United States of America for the Use and Benefit of Grinnell Corporation v. Dni, Inc., a Hawaii Corporation Island Insurance Company, Ltd., a Hawaii Corporation, United States of America for the Use and Benefit of Grinnell Corporation v. Dni, Inc., a Hawaii Corporation Island Insurance Company, Ltd., a Hawaii Corporation, Surety

106 F.3d 411, 1997 U.S. App. LEXIS 25363
CourtCourt of Appeals for the Ninth Circuit
DecidedJanuary 22, 1997
Docket95-16514
StatusUnpublished

This text of 106 F.3d 411 (United States of America for the Use and Benefit of Grinnell Corporation v. Dni, Inc., a Hawaii Corporation Island Insurance Company, Ltd., a Hawaii Corporation, United States of America for the Use and Benefit of Grinnell Corporation v. Dni, Inc., a Hawaii Corporation Island Insurance Company, Ltd., a Hawaii Corporation, Surety) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America for the Use and Benefit of Grinnell Corporation v. Dni, Inc., a Hawaii Corporation Island Insurance Company, Ltd., a Hawaii Corporation, United States of America for the Use and Benefit of Grinnell Corporation v. Dni, Inc., a Hawaii Corporation Island Insurance Company, Ltd., a Hawaii Corporation, Surety, 106 F.3d 411, 1997 U.S. App. LEXIS 25363 (9th Cir. 1997).

Opinion

106 F.3d 411

NOTICE: Ninth Circuit Rule 36-3 provides that dispositions other than opinions or orders designated for publication are not precedential and should not be cited except when relevant under the doctrines of law of the case, res judicata, or collateral estoppel.
UNITED STATES of America for the use and benefit of Grinnell
Corporation, Plaintiff-Appellee,
v.
DNI, INC., a Hawaii corporation; Island Insurance Company,
Ltd., a Hawaii corporation, Defendants-Appellants.
UNITED STATES of America for the use and benefit of Grinnell
Corporation, Plaintiff-Appellant,
v.
DNI, INC., a Hawaii corporation; Island Insurance Company,
Ltd., a Hawaii corporation, surety, Defendants-Appellees.

Nos. 95-16514, 95-17013.

United States Court of Appeals, Ninth Circuit.

Argued and Submitted Dec. 12, 1996.
Decided Jan. 22, 1997.

MEMORANDUM*

Before: FLETCHER, WIGGINS, and T.G. NELSON, Circuit Judges.

The district court granted summary judgment in favor of Grinnell Corporation in this contract dispute, awarding Grinnell $60,929.00 plus prejudgment interest for unpaid sums arising out the installation of a fire sprinkler system on a United States military base. The district court also awarded Grinnell attorney's fees in the amount of $18,910.37. DNI, Inc. and Island Insurance Company, Ltd. ("DNI") appeal, contending that the district court's order granting summary judgment was erroneous. Grinnell cross-appeals, arguing that the district court incorrectly decided its claim for attorney's fees. We affirm the district court's judgment in its entirety.

I.

DNI contends that Grinnell's complaint was untimely under the Miller Act's one-year statute of limitations, 40 U.S.C. § 270b. To analyze whether a suit is timely under the Miller Act, "the test to be applied is whether the work was performed and the material supplied as part of the original contract or for the purposes of correcting defects, or making repairs following inspection of the project." United States ex rel. Austin v. Western Elec. Co., 337 F.2d 568, 572-73 (9th Cir.1964) (internal quotations omitted).

Grinnell filed its complaint on December 21, 1993. Accordingly, Grinnell's complaint is time-barred unless work was performed or material was supplied on or after December 21, 1992. The district court concluded that work was performed on December 23, 1992, when a Grinnell technician attended a final inspection of the sprinkler system. During the inspection, the system was "put into service" and turned over to the Navy.1

The Grinnell-DNI subcontract obligated Grinnell to perform certain duties delineated in DNI's contract with the Navy. The Navy-DNI contract required "the system installer" to provide "an experienced technician" during the final inspection of the sprinkler system. Thus, Grinnell's work performed on December 23, 1993 was part of its contract with DNI. Therefore, we conclude that Grinnell's Miller Act complaint was timely filed.

