United States v. Everett Poarch

878 F.2d 1355, 35 Cont. Cas. Fed. 75,700, 1989 U.S. App. LEXIS 11321, 1989 WL 78569
CourtCourt of Appeals for the Eleventh Circuit
DecidedAugust 3, 1989
Docket88-3769
StatusPublished
Cited by10 cases

This text of 878 F.2d 1355 (United States v. Everett Poarch) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Everett Poarch, 878 F.2d 1355, 35 Cont. Cas. Fed. 75,700, 1989 U.S. App. LEXIS 11321, 1989 WL 78569 (11th Cir. 1989).

Opinion

GARZA, Senior Circuit Judge:

Everett Poarch was convicted of one count of conspiring to defraud the United States by impeding, impairing, obstructing, and defeating the lawful functions of the United States Department of Defense in its negotiation of a defense contract in violation of 18 U.S.C. Sec. 371, and one count of knowingly falsifying, concealing or covering up a material fact in a matter within the jurisdiction of the Defense Logistics Agency, in violation of 18 U.S.C. Secs. 1001 & 2. Specifically, Poarch was convicted of providing incomplete and misleading cost and pricing data on an aircraft renovation project on which he worked, as an employee of Aero Corporation, for the Department of Defense.

Poarch appeals his conviction, alleging discrepancies between the indictment and the jury charge, as well as arguing that he should have been granted a judgment of acquittal due to insufficiency of the evidence on the issue of Poarch’s duty to supply accurate and complete information regarding the contract hours to the government. Because we find Poarch’s allegations of error to be without merit, we must affirm his conviction.

Background

In the early 1980’s, Aero Corporation (“Aero”) successfully bid on and received a contract with the Department of Defense (“DOD”) for the rehabilitation of Air Force C-130 aircraft. Subsequent to the execution of the basic contract, Aero and DOD reached an agreement on a contract modification to structurally renovate the center *1357 wing section of the aircraft. While renovating the center wing area, Aero employees found that the electrical wiring in the center wing area was not serviceable, and negotiated a separate contract with the government to perform the necessary wiring on the center wing area; this rewiring was referred to as “over and above” work.

The basic contract was at a fixed-price, while the over and above work was performed at a rate of $22/hour. Aero and DOD agreed to a “learning curve” whereby Aero would be allotted 4200 hours to complete the first plane, with the time declining gradually to 3620 hours for the last plane. This time frame was based on representations by Aero that work on the first plane had taken about 4200 hours.

However, by Aero’s own admission, the work required on the first plane was less than 4200; actually, it was 8671.9. A government witness, Leon Wiggins, who was an Industrial Specialist under the supervision of Martha Wright, testified that he negotiated the pricing arrangement based on a representation by company employees that the work performed on the first aircraft had required 4200 hours.

An Aero employee testified that Everett Poarch, the Contracts Administrator for Aero, was aware of the practice at Aero of “upping” the hours required for a job during negotiations. Between March and May of 1984, Poarch stopped to talk to Steve Alford, a line employee, in the hangar where Alford worked. Poarch told Alford to “[b]e damn sure that you charge all the time to your wiring that goes there.” Alford asked him “What about my basic?” to which Poarch responded “Forget your basic, charge your over and above first. If you have work after that, then charge it to your basic.” This would have the effect of inflating the number of hours spent on over and above work at the expense of work correctly attributable to the basic contract, thus concealing the initial “upping” of contract hours required.

In late Summer of 1984, the Government Administrative Contracting Officer in charge of the Aero contract, Martha Wright, was informed by Wiggins that he was uneasy about the price that had been negotiated. On September 4, 1984, Wright sent a formal request to Aero requesting that the Government auditor be allowed access to records and data involving transactions related to the contract. Over the course of the next three weeks, Wright sent Aero several letters stating that submission by Aero of certified cost and pricing data was necessary, citing the Truth in Negotiations Act, 10 U.S.C. Sec. 2306(f) and the Federal Acquisition Regulations, 48 C.F.R. 15.804-2 as authority for the request.

After initially questioning Wright’s authority to demand the data, Aero ultimately provided a form containing data for the first fifteen aircraft on which work was performed. This form was prepared by Aero’s comptroller, Brenda Patterson-Ball, after discussion with Poarch. Patterson-Ball admitted that she had deliberately used incomplete data by including only 15 aircraft even though 41 or 42 had been completed in order to maximize the number of hours on the form. This is because the first aircraft took longer to renovate than the subsequent ones, and inclusion of only the early aircraft on the form would make the average hours reported on the form seem higher. Although this act formed one of the bases for Count II of the indictment of Aero, Poarch was not indicted in that count. Aero corporation provided the government with further data on January 23, 1985, in the form of a computer printout of labor hours to government auditor John Sears. However, the hours on this printout were incorrect due to Alford’s mischarging time on aircraft 34 through 50.

Aero and the government then entered into negotiations for a contract to perform center wing rewiring on aircraft 54 and subsequent aircraft. Sears analyzed the hours printout and advised Wright that an average of 2304 hours per aircraft was required. Wright then negotiated with Poarch for approximately three days, and they reached agreement that the contract for the subsequent aircraft would allow 2404 hours. After the negotiations, *1358 Wright sent Poarch a form under the Federal Acquisition Regulations containing a certificate that the data supplied were current, accurate, and complete, which Poarch signed.

Jury Instructions

Counts I and III of the indictment against Poarch charged that he had violated 18 U.S.C. Sec. 1001 by “falsifying, concealing and covering up” material facts within the jurisdiction of the Defense Logistics Agency. The court’s jury instructions, however, charged the jury that Poarch could be found guilty if he did “falsify, conceal or cover up” a material fact. Poarch argues that the use of the conjunctive “and” in the indictment but the disjunctive “or” in the jury instructions fundamentally an essential element of offense with which he was charged. This, argues Poarch, amounts to a constructive amendment to the indictment, which is reversible error per se. United States v. Peel, 837 F.2d 975, 979 (11th Cir.1988).

We do not agree that the court’s charge constituted a constructive amendment. A constructive amendment to the indictment occurs where the jury instructions so modify the elements of the offense charged that the defendant may have been convicted on a ground not alleged by the indictment. United States v. Lignarolo, 770 F.2d 971, 981 n. 15 (11th Cir.1985), cert. denied, 476 U.S. 1105, 106 S.Ct. 1948, 90 L.Ed.2d 358 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Jordan Leahy
Eleventh Circuit, 2025
Thomas v. United States
M.D. Florida, 2021
United States v. Julio Rolon
445 F. App'x 314 (Eleventh Circuit, 2011)
United States v. Vigil
478 F. Supp. 2d 1285 (D. New Mexico, 2007)
United States v. Hasner
340 F.3d 1261 (Eleventh Circuit, 2003)
United States v. Serges Jacques Descent
292 F.3d 703 (Eleventh Circuit, 2002)
United States v. Simpson
228 F.3d 1294 (Eleventh Circuit, 2000)
United States v. Dollar
25 F. Supp. 2d 1320 (N.D. Alabama, 1998)
United States v. Crop Growers Corp.
954 F. Supp. 335 (District of Columbia, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
878 F.2d 1355, 35 Cont. Cas. Fed. 75,700, 1989 U.S. App. LEXIS 11321, 1989 WL 78569, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-everett-poarch-ca11-1989.