Union High School District No. 400 v. Pacific Northwest Construction Co.

269 P. 809, 148 Wash. 594, 1928 Wash. LEXIS 902
CourtWashington Supreme Court
DecidedAugust 21, 1928
DocketNo. 21199. Department Two.
StatusPublished
Cited by6 cases

This text of 269 P. 809 (Union High School District No. 400 v. Pacific Northwest Construction Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Union High School District No. 400 v. Pacific Northwest Construction Co., 269 P. 809, 148 Wash. 594, 1928 Wash. LEXIS 902 (Wash. 1928).

Opinions

*595 Askren, J.

Union High School District No. 400, of Whatcom county, Washington, had a new high school constructed in 1925 by the Pacific Northwest Construction Company, at a cost of approximately $90,000. The Fidelity and Deposit Company of Maryland issued the surety bond for the faithful performance of the contract. One William Mallis of Seattle, Washington, was the architect selected by the school board.

On November 24, 1925, the board passed the following resolution; which was duly spread upon the minutes:

“Motion by Hemingsen, seconded by Reed, that we accept the school building on Mr. Millis recommendation. Motion carried.”

On the 24th of December the clerk of the school board sent the following letter to the county auditor:

“This is to notify you that the thirty day period following the acceptance of the new Mt. Baker Union High School building by the board of directors expires today.”

At that time, there were several unpaid bills upon the job, for the payment of which the surety was bound under its bond. Those claims were as follows: George V. Nolte $768.28; Rainier Electric Company $885.00; D. A. Griffin & Co., $25.80, and Thiel & Welter, $140.00; or a total of $1,819.08. On May 1,1926, a new board of directors having been elected in the meantime, the following action was taken as evidenced by the minutes of the board:

“Motion by Mathews, seconded by Macauley, to accept the building with $272 for defects, carried.”

Within thirty days thereafter, each of the four claimants just referred to filed with the board a notice in writing making a claim for the amounts due them as against the bond issued by the surety. The school *596 district having on hand the sum of $1,863.72 filed a complaint in interpleader on July 7, 1926, and paid the money into the registry of the court, asking the court to settle the issue as to who was entitled to the fund. A further payment of $12.00 was later added thereto. George Y. Nolte, on behalf of himself and as assignee of the three other claimants, filed a cross-complaint asking for judgment against the contractor on the four claims referred to; that the amount thereof be declared a lien upon the money deposited with the court; and that, if the fund proved insufficient, that he recover from the surety any deficiency.

The surety filed an answer claiming the fund in controversy by virtue of the fact that it had been required to pay upwards of $5,000 to laborers and materialmen holding valid claims against the building, and by a valid assignment from the contractor to all money due on the contract.

The contractor answered admitting liability on three of the claims, but alleged that the claim of the Rainier Electric Company had been settled by that company accepting the notes of four individuals in payment thereof.

With the issues so made up, the case proceeded to trial. The court, after hearing, held that the four claims were not filed with the board within thirty days after the acceptance of the work, and were therefore not valid claims against the bond; awarded the fund on deposit to the surety; gave judgment against the contractor for three of the claims, but held that the Rainier Electric Company claim had been settled and refused any judgment thereon. From this disposition of the case, Nolte has appealed.

The issues in this case were narrowed in the trial .court and are limited here to two questions: (l)Was the building accepted on November 24, 1925, by the *597 board of directors under its resolution of that date, or by the resolution of the later board on May 1, 1926; and (2), Was there a novation as to the claim of the Rainier Electric Company? The answers to these questions will determine the controversy.

It is admitted by appellant that, under § 1161, Rem. Comp. Stat., it is necessary that claims be filed against the bond of a contractor within thirty days after the acceptance of the work; and therefore he strenuously asserts that the building was not accepted until the resolution of May 1, 1926. To support this assertion there was offered in evidence a letter from the architect to the school board dated November 23, 1925. It reads as follows:

Seattle, Washington, November 23, 1925
Mr. M. D. Macaulay,
Clerk School District No. 400,
Deming, Wn.
Mt. Baker Union High School Bldg.
Dear Sir:
We recommend that your board accept the General Contractors work on the above building on the following basis.
Contract price ............................ $86,886.31
Finished hardware ............. $800.00
Electric fixtures ................ 700.00 1,500.00
$85,386.31
355.12
346.99 8.13
$85,378.13
Deductions for defective shower room, plaster and boiler room floor................................. 30.00
$85,348.18
Deduction by owner
Damages by delay............ $170.00
Fire insurance .....................
Electrical current ..................
We have not the amount of the last two items which the contractor agreed to pay.
The contractor, is required to make good all the items in our letter of October first, 1925, addressed to him and all the conditions of our letter to him of this date otherwise this acceptance is null and void and all the conditions of the contract to remain in effect.
Yours truly,
WM/A (Signed) Wm. Mallis.
Deductions
Additions

*598 It is said that, since the letter of the architect refers to certain things that the contractor is required to do, the action of the board on the following day could be nothing more than a conditional acceptance — not to become final until the things referred to therein had been performed by the contractor.

The difficulty facing this argument is that the resolution of acceptance does not appear to be conditional. It is an absolute acceptance of the building. Appellant attempts to meet this with a construction of the words “on Mr. Mallis’ recommendation.” The argument is that these words require construction, and that Mallis’ letter, when referred to in aid of their construction, shows that he intended only a conditional acceptance; that the board acting thereon did and could make only a conditional acceptance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boise Cascade Corp. v. Distinctive Homes, Inc.
407 P.2d 452 (Washington Supreme Court, 1965)
National Blower & Sheet Metal Co. v. American Surety Co.
248 P.2d 547 (Washington Supreme Court, 1952)
United States Pipe & Foundry Co. v. Goerig
195 P.2d 91 (Washington Supreme Court, 1948)
Kirkpatrick v. Douglas
65 P.2d 1169 (Montana Supreme Court, 1937)
Seattle Plumbing Supply Co. v. Maryland Casualty Co.
276 P. 552 (Washington Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
269 P. 809, 148 Wash. 594, 1928 Wash. LEXIS 902, Counsel Stack Legal Research, https://law.counselstack.com/opinion/union-high-school-district-no-400-v-pacific-northwest-construction-co-wash-1928.