United States of America v. Nova Group Inc

District Court, W.D. Washington·Decided July 27, 2021·No. 3:20-cv-05954·Unknown

Opinion

UNITED STATES DISTRICT COURT AT TACOMA UNITED STATES OF AMERICA, for CASE NO. C20-5954BHS-DWC the use and benefit of BALLARD MARINE CONSTRUCTION, LLC, ORDER ADOPTING REPORT Plaintiff, v. NOVA GROUP INC, et al., Defendants.

THIS MATTER is before the Court on the Report and Recommendation (“R&R”) of the Honorable David W. Christel, United States Magistrate Judge, Dkt. 61, resolving seven pending motions in this Miller Act case: (1) Defendant Sureties Federal Insurance Company and Liberty Mutual Insurance Company’s Motion to Dismiss Plaintiff Ballard Marine Construction’s extracontractual claims against them, Dkt. 14; (2) Defendant general contractor Nova Group, Inc.’s Motion to Dismiss Ballard’s claims against it for lack of subject matter jurisdiction, Dkt. 20; (3) Ballard’s Motion for Partial Summary Judgment on its payment claims against the sureties, Dkt. 30; (4) Federal and Liberty Mutual’s Alternative Motion to Stay, Dkt. 38;

(5) Ballard’s Motion to Strike, Dkt. 39; (6) Federal and Liberty Mutual’s Motion to Strike Ballard’s Reply, Dkt. 57; and; (7) Ballard’s Motion to Strike the Sureties’ Reply, Dkt. 58. There are four objections to the proposed resolution of these motions, two of which are substantive. The Court has reviewed the underlying motions, the Report and

Recommendation, the objections, and the responses to those objections. In 2016, the United States Navy hired a general contractor, Nova, to repair a fire suppression system at the Puget Sound Naval Shipyard. Nova hired Ballard as a subcontractor. The Subcontract price was $2,657,576. Under the Miller Act, 40 U.S.C.

§§ 3131–34, Nova (as principal) obtained from sureties Federal Insurance and Liberty Mutual payment bonds with a cumulative penal sum of $10,692,000. The Miller Act requires such bonds to ensure that subcontractors like Ballard are paid even if the general contractor does not or cannot pay them. Dkt. 47-1. Nova and Ballard encountered “differing site conditions” during the project.

Ballard claims that it was instructed to continue performing and to “track its [increased] costs.” Dkt. 47-5. Ballard completed its work in June 2020. It sought $13,301,285.281 1 Ballard Marine seeks this amount in addition to the subcontract price, which it has been paid. from Nova, and Nova declined to pay until the resolution of its “pass through” claim for the additional cost from the Navy. Ballard then sought payment from the sureties. Dkts. 17 at 50 and 31-3. The sureties similarly declined to pay, explaining that there was no

unpaid amount due under the Miller Act. Dkt. 51-6 at 2. Ballard notified the sureties that it was going to assert claims under Washington’s Insurance Fair Conduct Act, Chapter 48.30 RCW, et seq., (“IFCA”) and Consumer Protection Act, Chapter 19.86 RCW, et seq. (“CPA”). Meanwhile, Nova had submitted to the Navy a pass-through claim for payment of

the additional costs Ballard (and Nova) had incurred on the project, totaling more than $20,000,000. Dkt 21-3. In June 2020, the Government acknowledged receipt of Nova’s claim and informed it that the contracting officer would issue a decision by the end of July 2020. Dkt. 21-4. That estimated date was later revised to April 30, 2021 because the Navy requested an audit of Nova’s increased cost claim Dkt. 21-7.

