United States v. George A. Fuller Co.

14 F.2d 813, 1926 U.S. App. LEXIS 2113
CourtCourt of Appeals for the Eighth Circuit
DecidedSeptember 13, 1926
StatusPublished
Cited by12 cases

This text of 14 F.2d 813 (United States v. George A. Fuller Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. George A. Fuller Co., 14 F.2d 813, 1926 U.S. App. LEXIS 2113 (8th Cir. 1926).

Opinion

LEWIS, Circuit Judge

(after stating the facts as above). [1] This action is founded on the contract between the parties of date June 20, 1917 (set out above), for the Construction of Camp Funston on the Fort Riley Military Reservation; and the errors assigned are directed to the ruling of the court in sustaining a general demurrer to the third amended petition and its judgment of dismissal of the cause on that ruling. The original and first amended petitions each set up one-alleged cause of action for damage? based on a claimed breach of the contract by George A. Fuller Co. because of alleged lack of skill and negligence in its execution; and the second and third amended petitions each contain four alleged causes of action. To each petition a copy of the contract was attached and made a part of the pleading by reference. The preceding petitions were each held bad on motions to strike, to make more certain and demurrers filed thereto by the defendant. Before we come to the issue presented by the demurrer the rights and duties of the parties and the basis on which they rest should be determined, for the purpose of pleading. In reference to the third amended petition plaintiff’s counsel in his argument here says: “One of those causes of action is negligence, one in breach of .contract, one in quasi-contract, and one in fraud and deceit.” We fail to see any distinction between counts 1 and 2. Each of them charges the same negligence in general terms as constituting breach of the contract. The third count may be an attempt to charge damages for fraud and deceit; and the fourth is clearly for money had and received. But it is not necessary to define them. , The rights of each party rest on the contract and the acts complained of were done in its performance. Technical definitions are of no avail. The facts stated in the petition determine its character and sufficiency. Code pleading deals with substance, not with formalities. In Hamilton v. Empire Gas & Fuel Co., 297 F. 422, this court had occasion to consider the effect of stating a cause of action as for a tort when the plaintiff’s rights and duties rested on contract. We accepted the rule announced by Underhill and Pollock on Torts when applied to Code pleading and quoted from the latter thus:

“Now that forms of pleading are generally abolished or .greatly simplied, it seems better to say that wherever there is a contract to do something the obligation of the contract is the only obligation between the parties with regard to the performance, whether there was a duty antecedent to the contract or not. But injury which would have been a tort as breach of a duty existing at common law if there had not been any contract is still a tort;”

—and from Whittaker v. Collins, 34 Minn. 299, 25 N. W. 632, 57 Am. Rep. 55:

“Where the action is not maintainable without pleading and proving the contract— where the gist of the action is the breach of the contract, either by malfeasance or nonfeasance — it is, in substance, whatever may be the form of the pleading, an action on the contract. * * * The foundation of the action is the contract, and the gravamen of it - its breach.”

Pomeroy’s Code Remedies (3d Ed.) § 576, says:

“Since the reformed pleading requires the facts to be averred as they actually took place, it does not in general,permit a single cause of action to be set forth in two or more different forms or counts, as was the familiar practice at the common law. The rule is undoubtedly settled, that, under all ordinary circumstances, the plaintiff who has but one cause of action will not be suffered to spread it upon the record in differing shapes and modes as though he possessed two or more distinct demands; and when he does so without special and sufficient reason, he will be compelled, either by a motion before the trial or by an application and direction, at the trial, to select one of these counts, and to abandon the others.”

*825 And so here, the third amended petition, as well as the three that preceded it, each made the contract a part thereof by reference, and declared a breach thereof by the defendant. The contract provided that the material and supplies when brought to the site of the work should become the property of plaintiff, and we do not doubt that a good cause of action ex delicto might have been stated for its wanton waste or destruction by defendant. Such acts would have been separate and apart from the execution of the contract. But no ease of that bind was attempted to be made. All allegations about destruction or waste of material were made not as independent causes of action but as instances of neglect of contractual duty to sustain the alleged breach and entitle plaintiff to general damages. We think it clear that plaintiff must rely on the contract and base its action thereon in seeking relief. The contract was made a part of the pleading and the allegations of the petition must be considered in connection with it.

The Contractor was to receive his net outlay in doing the work and a fee based on that outlay, as shown in Article III of the contract. Article IV provides for monthly settlements between the Contracting Officer and the Contractor to ascertain the cost for materials and labor during the preceding month, and a part of the fee based thereon, which were to be thereupon paid to the Contractor; and it says in reference to those settlements :

“The statement so made and all payments made thereon shall be final and binding upon both parties hereto.”

Because of the possible magnitude of the undertaking it was contemplated (Art. II) that the Contractor might need engineers, superintendents, time-keepers, foremen and other employes in connection with the work; but Article I expressly provided .that in the construction and completion of the cantonment the work should be done “in accordance with the drawings and specifications to be furnished by the Contracting Officer, and subject in every detail to his supervision, direction and instruction.” The Contracting Officer was given the right to make changes in the drawings and specifications so to be furnished, to require additional work, to direct the omission of work previously ordered, notifying the Contractor from time to time in regard thereto. It is obvious that the power and control of the Contracting Officer over the extent of the work to be done and his supervision and control during its progress were complete. The schedule fixing the fees shows that the work which the Contractor would be called on to do might be less than $100,000 and it might greatly exceed $3,500,000. All material, equipment, machinery and supplies delivered at the site of the work, upon inspection and acceptance in writing by the Contracting Officer, became the property of the United States. The contract itself says it is a departure from the usual procedure in the matter of letting contracts and that the method which it adopted was for the purpose of insuring the most expeditious results; it also recognized the existence of disturbed conditions in the contracting industry throughout the country. It is plain that the Contractor did not have a free hand. It was required to be constantly ready to receive directions and instructions about the work from the Contracting Officer. These stipulations, agreements and recitals in the contract are to be borne in mind when we come to consider the sufficiency- of the third amended petition.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Solorio v. Ducart
N.D. California, 2020
United States v. Richard M. Penta
940 F.2d 13 (First Circuit, 1991)
Sutton v. Eastern Viavi Co.
138 F.2d 959 (Seventh Circuit, 1943)
Wenzel & Henoch Const. Co. v. Metropolitan Water Dist.
18 F. Supp. 616 (S.D. California, 1937)
McCullough v. Clinch-Mitchell Const. Co.
71 F.2d 17 (Eighth Circuit, 1934)
United States v. Great Northern Ry. Co.
57 F.2d 385 (Eighth Circuit, 1932)
Dayton Airplane Co. v. United States
21 F.2d 673 (Sixth Circuit, 1927)
United States v. A. Bentley & Sons Co.
16 F.2d 895 (Sixth Circuit, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
14 F.2d 813, 1926 U.S. App. LEXIS 2113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-george-a-fuller-co-ca8-1926.