United States v. Commonwealth of Massachusetts

890 F.2d 507, 1989 U.S. App. LEXIS 17709
CourtCourt of Appeals for the First Circuit
DecidedNovember 27, 1989
Docket89-1358
StatusPublished
Cited by12 cases

This text of 890 F.2d 507 (United States v. Commonwealth of Massachusetts) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Commonwealth of Massachusetts, 890 F.2d 507, 1989 U.S. App. LEXIS 17709 (1st Cir. 1989).

Opinion

TIMBERS, Circuit Judge:

The United States (“appellant”) appeals from an order entered March 3,1989 in the United States District Court for the District of Massachusetts, A. David Mazzone, District Judge, responding to objections by appellant to a plan submitted by the Commonwealth of Massachusetts (“appellee” or “Commonwealth”) to improve conditions at Worcester State Hospital, held that the plan complied with the terms of a consent decree entered into between the parties and approved by the court on August 25, 1987. The court also held that appellee’s efforts to provide staffing for the hospital, despite a slight shortfall, complied with the decree’s mandate.

On appeal, appellant argues: (1) that application of standard principles of contract interpretation compels us to rule that ap-pellee’s plan does not comply with the consent decree; and (2) that the staffing deficit is a substantial defect under the decree.

For the reasons set forth below, we affirm the district court’s order. 1

I.

We summarize only the prior proceedings and facts believed necessary to an understanding of the issues raised on appeal.

Appellee operates Worcester State Hospital, a facility for the mentally ill. In 1985, appellant commenced an action against the Commonwealth pursuant to 42 U.S.C. § 1997 et seq. (1988) (Civil Rights of Institutionalized Persons Act), alleging that conditions at the hospital violated the due process rights of its patients. The parties eventually reached a settlement agreement, which emerged as a consent decree when the district court endorsed it on August 25, 1987.

The consent decree consists of five substantive sections. Section one contains definitions of the relevant terms. Section two is a statement of the decree’s five purposes and objectives. 2 Section three requires that the hospital attain certain staffing ratios within six months of the entry of the decree, including registered nurse-patient and licensed practical nurse-patient ratios of 1:35 per shift, but states that appellee will not be in contempt of the agreement for good faith failure to meet the ratios due to unavoidable circumstances. Section four lists thirteen problem areas in the hospital that relate to the overall objectives, and requires that appellee submit a plan with “specific terms and reasonable *509 detail” to address them. Section five, on construction and implementation of the plan, leaves the specific means to achieve compliance to appellee.

The decree called for appellee to submit the plan by October 24, 1987, to be implemented no later than February 25, 1988. Appellant had until December 23, 1987 to file objections to the plan. Appellee timely filed its plan. Appellant objected to it, claiming that it did not contain the specificity and detail mandated by the decree.

The plan indeed is sketchy in several areas. For example, where the decree calls for a description of procedures to assure periodic professional evaluations of each hospital resident, the plan states that the hospital “will adopt a policy” to provide for the necessary evaluations. There are several other sketchy provisions.

The district court held a hearing on the adequacy of the plan on January 15, 1988. The court observed that the plan was a bit sparse on details, but deferred resolution of the dispute. Instead it asked appellee to provide further documentation 3 and appointed two compliance monitors to assure that appellee actually was implementing the improvements. The monitors eventually submitted two reports, dated January 9 and March 30, 1989, respectively. Both offered suggestions for improvement, but expressed general satisfaction with the hospital’s progress. The latter report stated that “[t]he Plan has provided a broad-based blueprint for this change.”

Both parties agree that the hospital failed to meet the staffing ratios by the deadline set by the decree. The monitors, however, perceived no serious problem with staffing, despite failure to meet the ratios provided in the decree and the continuing use of temporary agency nurses.

Although conditions were improving at the hospital, the parties failed to agree on the adequacy of the plan. On October 24, 1988 appellant moved by order to show cause for enforcement of the plan and staffing ratios and for a contempt judgment against appellee. The court heard arguments on the contempt issue on February 7, 1989 and ruled in appellee’s favor the same day. On March 3, 1989, it entered a memorandum and order finally approving appellee’s amended plan. 4

II.

In a commercial context, a consent decree may be treated like a contract. United States v. ITT Continental Baking Co., 420 U.S. 223 (1975). As a result, it should be construed primarily by reference to the four corners of the instrument. Thus an appellate court is given “considerable freedom” to review the findings of the district court in regard to a consent decree. AMF Inc. v. Jewett, 711 F.2d 1096, 1100 (1st Cir.1983). Appellant appears to place itself in the position of a private party to an agreement, complaining that it has not received the “benefits of the bargain” to which it is entitled. Appellant, however, is not really the recipient of the benefits of this bargain. The success of the consent decree and subsequent plan should be judged by their effect on the patients at the hospital.

Recognizing that in public litigation the beneficiaries are commonly third parties, several appellate courts have held that district courts, which are responsible for overseeing the execution of consent decrees, should have broad discretion in determining whether the objectives of the decree have been substantially achieved. We have stated that “in examining a decree issued in public law litigation ... the appellate court should recognize that broad ‘judicial *510 discretion may well be crucial' for the district judge to secure ‘complex legal goals.' ” Massachusetts Ass’n of Older Americans v. Commissioner of Public Welfare, 803 F.2d 35, 38 (1st Cir.1986) (quoting AMF, supra, 711 F.2d at 1101). See also Twelve John Does v. District of Columbia, 861 F.2d 295, 298 (D.C.Cir.1988); New York State Ass’n for Retarded Children v. Carey, 706 F.2d 956, 970 (2d Cir.), cert. denied, 464 U.S. 915 (1983).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rolland v. Patrick
946 F. Supp. 2d 226 (D. Massachusetts, 2013)
LATINO OFFICERS ASS'N CITY OF NY v. City of NY
519 F. Supp. 2d 438 (S.D. New York, 2007)
Laaman v. Powell
D. New Hampshire, 1995
Juan v. Weicker
37 F.3d 874 (Second Circuit, 1994)
Juan F. ex rel. Lynch v. Weicker
37 F.3d 874 (Second Circuit, 1994)
Unknown case name
First Circuit, 1993
Roberto Navarro-Ayala v. Rafael Hernandez-Colon
951 F.2d 1325 (First Circuit, 1991)

Cite This Page — Counsel Stack

Bluebook (online)
890 F.2d 507, 1989 U.S. App. LEXIS 17709, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-commonwealth-of-massachusetts-ca1-1989.