United States of America for the use and benefit of Casas Construction v. Sierra Range Construction

District Court, D. Nevada·Decided March 31, 2024·No. 2:21-cv-00573·Unknown

Opinion

* * *

UNITED STATES OF AMERICA for the use Case No. 2:21-cv-00573-RFB-BNW and benefit of CASAS CONSTRUCTION, Plaintiff, v. SIERRA RANGE CONSTRUCTION, et al., Defendants.

SIERRA RANGE CONSTRUCTION, Counter Claimant, v. CASAS CONSTRUCTION et al., Counter Defendant.

Before the Court are the Motion for Partial Summary Judgement by Plaintiff Casas Construction and Counter Defendant Daniel Casas (ECF No. 39) and the Motion for Summary Judgement by Defendants Philadelphia Indemnity Insurance Company and Defendant-Counter Claimant Sierra Range Construction (ECF No. 40). For the reasons provided below, the Court denies Casas’ motion and grants in part and denies in part Defendants’ motion. A. Undisputed Facts The Court finds the following facts are not in dispute. In October 2017, Sierra Range Construction (“Sierra”) executed a contract (“the Prime Contract”) with the federal government1 to perform work on Nellis Airforce Base (“the Project”). Sierra executed and delivered a labor and payment bond with Philadelphia Indemnity Insurance Co. (“PIIC”) as surety. Casas Construction (“Casas”) provided Sierra with proposals to perform subcontractor work, including, on April 15, 2019, a document titled “Proposal/Contract Revision 2” (“the Proposal”). On January 15, 2020, Sierra and Casas executed a subcontract (“the Subcontract”) to which the Proposal was attached. Casas sent Sierra multiple documents providing for a schedule of values (“SOV”) between January and March 2020. Issues with securing funds from the Government led to a bottleneck in the Project. On March 5, 2020, Randy Spencer of Sierra emailed Jason Casas and Daniel Casas of Casas2 that “because of our issues with costs right now, can you do me a favor and before you purchase anything let me know how much it will be so I can keep a running track and we don’t exceed what we have.” That day, Jason Casas replied to that email, saying Casas had a cable tray for $175,269 due for delivery at the end of the month and switch gear for $466,022 shipping in July, totaling $641.291. On March 25, 2025, Virginia Casas for Casas emailed Spencer with an invoice. That invoice purports to be from Casas to Sierra, seeking payment of $641.291. On March 26, 2020, Sierra requested that Casas perform certain work, including conduit rough-in work, and Casas subcontracted with CLS Electrical Corporation to complete these tasks. At 10:19 a.m. on April 1, 2020, Spencer emailed Jason Casas and Daniel Casas “a reminder to send [Sierra] the invoice that shows [Casas] paid for the cable trays and how much they were. Also for long lead items that you have to put a deposit on, we need something form the manufacturer stating that a deposit is required and how much for each item.” Spencer emailed again at 11:12 a.m. saying: “I should not have said how much you paid for the cable trays and other long lead 1 The Prime Contract was executed between Sierra and the United States of America, acting by and through the Department of Air Force, 99th Contracting Squadron, Nellis Air Force Base. Plaintiff refers to the federal actor as “99 CONS” and Defendants typically refer to it as the Air Force, for purposes of this Order, the Court will simply use the term federal government. 2 For clarity, where an individual with the surname Casas is referenced in this Order, they are referred to by both their first and last names whereas the term “Casas” on its own is used by the Court to refer only to Defendant Casas Construction. items. I should have said invoice that shows what the manufacturer is billing you for the long lead items that have arrived. You are not required to pay for them up front, we will get the invoice, bill the government, get the payment from the government and pay you so you can pay the manufacturer.” At 5:25 a.m. that same day, Jason Casas emailed Spencer in that same chain, saying: “Thanks for taking our call. Per our conversation attached are the invoices for the onsite stored materials.” Attached to that email were invoices purporting to be from Casas’ supplied by Main Electric to Casas, seeking payment of $641.291. In reality, Casas altered the amounts on the original invoices. Jason Casas made changes to the original Main Electric invoices to increase the amount of the invoices from $304,701.41 to $641,291. In early June 2020, one of Casas’ subcontractors, CLS Electric, informed Sierra that conduit work was completed. After some communication with Sierra, Casas submitted an application for a progress payment to Sierra on April 28, 2020. This application requested a total of $743,919, broken into $568,191 for onsite materials and $175,000 for conduit work. On July 1, 2020, Casas made a $10,000 good faith deposit to Main Electric. Sierra received $90,929 from the federal government for the conduit work, which was paid to Casas who divided the sum between Casas and CLS Electric. On September 22, 2020, Sara Hardin, an account manager at Main Electric contacted Sierra regarding delays in payment and furnished Sierra with the unaltered invoices from Main Electric. Hardin confirmed that the invoices supplied by Casas were not authentic Main Electric invoices. In November 2020, Casas indicated it would not continue work until its outstanding invoices were paid. Eventually, Sierra hired a substitute subcontractor to complete Casas’ remaining scope of work. In January 2021, Sierra sought and received from the government $302,201.36 for the materials provided by Main Electric. Sierra issued a joint check payable to both Casas and Main Electric for $304,701.41. Casas did not endorse the check. On February 1, 2021, Sierra threatened to terminate the Subcontract if Casas did not endorse the check. On February 5, 2021, Sierra terminated the Subcontract. Thereafter, Sierra reissued a check for $304,701.41 to Main Electric, which was deposited paying the invoice in full. B. Disputed Facts The Court finds the following material facts in dispute: whether Sierra instructed Casas to create the altered invoices during the April 1, 2020, call, whether Casas was aware that its invoices and that of its subcontractors were required to be submitted by Casas to the federal government for payment, whether Sierra acted with intention to disrupt Casas’ contractual relationships by making direct payments to its supplier and subcontractor. The parties also dispute: whether Sierra approved a Schedule of Values, whether Sierra contracted out portions of Casas’ scope of work, whether and when Casas’ scope of work was finalized and what that final scope of work entailed, whether delays occurred, whether those delays are solely attributable to Casas, and whether and to what extent either party suffered damages. II. PROCEEDURAL HISTORY On April 7, 2021, Casas filed the Complaint. ECF No. 1. In the Complaint, Casas asserts six causes of action: (1) Breach of Contract, (2) Unjust Enrichment, (3) Breach of Good Faith and Fair Dealing, (4) Violation of the Miller Act, (5) Interference with Contractual Relations, and (6) Action on Payment of Bond. Id. On April 29, 2021, Sierra filed an Answer and Counter Claim. ECF Nos. 8, 9. The Counter Claim presents three claims for relief against Casas and Daniel Casas: (1) Fraud in the Inducement, (2) Breach of Contract, and (3) Fraud. ECF No. 9. On December 6, 2022, both Defendants Sierra and PIIC and Plaintiff Casas Construction filed Motions for Summary Judgement. ECF Nos. 39, 40. After multiple stipulated extensions and errata, the motions were fully briefed on March 8, 2023. ECF Nos. 41-60. On August 2, 2023, the Court set a hearing on the motions for September 14, 2023. ECF No. 63. This hearing was vacated and held on February 15, 2024. ECF Nos. 64-66. The Court’s order follows. Summary judgment is appropriate when the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show “that there is no genuine dispute as to any material fact and the m

