United States Pipe & Foundry Co. v. Goerig

195 P.2d 91, 31 Wash. 2d 22, 1948 Wash. LEXIS 243
CourtWashington Supreme Court
DecidedJune 24, 1948
DocketNo. 30421.
StatusPublished
Cited by1 cases

This text of 195 P.2d 91 (United States Pipe & Foundry Co. v. Goerig) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Pipe & Foundry Co. v. Goerig, 195 P.2d 91, 31 Wash. 2d 22, 1948 Wash. LEXIS 243 (Wash. 1948).

Opinion

Schwellenbach, J.

— This is an appeal from judgments dismissing an action, after demurrers to the complaint had been sustained, the plaintiffs having elected to stand upon their complaint.

The complaint alleged the entering into of a contract on July 14, 1945, between Goerig & Philp and the city of Sunnyside, whereby Goerig & Philp agreed to construct a sewage disposal plant for the city for the agreed contract price of $157,613.40; that between August 1, 1945, and *23 April 13, 1946, plaintiffs furnished supplies to the contractors, on which there is a balance owing and.unpaid of $7,098.72; that said supplies were used for the benefit of and became a part of the sewage disposal plant.

That on or about the eighth day of October, 1946, and while the performance of said contract dated July 14, 1945, remained unfinished and uncompleted, the defendants, Goerig & Philp, and the defendant, city of Sunnyside, entered into a supplemental contract, whereby the said Goerig & Philp agreed to perform work unfinished under the original contract dated July 14, 1945.

That on or about the twenty-eighth day of January, 1947, and prior to the completion of the performance of the work by Goerig & Philp under the two contracts, the plaintiffs duly filed notice of claim with the city clerk, all in accordance with the provisions of Rem. Rev. Stat., § 1161 [P.P.C. § 180-47].

The complaint also alleged the execution of a performance bond, on July 16, 1945, by the Continental Casualty Company, as surety, in the sum of $157,613.40 on the first contract; and the execution of a performance bond, on November 13, 1946, by the Manufacturers’ Casualty Company, as surety, in the sum of $5,000, on the supplemental contract.

Exhibit B, made a part of plaintiffs’ complaint, is as follows:

“Supplemental Contract
Contract made 8 October 1946.
“Whereas contract made between parties June, 1945, to construct Sewage Disposal Plant stating F.W.A. No. etc.
“Whereas Party of the second part has been unable to perform any substantial amount of work on the project for the past three months or four months due to inability to obtain recirculation pumps and other items essential to the full completion of the present contract, and it is the desire of the F.W.A. to terminate that contract.
“It Is Mutually Agreed by and between the parties hereto the present contract shall be terminated and this supplemental contract shall be substituted for the present contract subject to the following conditions:
*24 “(1) The unfinished work shall be completed in accordance with the original plans and specifications.
“ (2) This supplemental contract shall be in full force and effect from the date it is executed. The terms and provisions of this contract do not alter or reduce the contractor’s obligations under the original contract which has been accepted as completed on October 7, 1946.
“ (3) The value of the work remaining to be performed— itemized statement total $5000.
“(4) The contractor shall furnish an indorsement on his insurance.
“(5) Upon compliance with the foregoing requirements, the City will pay to the contractor on or within 15 days after November 7, 1946, the balance due less the value of uncompleted work or $5000.
“(6) Upon completion of the uncompleted work, or any part thereof, the City will pay to the contractor not of tener than once each month 85% of the value of the work performed in the preceding month. Upon full completion and acceptance of the items covered by this supplemental contract the City will pay the retainage (30) days after the completion and acceptance.
“Executed in quadruplicate.
Address: By S. A. Rossier
Pier 65 Mayor
Foot of Lenora Street K. H. Stone
Seattle 1, Wash. City Clerk
Goerig & Philp
By A. J. Goerig
“Contract accepted by F.W.A. Nov. 27, 1946.”

Rem. Rev. Stat., § 1161, provides in part:

“. . . Provided, that such persons shall not have any right of action on such bond for any sum whatever, unless within thirty (30) days from and after the completion of the contract with an acceptance of the work by the affirmative action of the board, council, commission, trustees, officer, or body acting for the state, county or municipality, or other public body, city, town or district, ...”

Respondents claim that it appears upon the face of the complaint that appellants did not file their claim within the thirty-day period as required by the above statute so as to preserve their right of action against the respondent *25 bonding companies on their statutory performance bonds, and their lien upon the reserve fund in the hands of the city.

Our problem is to determine whether or not there was a completion of the contract of July 14, 1945, and an acceptance of the work by the affirmative action of the council.

In Puget Sound Bridge & Dredging Co. v. John & Bressi, 148 Wash. 37, 268 Pac. 169, we held:

“Rem. Comp. Stat., § 1161, providing for the protection of laborers and materialmen by a contractor’s bond on public work, upon their filing a claim within thirty days after ‘completion of the contract with an acceptance of the work’, refers to the final completion of the contract by the city or the sureties, and not to the time when the contractor abandons the work or is discharged for non-performance.”

In John Dower Lbr. Co. v. New Amsterdam Cas. Co., 152 Wash. 186, 277 Pac. 696, one Scott, on August 26, 1925, entered into a contract with the city of Sunnyside to drill a well. The contract provided:

“ ‘The price for such sinking and construction of city well to be the sum of $8 per foot, for the full depth of said well, not to exceed 1,000 feet. . . . The construction of said well shall be according to the plans and specifications prepared by the city engineer, to which reference is hereby made and considered as a part of this contract. . . . ’ ”

The specifications, attached to, and made a part of, the contract, read in part as follows:

“ ‘The work herein specified to be done under the direction of the city council. . . . The well shall be drilled in a workmanlike manner; bore to be straight and of such width as will permit the installation of a twelve-inch casing to bed rock which is estimated to be about two hundred feet. The contractor shall be required to drill the well to the depth required by the city council, which depth will not exceed 1,000 feet:’ ”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

National Blower & Sheet Metal Co. v. American Surety Co.
248 P.2d 547 (Washington Supreme Court, 1952)

Cite This Page — Counsel Stack

Bluebook (online)
195 P.2d 91, 31 Wash. 2d 22, 1948 Wash. LEXIS 243, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-pipe-foundry-co-v-goerig-wash-1948.