United States of America, for the Use of J. Huizar and Sons, Inc. v. Environmental Construction Company Frank Munoz, Dba Environmental Construction Company

52 F.3d 336, 1995 U.S. App. LEXIS 18840
CourtCourt of Appeals for the Ninth Circuit
DecidedApril 13, 1995
Docket94-15434
StatusUnpublished

This text of 52 F.3d 336 (United States of America, for the Use of J. Huizar and Sons, Inc. v. Environmental Construction Company Frank Munoz, Dba Environmental Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the Use of J. Huizar and Sons, Inc. v. Environmental Construction Company Frank Munoz, Dba Environmental Construction Company, 52 F.3d 336, 1995 U.S. App. LEXIS 18840 (9th Cir. 1995).

Opinion

52 F.3d 336

NOTICE: Ninth Circuit Rule 36-3 provides that dispositions other than opinions or orders designated for publication are not precedential and should not be cited except when relevant under the doctrines of law of the case, res judicata, or collateral estoppel.
UNITED STATES of America, for the Use of J. HUIZAR AND SONS,
INC., Plaintiff-Appellee,
v.
ENVIRONMENTAL CONSTRUCTION COMPANY; Frank Munoz, dba
Environmental Construction Company, Defendants-Appellants.

Nos. 93-16914, 94-15434.

United States Court of Appeals, Ninth Circuit.

Argued and Submitted Feb. 15, 1995.
Decided April 13, 1995.

Before: REINHARDT, THOMPSON, and KLEINFELD, Circuit Judges.

MEMORANDUM*

We affirm this Miller Act judgment. Though arguably some of the decisions could have been made the other way, the factual determinations were not clearly erroneous, and the others were not an abuse of discretion.

I. Evidence Supporting Judgment

We review the findings of fact for clear error, which requires a definite and firm conviction that a mistake has been committed. United States v. Ramos, 923 F.2d 1346, 1356 (9th Cir.1991). Environmental, the general contractor, claimed that the subcontractor had not performed properly. The subcontractor, Huizar, claimed that it had performed as directed. There was evidence both ways. The judge was persuaded of the subcontractor's position, and adequate evidence supported her decision.

Both sides agreed that the original plans were of little use, because what was found underground differed so greatly from what was shown in the drawings. Should Huizar have done more exploratory work to avoid delay, or did Huizar properly comply with the general contractor's and the Coast Guard's directions? The court found that Huizar properly complied with directions:

9. It was physically impossible for J. Huizar to install the waterline according to the original bid set of plans....

14. J. Huizar was directed to stop work upon encountering obstructions and await further directions from Environmental Construction Company.

15. J. Huizar and Sons performed all exploratory work that it was directed to perform by Environmental Construction Company. When J. Huizar was directed to explore, that exploration occurred; when J. Huizar was not directed to explore, no exploration occurred....

17. Environmental Construction Company never directed Huizar and Sons to explore for obstructions or to use an exploratory backhoe at the site.

Evidence supported the district court's findings. Mr. Huizar testified that the custom in the industry was for the general, not the sub, to take the initiative to direct exploratory work and obtain change orders from the government:

Q. Based on your knowledge and experience in the industry, whose responsibility was it to determine whether or not it was appropriate for you to have an exploratory backhoe on the site?

A. Environmental.

Q. And whose responsibility, based on your experience in the industry, was it to obtain a change order from the Coast Guard to add to the scope of the contract work, exploratory backhoe work?

Q. And Environmental never obtained a change order from the Coast Guard for this work to be done?

A. No, they didn't.

Q. And you were never ordered by Environmental to do exploratory work up in front, were you?

A. No, I wasn't.

[SER 89-90]

The Coast Guard's project manager testified that there was no provision in the contract requiring Huizar to do exploratory work, nor was there anything in the original plans and specifications that would lead Mr. Huizar to include the cost of an exploratory backhoe into his original bid. [SER 136] A Coast Guard inspector on the jobsite confirmed that the Coast Guard required Mr. Huizar to obtain approval or instruction as to how to negotiate an obstruction that was not indicated on the plans. [SER 114]

Mr. Huizar testified that the duplicative work he did was at the Coast Guard's direction:

Q. Why did you lay and then relay pipe that you had already laid?
A. That was upon direction of the Coast Guard.

Q. So it wasn't because of any changes that you independently made, it was because the Coast Guard was directing you to make those changes?

A. Yes, sir. That's correct.
Q. Did Environmental ever direct you to make any of those changes?
A. No, sir.
Q. It was always the Coast Guard?
A. Yes.

[SER 91].

Mr. Munoz, who owned and operated the general, conceded that he did not tell Huizar to use more men and did not obtain a change order from the Coast Guard for Huizar to obtain more men and equipment. [SER 105-06]

Although Environmental presented conflicting evidence, we are not left with a definite and firm conviction that the district court's findings are mistaken.

II. Exclusion of Exhibit H

Environmental next argues that the district court improperly excluded Exhibit H. This exhibit was intended to prove the general's expenses for doing the work the sub allegedly should have done after the general fired the sub. It is a multi-page spreadsheet indexing original documents, with the original documents attached. Some of the supporting documents look like contemporaneously kept business records, such as the "foreman's daily cost report." Some are invoices from materialmen. Some are checks to suppliers of materials and services. The spreadsheet itself appears to be a compilation prepared for trial to show the totals.

On appeal, the general argues that the spreadsheet should have been admitted as a summary under Federal Rule of Evidence 1006. But at trial, the general did not purport to be offering the spreadsheet and documents as a Rule 1006 summary. The judge therefore had no occasion to determine whether the requirements for admission were complied with. In particular, the foundation requirements of availability for inspection at a reasonable time and place might or might not have been put at issue, had a proper proffer been made. Also, the proponent of a Rule 1006 summary must bear the burden of establishing foundation for the admissibility of the supporting materials. United States v. Johnson, 594 F.2d 1253, 1255 (9th Cir.1979).

At trial, the sub's attorney objected to the exhibit as hearsay. The court agreed. The general's attorney responded that it was nevertheless admissible as a "business record" pursuant to Federal Rule of Evidence 803(6).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
52 F.3d 336, 1995 U.S. App. LEXIS 18840, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-of-j-huizar-and-sons-inc-v-ca9-1995.