United States v. Carr

132 U.S. 644, 10 S. Ct. 182, 33 L. Ed. 483, 1890 U.S. LEXIS 1883
CourtSupreme Court of the United States
DecidedJanuary 6, 1890
Docket411
StatusPublished
Cited by30 cases

This text of 132 U.S. 644 (United States v. Carr) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States v. Carr, 132 U.S. 644, 10 S. Ct. 182, 33 L. Ed. 483, 1890 U.S. LEXIS 1883 (1890).

Opinion

Me. Chief Justice Fullee

delivered the opinion of the court.

The amount sued for was $782.17, of which the sum of $35.92, the aggregate of some small deductions upon other contracts, • was disallowed by the Court of Claims, and that result accepted by the claimant.

It' appears from the third finding that the Postmaster General deducted from the claimant’s compensation, under contract No. 46¡118, $746.25, “which deduction equals one-quarter of the total compensation fixed by the contract for Avhole service under it during the period covered by the alleged delinquency; ” being the three years and three-quarters from July 1, 1878, to March 31, 1882. It follows, then, that the contractor performed the service for the months of April, May and June, 1882, as required by the contract, as hereafter considered. As to $398 of the $746.25, that sum was withheld from the compensation under the contract in question, the last two quarters not having been paid, but the balance of $348.25 was deducted from moneys coming to the petitioner on other contracts, and he contends that it should not have been so deducted, because that amount had been voluntarily paid by the United States, and, therefore, could not be recovered back. But if the contractor was pot entitled to $746.25 of the compensation provided by this contract, and if payments were made thereon up to the last two quarters by mistake, for service that had not been performed, or under such circumstances as brought them within section 4057 of the Revised Statutes, then the payments could be recovered back, and their deduction in part from other money coming to *651 .petitioner was proper in the settleinent of the accounts between the parties.

Section 4057 is as follows:

“ In all cases where money has been paid out of the funds of the Post-Office-Department under the pretence that service has been performed therefor, when,, in fact, such service has not been performed, or as additional allowance for increased service actually rendered, when the additional allowance exceeds the sum which, according to law, might rightfully have been allowed thprefor, and in all other cases where money of the Department has been paid to any persón in consequence of fraudulent representations, or by the mistake, collusion, or misconduct of any officer or other employé in the postal serr vice, the Postmaster General shall cause suit to be brought to recover such wrong or fraudulent payment or excess, with interest thereon.”

- This section was applied in United States v. Barlow, ante, 271, 281, and Mr. Justice Field, in delivering the opinion, quotes with approval the language of Baron Parke in Kelly v. Solari, 9 M. & W. 54, 58, that “ where money is paid to another under the influence of a mistake, that is, upon the supposition that a specific fact is true, which would entitle the other to the money, but which fact is untrue, and the money would not have been paid if it had been known to the payer that the fact was untrue; an action will lie to recover it back, and it is against conscience to retain it; ” and adds: “ Seasons for the application of the rule are much more potent in the case of the contracts of the government than of contracts of individuals; for the government must necessarily rely upon the acts of agents, whose ignorance, carelessness or unfaithfulness would otherwise often bind it, to the serious injury of its operations.” Nothing more need bé said on this point, and this brings us to the real question in the case.

Claimant contracted to carry the mails from Salinas, by Santa Bita and Natividad, to Gabilan, 15 miles, and back.” The time to be taken on the trip was specified at six hours each- way. There is no ambiguity in this contract, from which a doubt could arise as to whether the return route was to be *652 identical with the outward route. Where places are designated as on the line of a mail route from one point to another and back, no reason is perceived for their omission on the return. There may be instances where retracing the road is not deemed important, or is impracticable in view of particular exigencies; but if so, the difference in route would be specified. And where the transportation is for a given number of miles and back, this does not mean the number named one way and an indefinite and less number the other.

The contractor was clearly required to return to Salinas from Gabilan by the same way he went to Gabilan from Salinas.