Ballard sued Nova and the sureties in September 2020. It seeks payment under the Subcontract and under the surety’s payment bonds. Ballard also seeks exemplary (trebled) damages from the sureties under the IFCA and the CPA. The sureties seek dismissal of Ballard’s IFCA and CPA claims, arguing that as a third-party claimant it does not have statutory standing to assert those claims against a

surety. Dkt. 14. The R&R, Dkt. 61, recommends that the Court deny the sureties’ Motion to Dismiss, Dkt. 14, and the sureties object, Dkt. 62. Nova also seeks dismissal, Dkt. 20, arguing that this Court does not have subject matter jurisdiction over Ballard’s claim. It argues that Ballard’s “immediate payment” claim for differing site conditions against Nova is governed by Contract Disputes Act (“CDA”), which divests the Court of jurisdiction. To the extent Ballard has other claims against Nova, it argues, they are subject to the subcontract’s arbitration provision.

Ballard does not oppose dismissal of its payment claim against Nova. It does move to strike the sureties’ joinder in Nova’s motion, Dkt. 34. The R&R recommends granting Nova’s Motion to Dismiss (as to Nova, not as to the sureties) and denying as moot Ballard’s Motion to Strike. Ballard does not object to either proposed ruling. Accordingly, the R&R on these points is ADOPTED, and Nova’s Motion to Dismiss

Ballard’s payment claim against it, Dkt. 20, is GRANTED and that claim is DISMISSED without prejudice. Ballard’s Motion to Strike, Dkt. 39, is DENIED. Ballard seeks partial summary judgment on its payment claim against the sureties. Dkt. 30. The R&R recommends denying the motion without prejudice pending resolution of the CDA process. Ballard does not object. Accordingly, the R&R on this point is

ADOPTED, and Ballard’s Motion for Partial Summary Judgment, Dkt. 30, is DENIED without prejudice to re-file. The sureties move in the alternative to stay the case, Dkt. 38, until Ballard’s differing site conditions claim is resolved under the subcontract and the CDA, arguing that until that occurs, there is “no amount due” under the contract. The R&R recommends

granting the Motion to Stay, and Ballard objects, Dkt. 64. The sureties’ response, Dkt. 68, asks this Court to strike Ballard’s objection as over-length. Federal and Liberty Mutual’s Surreply, Dkt. 57, includes a Motion to Strike Ballard’s Reply, Dkt. 53, in support of its Motion for Partial Summary Judgment, Dkt. 30, arguing it was untimely and over-length. The R&R recommends granting the Motion to Strike. Although Ballard does not object to the denial of its underlying partial summary judgment motion, it does object to the R&R’s proposed resolution of the

sureties’ Motion to Strike one of its briefs in support of that motion. Dkt. 63. The sureties’ response to that objection, Dkt. 68, asks this Court to strike Ballard’s objection, Dkt. 63, as over-length under the Local Rules. Ballard’s own Surreply, Dkt. 58, includes a Motion to Strike the sureties’ overlength reply, Dkt. 52, in support of its their Alternative Motion to Stay, Dkt. 38,

arguing it was untimely and over-length. The R&R recommends granting in part the Motion to Strike. The sureties did not object. Accordingly, the R&R on this point is ADOPTED, and Ballard Marine’s Motion to Strike, Dkt. 58, is GRANTED IN PART. Finally, Nova objects to two sentences in the R&R, which it suggests may be factual findings and which it claims are not accurate. Dkt. 65. It asks the Court to revise

the R&R’s statements. Ballard responds that the statements are accurate. Dkt. 70. The R&R’s disputed proposed rulings are addressed in turn. A district judge must determine de novo any part of a magistrate judge’s proposed disposition that has been properly objected to. The district judge may accept, reject, or

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America v. Nova Group Inc, (W.D. Wash. 2021).

United States of America v. Nova Group Inc (United States of America v. Nova Group Inc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Amelco Electric v. Donald M. Drake Co.
583 P.2d 648 (Court of Appeals of Washington, 1978)
Tank v. State Farm Fire and Casualty Co.
715 P.2d 1133 (Washington Supreme Court, 1986)
Trinity Universal Insurance v. Ohio Casualty Insurance
312 P.3d 976 (Court of Appeals of Washington, 2013)
Pemberton v. Wendt
198 Wash. 6 (Washington Supreme Court, 1939)
Navigators Specialty Insurance v. Christensen Inc.
140 F. Supp. 3d 1097 (W.D. Washington, 2015)