United States of America v. Nova Group Inc

District Court, W.D. Washington·Decided October 22, 2021·No. 3:20-cv-05954·Unknown

Opinion

1 2 3

5 UNITED STATES DISTRICT COURT 6 WESTERN DISTRICT OF WASHINGTON AT TACOMA 7 UNITED STATES OF AMERICA, for CASE NO. C20-5954 BHS-DWC 8 the use and benefit of BALLARD MARINE CONSTRUCTION, LLC, ORDER ON MOTION FOR 9 RECONSIDERATION Plaintiff, 10 v. 11 NOVA GROUP INC., et al., 12 Defendants. 13

THIS MATTER is before the Court on Plaintiff Ballard Marine’s Motion for 14 Reconsideration or Clarification, Dkt. 73, of the Court’s Order, Dkt. 72, adopting the 15 Magistrate Judge’s Report and Recommendation (“R&R”), Dkt. 61. The Court stayed 16 Ballard’s Miller Act claim pending resolution of the “upstream” Contracts Dispute Act 17 (“CDA”) process, as required in the Prime Contract between the Navy and Nova, which 18 was incorporated into the Subcontract between Nova and Ballard. Dkt. 72 at 16. 19 Ballard seeks clarification on the extent of the stay, arguing that the Court’s Order 20 contemplated that the CDA process, and thus the stay, would conclude when the Navy 21 Contracting Officer issued a final decision on Nova’s “pass through” claim to the Navy— 22 1 which is expected at the end of this month. Dkt. 79-1 at 1. It argues that if the Court 2 intends to stay the case until all possible appeals of that decision are exhausted, it will 3 potentially force Ballard to wait until 2026 to assert its claims against Nova and the

4 sureties and to obtain payment for the work it has already performed. Dkt. 73 at 2. If that 5 was the Court’s intent, it asks the Court to Reconsider its Order granting a stay, arguing it 6 would conflict with the Miller Act’s purpose and with fundamental equity. Dkt. 73 at 6– 7 7. 8 Nova and its sureties reiterate that the Subcontract requires Ballard to await the

9 resolution of the CDA process—the determination of the amount of additional payment 10 to which it is entitled—before pursuing Nova or its sureties for that additional payment. 11 Dkt. 77. They ask the Court to confirm that it stayed the case until that determination is 12 made, and to deny Ballard’s motion for reconsideration. Id. at 10. 13 Under Local Rule 7(h)(1), motions for reconsideration are disfavored, and will

14 ordinarily be denied unless there is a showing of (a) manifest error in the ruling, or (b) 15 facts or legal authority which could not have been brought to the attention of the court 16 earlier, through reasonable diligence. The term “manifest error” is “an error that is plain 17 and indisputable, and that amounts to a complete disregard of the controlling law or the 18 credible evidence in the record.” Black's Law Dictionary 622 (9th ed. 2009).

19 Reconsideration is an “extraordinary remedy, to be used sparingly in the interests 20 of finality and conservation of judicial resources.” Kona Enters., Inc. v. Est. of Bishop, 21 229 F.3d 877, 890 (9th Cir. 2000). “[A] motion for reconsideration should not be granted, 22 absent highly unusual circumstances, unless the district court is presented with newly 1 discovered evidence, committed clear error, or if there is an intervening change in the 2 controlling law.” Marlyn Natraceuticals, Inc. v. Mucos Pharma GmbH & Co., 571 F.3d 3 873, 880 (9th Cir. 2009). Neither the Local Civil Rules nor the Federal Rules of Civil

4 Procedure, which allow for motions for reconsideration, are intended to provide litigants 5 with a second bite at the apple. A motion for reconsideration should not be used to ask a 6 court to rethink what the court had already thought through—rightly or wrongly. Defs. of 7 Wildlife v. Browner, 909 F.Supp. 1342, 1351 (D. Ariz. 1995). 8 Ballard argues that the CDA process, including appeals, could take years to fully

9 resolve. It claims that the initial “pass through” portion of that process, in which the 10 contractor (here, Nova) submits a claim to the appropriate government agency (here, the 11 Navy) for a “final decision” on payment, is the appropriate length of any stay. It asks the 12 Court to clarify that, in its discretion, that is what the Court ordered when it adopted the 13 Magistrate Judge’s R&R. Dkt. 73 at 4.

