United States of America v. Metropolitan District Commission

930 F.2d 132, 21 Envtl. L. Rep. (Envtl. Law Inst.) 20963, 32 ERC (BNA) 2011, 1991 U.S. App. LEXIS 7118, 1991 WL 61789
CourtCourt of Appeals for the First Circuit
DecidedApril 22, 1991
Docket91-1337
StatusPublished
Cited by11 cases

This text of 930 F.2d 132 (United States of America v. Metropolitan District Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America v. Metropolitan District Commission, 930 F.2d 132, 21 Envtl. L. Rep. (Envtl. Law Inst.) 20963, 32 ERC (BNA) 2011, 1991 U.S. App. LEXIS 7118, 1991 WL 61789 (1st Cir. 1991).

Opinion

BREYER, Chief Judge.

On February 25, 1991, the district court entered an order in the Boston Harbor Clean-up case that, in effect, says that the Commonwealth 1) must give the Massachusetts Water Resources Authority (MWRA) the power “to acquire a ... suitable ... landfill” site, and 2) may not hook up any new sewer lines emptying into Boston Harbor until it does so. The Commonwealth appeals, arguing that the order (along with the court’s April 5 refusal to modify the order) is unreasonable. For that reason, it says, the court’s actions are unlawful. We have expedited proceedings in the appeal. After holding oral argument, reading the briefs, and examining the record, we decide that the orders are reasonable and, consequently, lawful. We therefore affirm the orders and deny, as moot, the Commonwealth’s motion for a stay pending appeal.

I

Background

To appreciate the basis for the district court’s orders, and for other reasons, the reader must understand something of the history of this case. We have set out a chronology of the ease in an Appendix. We shall summarize the key matters that the chronology reveals.

1) The Commonwealth, for more than fourteen years, has unlawfully discharged sewage into Boston Harbor, in violation of the Federal Clean Water Act. 33 U.S.C. §§ 1251 et seq. The Conservation Law Foundation, in 1983, and the United States, in 1985, brought separate suits (later consolidated) to stop this discharge. On September 5, 1985, the district court found that the Commonwealth was guilty of “persistent and severe violations of the Act.” United States v. Metropolitan District Commission, 23 Env’tRep.Cas. (BNA) 1350, 1358, 1985 WL 9071 (D.Mass.1985).

2) The district court, in developing a remedy for the violations of law, did not enjoin the further discharge of pollutants, although the statute made this remedy available. See 33 U.S.C. § 1342(h) (authorizing ban on new sewer hook-ups). Rather, together with the parties, the court developed a 15-year Compliance Plan. The Plan calls for the construction, by December 1999, of a new $6 billion sewage treatment system for the metropolitan Boston area. The detailed remedial schedule contains specific deadlines for the building and opening of numerous facilities. Among other things, it requires that the MWRA build a plant that will turn sludge into fertilizer, which it may then sell. It also requires construction of a “landfill” to hold grit and sediment, as well as any sludge that is not sold as fertilizer. The MWRA is to oversee, and to implement, the plan.

*134 3) The landfill is a key element of the remedial program. The plan requires the MWRA to prepare a final landfill design by November 1991, to begin construction by September 1992, and to commence operation of the landfill (in coordination with the opening of a new sludge-into-fertilizer plant) by March 1994.

4) In 1986, the MWRA began a five-year effort to find a suitable landfill location. It surveyed 299 potential sites and eventually narrowed the number to two: Walpole, the preferred site, and Rowe Quarry in Mal-den/Revere. By late 1990 and early 1991, the MWRA had obtained all needed environmental approvals, and all other necessary action from various state and federal agencies, with respect to the Walpole site, with one exception (discussed in the next paragraph). The MWRA so far has spent $10 million on this site-selection process.

5) Under state law, the state legislature must approve any transfer of the Walpole site to the MWRA from its current owner, the Department of Correction. See, e.g., Mass.Gen.Laws ch. 7, §§ 40E-40J. In December 1990, the legislature voted not to approve a bill that would have given the MWRA the authority needed to obtain the site. Thus, as far as state law is concerned, the MWRA cannot begin to build the needed landfill at Walpole or anywhere else.

6) Ever since May 1989, when the MWRA designated its landfill alternatives, the court has pointed out that timely acquisition of a site is essential. In July 1990, when the legislature deferred action on the necessary legislation for six months, the court expressly warned that it might have to forbid additional new sewer discharges into the harbor, in order to avoid jeopardizing the schedule, and (in the absence of scheduling certainty) to prevent added pollution. In December 1990, in response to the legislature’s rejection of a transfer bill, the United States asked the court 1) to order the transfer of the Walpole site to the MWRA directly, and to enjoin enforcement of state law to the contrary; 2) to order the Commonwealth to approve the transfer itself; or 3) to order the Commonwealth not to connect new sewer hook-ups to the Harbor discharge system until the MWRA had authority to acquire a suitable landfill site. The court chose this last option, entering its “ban or transfer” order on February 25, 1991.

7) On April 1, 1991, the Commonwealth established a Commission to look for alternative landfill sites. The Commission is to report within 120 days. If the Commission finds an alternative site, the Commonwealth says it will submit that site to the court for approval. If the court rejects the alternative site, or if the Commission finds none within 120 days, the Commonwealth promises to pursue a plan to lease the Walpole site to the MWRA for 28 years, and to use its best efforts to obtain legislative approval for such a lease.

8) On April 2, 1991, the Commonwealth asked the district court to modify its order, suspending the sewer hook-up ban, pending receipt of the Commission’s report. On April 5, the district court denied the Commonwealth’s motion. The Commonwealth now appeals both the February 25 order and the April 5 refusal to modify.

II

Reasonableness

The Commonwealth agrees with the propositions set forth above. It concedes that a landfill site is needed, and that its timely acquisition is critical if the Commonwealth is to meet the court’s schedule and comply with the law. The Commonwealth also told the district court, on April 5, 1991, that “the only site we know of today that we know will meet the schedule” is Walpole. But, it says, the newly elected State Administration should have 120 days to find an alternative site; in the meantime, in the Commonwealth’s view, the MWRA should remain without the authority to use state land or acquire other land by eminent domain in order to obtain a suitable site. And, the Commonwealth adds, it is unreasonable for the district court to order the contrary — in particular, to force a change in state law (giving the MWRA a site, or site-acquisition power) through the use of so serious a sanction (a prohibition of new sewer connections).

*135 After reviewing the law, the record, and the arguments, we agree with the United States that the district court acted lawfully in imposing a ban on new sewer hook-ups until the MWRA receives site-acquisition authority.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
930 F.2d 132, 21 Envtl. L. Rep. (Envtl. Law Inst.) 20963, 32 ERC (BNA) 2011, 1991 U.S. App. LEXIS 7118, 1991 WL 61789, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-v-metropolitan-district-commission-ca1-1991.