United States of America for the Use and Benefit of: McCullough Plumbing, Inc. v. Halbert Construction Company, Inc.

District Court, S.D. California·Decided September 27, 2019·No. 3:17-cv-00803·Unknown

Opinion

UNITED STATES OF AMERICA for the Case No.: 17-CV-803-CAB-WVG use and benefit of: ORDER DENYING MOTION FOR McCULLOUGH PLUMBING, INC., ATTORNEY’S FEES AND MOTION TO ALTER JUDGMENT Plaintiff,

v.

[Doc. Nos. 170, 175] COMPANY, INC. et al., Defendants.

COUNTERCLAIMS AND THIRD This matter is before the Court on a motion for attorneys’ fees, nontaxable costs, and prejudgment interest by McCullough Plumbing, Inc. (“McCullough”) and The Guarantee Company of North America USA (“Guarantee”), and a motion to alter the judgment by Halbert Construction Company, Inc. (“Halbert”). The motions have been fully briefed, and the Court deems them suitable for submission without oral argument. Both motions are denied. I. Background The parties are familiar with the facts which will not be repeated in detail here. Halbert was the prime contractor on a contract with the United States Army Corps of Engineers for work on a dining facility in Monterey, California (the “Project”). In connection with the Project, Halbert and Defendant Western Surety Company (“Western”) executed and delivered a payment bond to the United States under the Miller Act, 40 U.S.C. §§ 3131 et seq. Plaintiff McCullough Plumbing, Inc. (“McCullough”) entered into a subcontract with Halbert to provide plumbing work for the Project (the “Subcontract”). In its complaint, McCullough alleged that Halbert had not paid McCullough for the full value of the labor, services, materials, equipment, and supplies it provided to the Project. Based on these allegations, McCullough asserted claims against Halbert for breach of the Subcontract and quantum meruit, and against Halbert and Western jointly for recovery on the Miller Act payment bond. McCullough’s alleged damages fell into three categories: (1) the unpaid balance of the original Subcontract amount; (2) payment for change orders; and (3) damages resulting from delay in completion of the Project such as extended overhead and personnel costs. Halbert filed a counterclaim against McCullough for breach of contract, breach of express warranty, and negligence, and a third party claim against Guarantee on a bond Guarantee had issued for McCullough’s performance on the Subcontract (the “Performance Bond”). [Doc. No. 68.] Halbert’s alleged damages fell into four categories: (1) cost to repair inadequate work by McCullough; (2) cost to complete work McCullough failed to perform under the Subcontract; (3) a contractual mark-up to the costs for completion work; and (4) damages for delays to Project caused by McCullough’s breach. At the conclusion of a nine-day trial, a jury found that McCullough had proved its breach of contract claim and its claim that it provided additional work outside the Subcontract and approved Change Orders. On the verdict form, the jury found that McCullough had proved damages of: (1) $220,909.00 for unpaid work and materials on the Subcontract and any approved Change Orders; (2) 47,814.70 for delay; and (3) $135,947.70 for unpaid work and materials outside the Subcontract and approved Change Orders. The jury found that Halbert’s surety, Western Surety owes McCullough the full amount of these damages totaling $404,671.40. [Doc. No. 166.] The jury also found that Halbert had proved its breach of contract claim against McCullough. On the verdict form, the jury found that Halbert had proved damages of $345,362.00 for completion work, but no damages for repair work, mark-up, or delay. [Id.] The jury found that Halbert had not performed all its obligations under the performance bond issued by Guarantee and therefore found that Guarantee was not obligated to pay Halbert any damages for McCullough’s default on the Subcontract. [Id.] Pursuant to the Court’s order after the verdict was read, the parties jointly submitted a proposed judgment on July 29, 2019, and the Court signed and entered that judgment on the same day. [Doc. No. 168.] The Judgment states that: (1) McCullough recovers $404,671.40 from Halbert and Western, jointly and severally, on McCullough’s complaint; (2) Halbert recovers $345,362.00 from McCullough on Halbert’s counterclaim; and (3) Halbert recovers nothing on its claim against Guarantee. McCullough and Guarantee now move for their attorney’s fees pursuant to the fee provision in the Subcontract. [Doc. No. 170.] Halbert opposes that motion and separately moves to alter the judgment. [Doc. No. 175.] II. Halbert’s Motion to Alter the Judgment The verdict form asked the jury to itemize Halbert’s damages into four categories: (1) repair work; (2) completion work; (3) mark-up; and (4) delay damages. Halbert argues that the judgment of $345,362.00 on Halbert’s counterclaims is incorrect because the jury entered $345,362.00 on the line of the verdict form for completion work, but zero on the line for mark-up, whereas Halbert contends a 20% markup on completion work is mandated by the Subcontract. This argument is disingenuous considering that Halbert did not present evidence at trial that it incurred $345,362.00 in costs for completion work and in its closing argument asked the jury to enter just $287,802.00 on the line for completion work on the verdict form. Thus, Halbert is now arguing for a judgment that is not supported by the evidence presented to the jury at trial. Moreover, how the jury arrived at the total it entered on the line for completion work is readily apparent from the testimony and evidence at trial. Halbert’s expert, Michelle Mangan, testified that Halbert’s total actual costs for completion work were $287,802.00, and that Halbert was entitled to a 20% mark-up equaling $57,560.00 on that amount, for a total including mark-up of $345,362.00. [Doc. No. 183-1 at 5-42.] This is the exact amount the jury awarded to Halbert on the verdict form line for completion work and is the amount awarded to Halbert on its counterclaim in the judgment. [Doc. No. 168.] Ironically, Halbert argues that McCullough’s opposition asks the Court to construe the verdict as something it does not state when it is Halbert asking the Court to enter judgment inconsistent with the verdict and inconsistent with the evidence Halbert put on at trial with respect to the amount it incurred for completion work. Because the judgment accurately reflects the jury’s verdict, and because the verdict based on the evidence presented at trial reflects that the jury included a 20% markup on the amount of completion work Halbert itself argued it performed as a result of McCullough’s breach, Halbert’s motion to alter the judgment is denied. III. McCullough’s Motion for Attorney’s Fees and Costs The Subcontract states that: In the event it becomes necessary for either party to enforce the provisions of this Subcontract or to obtain redress for the violation of any provision hereof the prevailing party shall be entitled to recover from the other party all costs, reasonable attorneys’ fees, and expenses associated with such action, including statutory interest. [Doc. No. 170-2 at 40.] The parties do not dispute that California law applies to McCullough’s fee motion. Pursuant to California Civil Code section 1717, “[i]n any action on a contract, where the contract specifically provides that attorney’s fees and costs, which are incurred to enforce that contract, shall be awarded either to one of the parties or to the prevailing party, then the party who is determined to be the party prevailing on the contract, whether he or she is the party specified in the contract or not, shall be entitled to reasonable attorney’s fees in addition to other costs.” Cal. Civ. Code § 1717(a). “Although generally the prevailing party is the one ‘who recovered a greater relief in the action on the contract[,]’ the court may determine there is no prevailing party.” Deane Gar

