United States of America f/u/b/o Aarow Electrical Solutions, LLC v. Liberty Mutual Insurance Co.

District Court, E.D. Virginia·Decided September 12, 2026·No. 1:25-cv-01236·Unknown

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF VIRGINIA Alexandria Division

UNITED STATES OF AMERICA, ) f/u/b/o Aarow Electrical Solutions, LLC, ) ) Plaintiff, ) ) v. ) Civil Action No. 1:25-cv-01236 (AJT/IDD) ) LIBERTY MUTUAL INSURANCE CO. ) ) Defendant. )

MEMORANDUM OPINION AND ORDER In this Miller Act1 case, Plaintiff-Relator Aarow Electrical Solutions, LLC (“Aarow” or “Plaintiff”), an electrical subcontractor on a federally-funded construction project in Quantico, Virginia, seeks to recover unpaid fees in the amount of $5,275,043 from the prime contractor’s surety, Defendant Liberty Mutual Insurance Company (“Liberty,” or “Defendant”). Pending before the Court is Liberty’s Motion for Partial Summary Judgment ([Doc. No. 45] (the “Motion”) in which it contends that Aarow lacks sufficient evidence as a matter of law to recover three specific categories of damages that collectively constitute at least $3,754,424 of Plaintiff’s total damages claim in the amount of $5,275,043, and that Aarow’s maximum recoverable claim at trial is therefore limited at most to $1,353,038. The three issues central to Liberty’s Motion are (1) whether the governing subcontract’s “No-Damages-for-Delay” clause is enforceable, (2) whether Aarow meets the prerequisites to recover home office overhead costs, and (3) whether pursuant to the Subcontract and Contract

1 The Miller Act provides a cause of action for any parties that provide labor or material for a federally-funded construction project to recover sums justly due. 40 U.S.C. §§ 3131- 3133. Its specific provisions require prime contractors to post payment bonds, require the Federal Acquisition Regulation to provide alternative protections to suppliers, and grants a private right of action to any subcontractors or suppliers to recover against the prime for any costs unpaid for 90 days or more. Id. Disputes Act, 41 U.S.C. § 7103(g), Aarow waived its right to seek costs incurred from replacing allegedly-noncompliant metal-clad cable (“MC Cable”) work by failing to appeal the government contracting officer’s final determination of noncompliance . For the reasons below, the Motion is GRANTED as to Arrow’s claim for delay damages,

which include its claimed unabsorbed home office overhead costs, and is DENIED as to Aarow’s purported waiver of its right to recover the MC Cable claim. I. BACKGROUND The following facts are undisputed unless otherwise indicated: A. Background on the Project and Contract Structure This action arises out of the construction of the P021 Middle School/High School Replacement Project at Marine Corps Base Quantico, Virginia (the “Project”). The United States Government, acting through the Naval Facilities Engineering Command Washington, awarded the prime contract for the Project to John C. Grimberg Co., Inc. (“Grimberg”) on November 20, 2017. [Mot.] at 2 ¶ 1; [Doc. No. 38] ¶ 1. Pursuant to the Miller Act, Grimberg furnished a

payment bond for the Project, with Liberty as surety. [Mot.] at 2 ¶ 2; [Doc. No. 1-1]; [Doc. No. 38] ¶ 3. The bond was intended to secure payment to subcontractors furnishing labor and materials to the Project. Id. On December 11, 2017, Grimberg entered into a subcontract with Aarow (the “Subcontract”) in which Aarow agreed to furnish and install electrical work in strict accordance with the Prime Contract documents. [Mot.] at 2–3 ¶¶ 3-5; [Doc. No. 38] ¶¶ 4-6; [Doc. No. 46-3] at 2. Maryland law governs the Subcontract, except as required by controlling law. [Mot.] at 3 ¶ 6; [Doc. No. 38] ¶ 14(k); [Doc. No. 46-3] at 7 ¶ 33. The Subcontract incorporated certain of Grimberg’s standard terms and conditions (“STC”), including a “No-Damages-for-Delay” clause in paragraph 9 which limited the remedies available to Aarow for delays to work under the subcontract. [Mot.] at 7 ¶ 30; [Doc. No. 38] ¶ 14(f); [Doc. No. 46-3] at 5 ¶ 9. This clause provided different remedies depending on which

party or nonparty caused the delay in question: for delays caused by Grimberg, Aarow was entitled only to a time extension and no monetary compensation, even if such delays were not contemplated, amount to abandonment, or were caused by active interference. Id. For delays caused by the Government, by nonparties, or those otherwise outside of Grimberg’s control, Aarow was entitled to be reimbursed for delay damages actually recovered by Grimberg from the Government. [Mot.] at 7 ¶¶ 28-29; [Doc. No. 38] ¶¶ 14(e)-(f). The Subcontract also contained a “flow-down” provision (at STC ¶ 1) which purported to impose on Aarow all of Grimberg’s obligations, risks, responsibilities, and rights under the prime contract.2 [Mot.] at 3 ¶ 8; [Doc. No. 38] ¶ 14(a); [Doc. No. 46-3] at 4 ¶ 1. The original Subcontract sum was $7,125,000, later increased by change orders to