Free access — add to your briefcase to read the full text and ask questions with AI

United States of America for the use and benefit of Casas Construction v. Sierra Range Construction, (D. Nev. 2024).

United States of America for the use and benefit of Casas Construction v. Sierra Range Construction (United States of America for the use and benefit of Casas Construction v. Sierra Range Construction) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Motley v. Collins
3 F.3d 781 (Fifth Circuit, 1993)
United States Ex Rel. Sherman v. Carter Constr. Co.
353 U.S. 210 (Supreme Court, 1957)
Scott v. Harris
550 U.S. 372 (Supreme Court, 2007)
United States v. Marvin Byse
28 F.3d 1165 (Eleventh Circuit, 1994)
Lagrange Construction, Inc. v. KENT CORPORATION
496 P.2d 766 (Nevada Supreme Court, 1972)
Lincoln Welding Works, Inc. v. Ramirez
647 P.2d 381 (Nevada Supreme Court, 1982)
Bernard v. Rockhill Development Co.
734 P.2d 1238 (Nevada Supreme Court, 1987)
Hilton Hotels Corp. v. Butch Lewis Productions, Inc.
808 P.2d 919 (Nevada Supreme Court, 1991)
McKnight v. Torres
563 F.3d 890 (Ninth Circuit, 2009)
Mitchell v. Bailey & Selover, Inc.
605 P.2d 1138 (Nevada Supreme Court, 1980)
Consolidated Generator-Nevada, Inc. v. Cummins Engine Co.
971 P.2d 1251 (Nevada Supreme Court, 1998)
Las Vegas-Tonopah-Reno Stage Lines, Inc. v. Gray Line Tours
792 P.2d 386 (Nevada Supreme Court, 1990)
Leasepartners Corp. v. Robert L. Brooks Trust
942 P.2d 182 (Nevada Supreme Court, 1997)
J.J. Industries, LLC v. Bennett
71 P.3d 1264 (Nevada Supreme Court, 2003)