II.

DNI and Grinnell dispute whether the contract required Grinnell to replace the overhead main piping in the cold storage warehouse. Applying Hawaii law, the district court concluded that the terms of the contract were ambiguous on this issue and construed this ambiguity against DNI as the drafter of the subcontract between Grinnell and DNI. DNI contends the district court's analysis was erroneous, presenting four separate sub-issues: (1) whether Hawaii law should be used to interpret the contract; (2) whether the contract was in fact ambiguous; (3) whether the district court correctly interpreted the ambiguous contract against DNI; and (4) whether Grinnell's failure to show pre-bid reliance on the contract's ambiguity prevents it from recovering on its claim.

A.

State rather than federal substantive law applies in Miller Act cases to which the United States is not a party, i.e., disputes between the prime contractor and a subcontractor. E.g. United States ex rel. Union Bldg. Materials Corp. v. Haas & Haynie Corp., 577 F.2d 568, 571 n. 1 (9th Cir.1978). This contract was signed by two Hawaii corporations in Hawaii. Accordingly, the district court correctly applied Hawaii law to the interpretation of the contract.

B.

We agree with the district court that the contract was ambiguous as to whether Grinnell was required to replace the overhead main piping. The Navy's specifications required the contractor to "[r]emove all components of existing preaction in-rack sprinkler systems located in the Dairy, Fruit, and Vegetable Coolers and Freezer." Neither the Navy-DNI contract nor the DNI-Grinnell subcontract contain any provision specifying what is meant by the term "in-rack sprinkler system." Rather, the DNI-Grinnell subcontract seems to distinguish between piping "in-rack" and piping "overhead."

DNI's efforts to rely on extra-contractual sources to clarify the contract's terms are unavailing. DNI relies on an industry-wide standard defining "sprinkler system" and the underlying purpose of the warehouse project. We find neither persuasive. The industry standard does not help us determine what is meant by the term "in-rack sprinkler system." Nor does the purpose of the project help us determine what is meant by this language.

C.

Under Hawaii law, an ambiguous contract should be construed against the party who prepared the contract. E.g., Arakawa v. Limco, Ltd., 587 P.2d 1216, 1219 (Haw.1978); Union Building Materials Corp., 577 F.2d at 574. DNI prepared the DNI-Grinnell subcontract incorporating the terms of the Navy-DNI contract. Accordingly, we conclude the district court properly interpreted the ambiguity in the contracts against DNI.

D.

DNI argues that Grinnell had a duty to inquire about ambiguities in the subcontract and that Grinnell's failure to satisfy that duty prevents Grinnell from recovering. First, DNI argues that the ambiguity in the contract was a "patent ambiguity." This argument can be quickly rejected. The contract's terms are not patently ambiguous. Only after DNI took the position that replacement of the overhead piping was necessary did a latent ambiguity become apparent.

Where a latent ambiguity is present, federal procurement law establishes that a prime contractor has the obligation to show that it relied upon its interpretation of the ambiguity in the submission of its bid. See, e.g., Edward R. Marden Corp. v. United States, 803 F.2d 701, 705 (Fed.Cir.1986). DNI argues that Section 11.1.1 of the DNI-Grinnell subcontract places all of its obligations and responsibilities vis-a-vis the Navy on Grinnell. Accordingly, DNI argues that Grinnell has the obligation of showing that it relied upon its interpretation of the ambiguity in the submission of its bid.

Without reaching the validity of DNI's argument based on federal rather than state law, DNI's premise that Grinnell failed to show pre-bid reliance can be rejected.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
106 F.3d 411, 1997 U.S. App. LEXIS 25363, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-grinnell-corporation-v-ca9-1997.