Lincoln Welding Works, Inc. v. Ramirez

647 P.2d 381, 98 Nev. 342, 1982 Nev. LEXIS 469
CourtNevada Supreme Court
DecidedJune 29, 1982
Docket12361
StatusPublished
Cited by18 cases

This text of 647 P.2d 381 (Lincoln Welding Works, Inc. v. Ramirez) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Lincoln Welding Works, Inc. v. Ramirez, 647 P.2d 381, 98 Nev. 342, 1982 Nev. LEXIS 469 (Neb. 1982).

Opinion

*344 OPINION

Per Curiam:

Appellant Lincoln Welding Works sued respondent Rico Paving & Grading Company, seeking to recover for expenses incurred in repairing sheet-piling work, and for damages to a forklift rented by respondent from appellant. On cross-motions for summary judgment, the district court entered judgment in favor of respondent.

On June 2, 1977, respondent entered into a general contract with the Clark County Sanitation District to construct sewage lagoons near Mesquite, Nevada. Under the terms of the general contract, respondent was authorized to subcontract certain portions of the project.

Approximately June 17, 1977, appellant entered into a written subcontract with respondent, to drive sheet piling at the Mesquite construction site. Appellant completed the work on February 7, 1978, and was paid $54,162.00 by respondent.

On March 4 and 5, 1978, a flood occurred, causing extensive damage to a portion of the sheet piling work done by appellant. Shortly thereafter, respondent asked appellant to repair the damaged sheet piling. Operating under the assumption that it would be compensated for the additional work, appellant repaired the damages occasioned by the flood.

Upon completion of the repair work, appellant requested payment of $19,108.22. Respondent refused to compensate appellant for the work, claiming that the prime contract was incorporated by reference into the subcontract. Under the terms of the prime contract, the respondent claimed all subcontractors were obligated to bear the risk of loss until the project was formally accepted by the Sanitation District. The project was not formally accepted by the District until May 8, 1978.

Additionally, the parties entered into a bare rental agreement, wherein respondent rented a forklift from appellant for two and one-half weeks, at a cost of $835.90. Five months after respondent returned the forklift, appellant demanded payment of $1,862.40 for damages allegedly caused by respondent’s misuse of the forklift.

*345 Appellant first contends there was not an incorporation by reference because the subcontract did not specifically incorporate all the terms of the prime contract. The general rule regarding incorporation by reference can be stated as follows: “[WJritings which are made a part of the contract by annexation or reference will be so construed; but where the reference to another writing is made for a particular and specified purpose, such other writing becomes a part for such specified purpose only.” Orleans M. Co. v. Le Champ M. Co., 52 Nev. 92, 284 P. 307 (1930).

In the instant case, respondent claims that the prime contract was incorporated by reference pursuant to the following language:

. . . the Sub-Contractor agrees to furnish at his own expense, all the labor and materials necessary to do and perform in a good and workmanlike manner all the necessary installation described as follows:
WORK PER PLANS, SPECS., AND ADDEM, #1 DATED 12/2/77 DRIVING SHEET PILING
$51,300.00
. . . said work to be done and material furnished therefore in conformity with the plans and specifications for the same prepared by VTN NEVADA-CONSULATING ENGINEERS.

Respondent contends the general reference to the “plans and specifications,” included in the prime contract, evidences the parties’ intent to incorporate the prime contract by reference.

Where reference in a contract to “plans and specifications” indicates an intention to incorporate them generally, such reference becomes a part of the contract for all purposes. Moreover, if “the plans and specifications are by express terms made a part of the contract, the terms of the plans and specifications will control with the same force as though incorporated in the very contract itself.” Valley Construction Co. v. City of Calistoga, 72 Cal.App.2d 839, 165 P.2d 521 (1946); see also, Trottier v. M. H. