the period of engagement by defendant on said work, and for the reason that each of such acts and factors and matters of conduct were so intermingled with and so acted upon other acts, factors, items, and character of misconduct as either generally or specifically hereinbefore alleged, that it is impossible (except in so far as hereinbefore set out) even approximately to state how much any one of said matters amounted to or added to the excessive cost of said project. But plaintiff avers that each and all of them contributed with the others unduly to enhance the cost of said project, so that all of them, both those averred generally and those averred specifically, each contributing in an unknown amount, caused the total cost, in which first and finally appears and is reflected the aggregate effect and result of all of said factors, items, and course of misconduct, to be $3,000,000 in excess of what it should reasonably and fairly have been, if the defendant had faithfully and honestly performed its duties and obligations.
“The plaintiff avers that all of the acts herein complained of were done with the connivance, knowledge, consent, and by procurement of the defendant, and that they were so done, among other reasons, for the fraudulent purpose of causing excessive cost to plaintiff, and of securing from the plaintiff a maximum rather than a fair and reasonable sum in compensation for its services; that defendant knowingly, willfully, and fraudulently misrepresented facts to the plaintiff, and concealed true facts from the plaintiff, in the manner and respects as hereinbefore averred, and thereby procured and aided in procuring to be paid by the plaintiff to defendant and others excessive sums of money to itself and others, that were known to the defendant to be a fraud upon the plaintiff, as reimbursements, for expenditures made and materials wasted and destroyed, which were not necessary in said work, to plaintiff’s damage as alleged.
“That by reason of the premises hereinbefore set forth, and the facts alleged, and the fraud and deceit thus practiced by defendant upon and against the plaintiff, the cost to plaintiff of the construction of said cantonment was three million dollars ($3,000,000) in excess of the fair and reasonable cost thereof, under the conditions and circumstances then existing, and the plaintiff has been damaged thereby by defendant in said amount, no part of which had been paid to the plaintiff by the defendant, or by any one for defendant. The damages stated under the separate items are not in addition to the total damages above averred, and no additional claim for damages is made on account of any of said items, but they are all included in and are parts of the said total damages herein averred.”

It is the theory-qf the pleader in this amended petition to plead the special facts in a few instances for the purpose of showing the same by evidence as a general practice or continuous course of conduct on the part of the defendant, while working under the contract in the attempt to perform it and complete the construction of the camp. Thus having shown or attempted to show the examples of alleged negligence pleaded as specimens or samples of defendant’s continuous course of conduct to ask the jury for a verdict of general damages measured by the actual cost of the building of the cantonment to the government in this case [209]*209and the fair and reasonable cost of constructing the same had defendant company been at all times, and in all things, whether pleaded or proven or not, diligent, and not wasteful or negligent. That this is the undoubted theory of the plaintiff on which it bases a right of recovery is clearly shown by the measure and manner of alleging damages found iñ the pleading as above quoted.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Creighton v. Bloom
165 A. 51 (Superior Court of Pennsylvania, 1932)
Domira
49 F.2d 324 (E.D. New York, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
300 F. 206, 1924 U.S. Dist. LEXIS 1425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-george-a-fuller-co-ksd-1924.