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America for the Use and Benefit of: McCullough Plumbing, Inc. v. Halbert Construction Company, Inc., (S.D. Cal. 2019).

United States of America for the Use and Benefit of: McCullough Plumbing, Inc. v. Halbert Construction Company, Inc. (United States of America for the Use and Benefit of: McCullough Plumbing, Inc. v. Halbert Construction Company, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

City of Emeryville v. The Sherwin-Williams Company
621 F.3d 1251 (Ninth Circuit, 2010)
Leff v. Gunter
658 P.2d 740 (California Supreme Court, 1983)
Scott Co. of California v. Blount, Inc.
979 P.2d 974 (California Supreme Court, 1999)
Chia-Lee Hsu v. Abbara
891 P.2d 804 (California Supreme Court, 1995)
Bank of Idaho v. Pine Avenue Associates
137 Cal. App. 3d 5 (California Court of Appeal, 1982)
Deane Gardenhome Assn. v. Denktas
13 Cal. App. 4th 1394 (California Court of Appeal, 1993)
Select Specialty Hospital - Denver, Inc. v. Sebelius
848 F. Supp. 2d 13 (District of Columbia, 2012)
Tamara Diaz v. Kubler Corporation
785 F.3d 1326 (Ninth Circuit, 2015)
The Chuck Olsen Co. v. F.P.D., Inc.
698 F. App'x 409 (Ninth Circuit, 2017)
Westport Ins. Corp. v. California Casualty Mgt.
916 F.3d 769 (Ninth Circuit, 2019)
Marina Pacifica Homeowners Ass'n v. S. Cal. Fin. Corp.
228 Cal. Rptr. 3d 799 (California Court of Appeals, 5th District, 2018)