United States of America for the Use and Benefit of: McCullough Plumbing, Inc. v. Halbert Construction Company, Inc.

CourtDistrict Court, S.D. California
DecidedSeptember 27, 2019
Docket3:17-cv-00803
StatusUnknown

This text of United States of America for the Use and Benefit of: McCullough Plumbing, Inc. v. Halbert Construction Company, Inc. (United States of America for the Use and Benefit of: McCullough Plumbing, Inc. v. Halbert Construction Company, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America for the Use and Benefit of: McCullough Plumbing, Inc. v. Halbert Construction Company, Inc., (S.D. Cal. 2019).

Opinion

1 2 3 4 5 UNITED STATES DISTRICT COURT 6 SOUTHERN DISTRICT OF CALIFORNIA 7 UNITED STATES OF AMERICA for the Case No.: 17-CV-803-CAB-WVG use and benefit of: 8 ORDER DENYING MOTION FOR 9 McCULLOUGH PLUMBING, INC., ATTORNEY’S FEES AND MOTION TO ALTER JUDGMENT 10 Plaintiff,

11 v.

12 HALBERT CONSTRUCTION [Doc. Nos. 170, 175] COMPANY, INC. et al., 13 Defendants. 14

15 AND RELATED CROSS-CLAIMS AND COUNTERCLAIMS AND THIRD 16 PARTY COMPLAINT 17 18 This matter is before the Court on a motion for attorneys’ fees, nontaxable costs, and 19 prejudgment interest by McCullough Plumbing, Inc. (“McCullough”) and The Guarantee 20 Company of North America USA (“Guarantee”), and a motion to alter the judgment by 21 Halbert Construction Company, Inc. (“Halbert”). The motions have been fully briefed, 22 and the Court deems them suitable for submission without oral argument. Both motions 23 are denied. 24 I. Background 25 The parties are familiar with the facts which will not be repeated in detail here. 26 Halbert was the prime contractor on a contract with the United States Army Corps of 27 Engineers for work on a dining facility in Monterey, California (the “Project”). In 28 connection with the Project, Halbert and Defendant Western Surety Company (“Western”) 1 executed and delivered a payment bond to the United States under the Miller Act, 40 U.S.C. 2 §§ 3131 et seq. Plaintiff McCullough Plumbing, Inc. (“McCullough”) entered into a 3 subcontract with Halbert to provide plumbing work for the Project (the “Subcontract”). 4 In its complaint, McCullough alleged that Halbert had not paid McCullough for the 5 full value of the labor, services, materials, equipment, and supplies it provided to the 6 Project. Based on these allegations, McCullough asserted claims against Halbert for breach 7 of the Subcontract and quantum meruit, and against Halbert and Western jointly for 8 recovery on the Miller Act payment bond. McCullough’s alleged damages fell into three 9 categories: (1) the unpaid balance of the original Subcontract amount; (2) payment for 10 change orders; and (3) damages resulting from delay in completion of the Project such as 11 extended overhead and personnel costs. 12 Halbert filed a counterclaim against McCullough for breach of contract, breach of 13 express warranty, and negligence, and a third party claim against Guarantee on a bond 14 Guarantee had issued for McCullough’s performance on the Subcontract (the 15 “Performance Bond”). [Doc. No. 68.] Halbert’s alleged damages fell into four categories: 16 (1) cost to repair inadequate work by McCullough; (2) cost to complete work McCullough 17 failed to perform under the Subcontract; (3) a contractual mark-up to the costs for 18 completion work; and (4) damages for delays to Project caused by McCullough’s breach. 19 At the conclusion of a nine-day trial, a jury found that McCullough had proved its 20 breach of contract claim and its claim that it provided additional work outside the 21 Subcontract and approved Change Orders. On the verdict form, the jury found that 22 McCullough had proved damages of: (1) $220,909.00 for unpaid work and materials on 23 the Subcontract and any approved Change Orders; (2) 47,814.70 for delay; and (3) 24 $135,947.70 for unpaid work and materials outside the Subcontract and approved Change 25 Orders. The jury found that Halbert’s surety, Western Surety owes McCullough the full 26 amount of these damages totaling $404,671.40. [Doc. No. 166.] 