14 Ballard emphasizes the multi-step CDA appeals process, on the other hand, 15 involves not just the Navy, but multiple appellate tribunals. In its reply, Ballard argues 16 that after the initial pass-through process, Nova will not be attempting to persuade the 17 Navy—its contracting partner—of the legitimacy of Ballard’s claim, but instead must 18 convince an independent tribunal of the right to additional compensation for the differing

19 site conditions it and Ballard encountered. Dkt. 81. Unlike the almost-complete pass- 20 through process, the CDA appeals process could take years, unfairly delaying payment 21 for work it has long since completed. Id. 22 1 Nova1 accurately characterizes Ballard’s motion as a repeat of the arguments it 2 made in opposition to a stay before the Magistrate Judge and in its objections to the 3 R&R. The sureties emphasize that they moved for a stay of Ballard’s claims against them

4 until a final determination of the amount owed under the subcontract, including any 5 potential appeals of the Navy’s Contracting Officer’s final decision, consistent with the 6 Subcontract. Dkt. 79 at 2. They emphasize that the R&R accurately reflected this request, 7 Dkt. 61 at 9 (“The Sureties move . . . to stay Ballard’s claims against them until Ballard’s 8 differing site conditions claim is resolved in accordance with the Subcontract between

9 Nova and Ballard, because at present there is no ‘amount due’ under the contract.”), and 10 recommended that this Court grant that motion, which it did, Dkt. 72. 11 Nova argues, persuasively, that the Miller Act was “never intended to allow 12 subcontractors to bypass the process under which their monetary entitlement is 13 quantified—a claim process under the Contract Disputes Act that controls all claims

14 against a Government owner for Differing Site Conditions.” Dkt. 77 at 3. Indeed, it 15 argues, permitting a subcontractor to pursue a claim for payment from the prime 16 contractor’s surety before the amount of its additional2 entitlement is determined (and 17 notwithstanding the contracts’ requirements) would turn both the subcontracting and the 18 surety industries “upside down.” Dkt. 84 at 3. Ballard explained its view of the procedure

19 in an August 2020 letter to Nova, explaining that its reading of the contracts, the CDA, 20

1 Nova’s Motion for Leave to File a Surreply, Dkt. 83, is GRANTED. 21 2 Ballard has been paid both its initial subcontract amount and, recently, an 22 additional $1,947,994.96. See Carlson Decl., Dkt. 78, at Exs. 1–4. 1 and the Miller Act would result in prompt payment, after which Nova and its sureties 2 could pursue “reimbursement” from the government, through the CDA process: 3 The bond claim process, if carried out by the sureties reasonably and in good faith, will result in payment to Ballard in the very near future. As 4 such, the claim against the Government will, essentially, be a means for Nova or its sureties to obtain reimbursement for that payment. 5 Dkt. 78 at 17, Ex. 5. None of the authorities upon which Ballard relies support its 6 claim that this is how the statutes or the contracts work. 7 As Nova argues, each of the cases Ballard cites for the proposition that a stay 8 pending the CDA appeals process is inconsistent with the Miller Act’s purpose involved 9 some sort of unusual fact pattern or “special circumstance” not present in this case. In 10 Pinnacle Crushing and Constr., LLC v. Hartford Fire Ins. Co., No. C17-1980JLR, 2018 11 WL 1907569, at *2 (W.D. Wash. April 23, 2018), the prime contractor had defaulted on 12 the contract and had been terminated. In Walton Tech., Inc. v. Weststar Eng’g, Inc., 290 13 F.3d 1199, 1202 (9th Cir.

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America v. Nova Group Inc, (W.D. Wash. 2021).

United States of America v. Nova Group Inc (United States of America v. Nova Group Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related