$8,600,004.26. [Doc. No 46] at 4 ¶ 10; [Doc. No. 38] ¶ 7; [Doc. No. 46-6]. As of January 22, 2026, Grimberg had paid Aarow $7,889,648.60. [Mot.] at 4 ¶ 11; [Doc. No. 38] ¶ 8; [Doc. No. 46-6]. B. Project Implementation and Suspension of Work The Subcontract identified an original Contract Completion Date (“CCD”) of January 11, 2020 for the school building, based on a notice to proceed date of December 7, 2017. [Mot.] at 4

2 Specifically, the flow-down provision states that “[e]xcept as otherwise provided in this Subcontract Agreement, the Subcontractor shall be bound to Grimberg in the same way that Grimberg is bound to the Owner under the Prime Contract Documents, and the Subcontractor shall assume toward Grimberg all of the obligations, risks and responsibilities which Grimberg has assumed toward the Owner under the Prime Contract Documents.” The same provision confers on Aarow the right “to enforce all of its rights and remedies and to defend against claims against it by the Owner” according to the terms of the subcontract’s disputes section. [Mot.] at 3 ¶ 8. ¶ 13; [Doc. No. 46-3] at 1. The baseline schedule contemplated that Aarow would complete its work prior to the CCD. [Opp.] at 3–4; [Doc. Nos. 49-50]; [Doc. No. 46-8] at 21 ¶ 5.2.5. The original CCD was subsequently extended multiple times, and still had not been achieved as of the filing of the Motion. [Doc. No. 38] ¶¶ 15, 23-24.

On June 26, 2020, the Government suspended all work on the Project. [Mot.] at 4 ¶ 15; [Doc. No. 38] ¶ 15. The suspension stemmed from concerns regarding the structural integrity of Insulated Concrete Form (“ICF”) walls installed as part of the school building, specifically, that Grimberg’s subcontractor in charge of building the ICF walls, Progressive Construction Solutions (“PCS”), improperly placed steel reinforcement bar within (rather than outside) the ICF wall forms. [Opp.] at 4–5, 12–13; [Doc. No. 50] ¶¶ 2-3; [Doc. No. 50-1]. The Government concluded that the walls posed a significant safety risk and were noncompliant with the Prime Contract requirements. [Opp.] at 4–5; [Doc. No. 50-2]. In July 2021, the Government directed that the ICF walls be demolished and rebuilt due to widespread nonconformance, including the misplaced reinforcing steel. [Opp.] at 4–5; [Doc. No. 50-2].3 Demolition and reconstruction of

the walls extended from late 2021 into 2024, [Opp.] at 5; [Doc. No. 50-3], although the Government’s suspension of all work on the Project ended on September 15, 2022. [Mot.] at 5 ¶ 16; [Doc. No. 38] ¶ 27. As of the time the Motions were filed, Aarow had not completed all work contemplated by the Subcontract, as the second phase of the Project had not yet commenced. [Mot.] at 4 ¶ 12; [Doc. No. 46-21] ¶ 7; [Doc. No. 38] ¶ 10.

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America f/u/b/o Aarow Electrical Solutions, LLC v. Liberty Mutual Insurance Co., (E.D. Va. 2026).

United States of America f/u/b/o Aarow Electrical Solutions, LLC v. Liberty Mutual Insurance Co. (United States of America f/u/b/o Aarow Electrical Solutions, LLC v. Liberty Mutual Insurance Co.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
The United States v. Johnson Controls, Inc.
713 F.2d 1541 (Federal Circuit, 1983)
Capital Electric Company v. The United States
729 F.2d 743 (Federal Circuit, 1984)
Metric Constructors v. United States
314 F.3d 578 (Federal Circuit, 2002)
Barbre v. Pope
935 A.2d 699 (Court of Appeals of Maryland, 2007)
Liscombe v. Potomac Edison Co.
495 A.2d 838 (Court of Appeals of Maryland, 1985)
Md.-Nat'l Cap. P. & P. v. Wash. Nat'l Arena
386 A.2d 1216 (Court of Appeals of Maryland, 1978)
State Highway Administration v. Greiner Engineering Sciences, Inc.
577 A.2d 363 (Court of Special Appeals of Maryland, 1990)
Howard v. Crumlin
197 A.3d 574 (Court of Special Appeals of Maryland, 2018)
Clearwater Constructors, Inc. v. United States
56 Fed. Cl. 303 (Federal Claims, 2003)
United States ex rel. Kitchens to Go v. John C. Grimberg Co.
283 F. Supp. 3d 476 (E.D. Virginia, 2017)