27 The jury also found that Halbert had proved its breach of contract claim against 28 McCullough. On the verdict form, the jury found that Halbert had proved damages of 1 $345,362.00 for completion work, but no damages for repair work, mark-up, or delay. [Id.] 2 The jury found that Halbert had not performed all its obligations under the performance 3 bond issued by Guarantee and therefore found that Guarantee was not obligated to pay 4 Halbert any damages for McCullough’s default on the Subcontract. [Id.] 5 Pursuant to the Court’s order after the verdict was read, the parties jointly submitted 6 a proposed judgment on July 29, 2019, and the Court signed and entered that judgment on 7 the same day. [Doc. No. 168.] The Judgment states that: (1) McCullough recovers 8 $404,671.40 from Halbert and Western, jointly and severally, on McCullough’s complaint; 9 (2) Halbert recovers $345,362.00 from McCullough on Halbert’s counterclaim; and (3) 10 Halbert recovers nothing on its claim against Guarantee. McCullough and Guarantee now 11 move for their attorney’s fees pursuant to the fee provision in the Subcontract. [Doc. No. 12 170.] Halbert opposes that motion and separately moves to alter the judgment. [Doc. No. 13 175.] 14 II. Halbert’s Motion to Alter the Judgment 15 The verdict form asked the jury to itemize Halbert’s damages into four categories: 16 (1) repair work; (2) completion work; (3) mark-up; and (4) delay damages. Halbert argues 17 that the judgment of $345,362.00 on Halbert’s counterclaims is incorrect because the jury 18 entered $345,362.00 on the line of the verdict form for completion work, but zero on the 19 line for mark-up, whereas Halbert contends a 20% markup on completion work is 20 mandated by the Subcontract. This argument is disingenuous considering that Halbert did 21 not present evidence at trial that it incurred $345,362.00 in costs for completion work and 22 in its closing argument asked the jury to enter just $287,802.00 on the line for completion 23 work on the verdict form. Thus, Halbert is now arguing for a judgment that is not supported 24 by the evidence presented to the jury at trial. 25 Moreover, how the jury arrived at the total it entered on the line for completion work 26 is readily apparent from the testimony and evidence at trial. Halbert’s expert, Michelle 27 Mangan, testified that Halbert’s total actual costs for completion work were $287,802.00, 28 and that Halbert was entitled to a 20% mark-up equaling $57,560.00 on that amount, for a 1 total including mark-up of $345,362.00. [Doc. No. 183-1 at 5-42.] This is the exact amount 2 the jury awarded to Halbert on the verdict form line for completion work and is the amount 3 awarded to Halbert on its counterclaim in the judgment. [Doc. No. 168.] Ironically, 4 Halbert argues that McCullough’s opposition asks the Court to construe the verdict as 5 something it does not state when it is Halbert asking the Court to enter judgment 6 inconsistent with the verdict and inconsistent with the evidence Halbert put on at trial with 7 respect to the amount it incurred for completion work. Because the judgment accurately 8 reflects the jury’s verdict, and because the verdict based on the evidence presented at trial 9 reflects that the jury included a 20% markup on the amount of completion work Halbert 10 itself argued it performed as a result of McCullough’s breach, Halbert’s motion to alter the 11 judgment is denied. 12 III. McCullough’s Motion for Attorney’s Fees and Costs 13 The Subcontract states that: 14 In the event it becomes necessary for either party to enforce the provisions of this Subcontract or to obtain redress for the violation of any provision hereof 15 the prevailing party shall be entitled to recover from the other party all costs, 16 reasonable attorneys’ fees, and expenses associated with such action, including statutory interest. 17 18 [Doc. No. 170-2 at 40.] The parties do not dispute that California law applies to 19 McCullough’s fee motion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Emeryville v. The Sherwin-Williams Company
621 F.3d 1251 (Ninth Circuit, 2010)
Leff v. Gunter
658 P.2d 740 (California Supreme Court, 1983)
Scott Co. of California v. Blount, Inc.
979 P.2d 974 (California Supreme Court, 1999)
Chia-Lee Hsu v. Abbara
891 P.2d 804 (California Supreme Court, 1995)
Bank of Idaho v. Pine Avenue Associates
137 Cal. App. 3d 5 (California Court of Appeal, 1982)
Deane Gardenhome Assn. v. Denktas
13 Cal. App. 4th 1394 (California Court of Appeal, 1993)
Select Specialty Hospital - Denver, Inc. v. Sebelius
848 F. Supp. 2d 13 (District of Columbia, 2012)
Tamara Diaz v. Kubler Corporation
785 F.3d 1326 (Ninth Circuit, 2015)
The Chuck Olsen Co. v. F.P.D., Inc.
698 F. App'x 409 (Ninth Circuit, 2017)
Westport Ins. Corp. v. California Casualty Mgt.
916 F.3d 769 (Ninth Circuit, 2019)
Marina Pacifica Homeowners Ass'n v. S. Cal. Fin. Corp.
228 Cal. Rptr. 3d 799 (California Court of Appeals, 5th District, 2018)

Cite This Page — Counsel Stack

Bluebook (online)
United States of America for the Use and Benefit of: McCullough Plumbing, Inc. v. Halbert Construction Company, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-mccullough-plumbing-casd-2019.