The Court of Claims did not take any other view of the language of the contract, but determined the case to the contrary, upon the ground that the contract had been otherwise “ construed by the claimant, and the responsible power of the defendants, and that construction became and was the contract at the time the services were performed covered by the period of deductions.” This conclusion is reached as to the Post-Office Department upon the reasoning that as “ it was the duty of the postmasters connected with the mail route at the termini to report to the department the manner in which the service was performed, and the presumption is, that they performed their duty and that the department was advised, not only during the time of the performance of the contract in controversy but the antecedent contracts, covering the same service embraced in contract No. 46,118 ;” and as the evidence was, “that on October 23, 1878, the Acting Second Assistant Postmaster General certified to the Auditor of the Treasury for the Post-Office- Department that for the quarter ending September 30, 1878, there had been no failure or delinquency in the execution of the contract upon the part of the contractor ; ” and as “ it is safe to assume that for all preceding payments the same certificate was made, based upon reports furnished by thó postmasters connected with route No. 46,118 ; ” the acts of “ the responsible officers, of the department being in possession of the same information and knowledge ” as the postmasters, “ commit the defendant to the construction of the agreement as placed upon it by the parties who performed *653 the labor of its execution, and who were cognizant of the mode in which it was performed.”

The Department did not direct or affirmatively permit the contractor to pursue the course he did, and if he could recover in whole or in part, upon-the ground of an acquiescence equivalent to assent in a certain mode of dealing with the subject matter of the contract, the burden was on him to show knowledge or information by the Department of his conduct in the premises. No evidence to establish such knowledge or information having been adduced, the case was made to rest upon the presumption that the postmasters at the termini, where the schedules of the time of the arrival and departure of the mails were kept and registers thereof made and returned, were acquainted with the terms of the contract and claimant’s non-compliance therewith, and this being presumed, upon the further presumption that they must have reported the failure in performance to the Department.

In United States v. Ross, 92 U. S. 281, 284, Mr. Justice Strong, speaking for the court, says:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fahey v. Whalen
84 Misc. 2d 1040 (New York Supreme Court, 1975)
Mount Sinai Hospital of Greater Miami, Inc. v. Weinberger
376 F. Supp. 1099 (S.D. Florida, 1974)
Hall v. City of Fayetteville
103 S.E.2d 815 (Supreme Court of North Carolina, 1958)
United States v. Lassoff
147 F. Supp. 944 (E.D. Kentucky, 1957)
Rockford Screw Products Co. v. Commissioner
21 T.C. 834 (U.S. Tax Court, 1954)
United States v. Williams
161 F.2d 835 (Second Circuit, 1947)
Bains v. Ensor
39 A.2d 62 (District of Columbia Court of Appeals, 1944)
American Sanitary Rag Co. v. United States
84 Ct. Cl. 417 (Court of Claims, 1937)
Bertrán de Picardo v. Domenech
48 P.R. 748 (Supreme Court of Puerto Rico, 1935)
de Picardo v. Domenech
48 P.R. Dec. 766 (Supreme Court of Puerto Rico, 1935)
United States v. Great Northern Ry. Co.
57 F.2d 385 (Eighth Circuit, 1932)
Esteves v. Registrar of Property of Aguadilla
43 P.R. 6 (Supreme Court of Puerto Rico, 1932)
Esteves v. Registrador de la Propiedad de Agitadilla
43 P.R. Dec. 7 (Supreme Court of Puerto Rico, 1932)
Nations v. United States
52 F.2d 97 (Eighth Circuit, 1931)
Commercial Casualty Insurance v. Southern Surety Co.
155 A. 391 (New Jersey Court of Chancery, 1931)
United States v. Golden
34 F.2d 367 (Tenth Circuit, 1929)
Roney v. Dothan Produce Co.
117 So. 36 (Supreme Court of Alabama, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
132 U.S. 644, 10 S. Ct. 182, 33 L. Ed. 483, 1890 U.S. LEXIS 1883, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-v-carr-scotus-1890.