United States of America, For the Use and Benefit of: Martin Brothers Construction v. Walsh Federal, LLC, et al.

District Court, E.D. California·Decided July 14, 2026·No. 2:24-cv-01705·Unknown

Opinion

UNITED STATES OF AMERICA, For No. 2:24-cv-01705-DJC-SCR the Use and Benefit of: MARTIN BROTHERS ORDER Plaintiff, v. WALSH FEDERAL, LLC, et al., Defendants. In 2020, Plaintiff Martin Brothers Construction and Defendant Walsh Federal, LLC, signed a contract for Plaintiff to provide earthwork and asphalt services in constructing an aircraft maintenance hangar at Travis Air Force Base in Fairfield, California. As required by the contract, Plaintiff signed certain waivers throughout the project in exchange for payment for completed work. The interpretation and effect of those waivers is now at issue. Because the Court finds that the affirmative defense of waiver is a factual dispute, Defendants Walsh Federal, LLC, and Travelers Casualty and Surety Company’s Motion for Partial Summary Judgment is GRANTED in part and DENIED in part. BACKGROUND1 On August 6, 2020, Plaintiff, a subcontractor, entered into a written subcontract (“Subcontract”) with Defendant Walsh Federal, LLC, the prime contractor, to provide earthwork and asphalt paving services for construction of an aircraft maintenance hangar at Travis Air Force Base. (Pl.’s Resp. to Defendants’ Separate Statement of Undisputed Facts (“DSUF”) (ECF No. 31) ¶ 2; Subcontract at Ex. A (ECF No. 1-1).) The original value of the Subcontract was $3,750,000.00. (Subcontract at 1.) During the project, the parties entered into several Subcontract Change Orders resulting in a current contract value of $5,201,824. (Resp. to DSUF ¶ 3.) The Subcontract contemplated changes to its scope and provided for such in Article 4.1 (Changes). (Id. ¶ 16.) Article 4.3 (Claims) of the Subcontract also required Plaintiff to submit an Initial Notice of Claim. (Id. ¶ 21.) Article 4.3’s Initial Notice and Claim requirements required strict compliance with its terms. (Id. ¶ 22.) The Subcontract also provided a procedure for payments whereby Plaintiff must execute a partial (or final) waiver and release prior to or in exchange for payment. (Id. ¶ 4; Proc. for Progress Payment (ECF No. 27) at 49, Ex. F.) The Subcontract included at least two form waivers: a California Civil Code section 8132 Conditional Waiver and Release on Progress Payment (the “California Waiver”) and Defendant Walsh’s own Partial Waiver and Release of Claims for Payment (the “Walsh Waiver”). (Resp. to Plaintiff’s Statement of Disputed Facts (“PSDF”) (ECF No. 34) at ¶ 19; see Waiver & Release Forms (ECF No. 27) at 64–72, Ex. I.)2 The Subcontract also

1 Defendants request this Court take judicial notice of the Subcontract, the Complaint, and Answers filed in this action. (See generally RJN (ECF No. 27).) Because the Complaint and Answers are already part of this Court’s record, it need not take judicial notice of them. As to the Subcontract and its related exhibits, the Court grants the request by way of the incorporation by reference doctrine because the Subcontract forms the basis of Plaintiff’s claims. Courts can consider documents under the “incorporation by reference” doctrine when a plaintiff “refers extensively to the document or the document forms the basis of the plaintiff’s claim. Khoja v. Orexigen Therapeutics, Inc., 899 F.3d 988, 1002 (9th Cir. 2018) (citation omitted). 2 The subcontract provided several representative examples of partial and final “Walsh” and included an anti-waiver provision entitled “Severability and Waiver” at Article 13.2. (Subcontract Art. 13.2.) That provision explained that the “failure of either party hereto to insist, in any one or more instances, upon the performance of any of the terms, covenants or conditions of this Agreement, or to exercise any right herein, shall not be construed as a waiver or relinquishment of such term, covenant, condition or right as respects further performance.” (Id.) Plaintiff signed the Subcontract on August 3, 2020, and Defendant signed on August 6, 2020. (Subcontract at 2.) During the project, Plaintiff submitted several payment applications for work performed. (Resp. to DSUF ¶ 8.) Plaintiff signed waivers and release of claims on October 31, 2022; December 31, 2022; and March 31, 2023. (Reed Decl. (ECF No. 26) ¶ 4 & Exs. 1–3.) Plaintiff submitted the signed California Waiver and Walsh Waiver together, contemporaneously, for all payment applications throughout the duration of the project. (Martin Decl. (ECF No. 30-1) at ¶ 33; Reed Decl. at Exs. 1–3; Resp. to PSDF ¶ 26.) To track and document work Plaintiff performed beyond its contracted scope, Plaintiff would prepare a Daily Extra Work Report (“DEWR”). (Resp. to PSDF ¶ 7.) Each DEWR documents the nature of the additional work, the personnel involved, labor hours, equipment used and duration, and any vendors, materials, or suppliers used to complete the work. (Id. ¶ 8.) A representative of Defendant Walsh would sign the DEWR to verify the labor, equipment, and materials used. (Id. ¶ 10; Reed Dep. 196:9– 13.) One copy of the DEWR is retained by Plaintiff’s foreman, one by Defendant Walsh, and one is transmitted to Plaintiff’s office. (Resp. to PSDF ¶ 11.) Defendant Walsh also received “Daily Reports” which apprised it of the day’s work. (Id. ¶ 14; Jacob Dep. 20:9–15.) In addition to the DEWRs, the parties communicated through onsite discussions and email correspondence regarding the alleged extra work. (Resp. to PSDF ¶ 15; Molinelli Decl. (ECF No. 30-2) ¶ 11; Martin Decl. (ECF No. 30-1)

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America, For the Use and Benefit of: Martin Brothers Construction v. Walsh Federal, LLC, et al., (E.D. Cal. 2026).

United States of America, For the Use and Benefit of: Martin Brothers Construction v. Walsh Federal, LLC, et al. (United States of America, For the Use and Benefit of: Martin Brothers Construction v. Walsh Federal, LLC, et al.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related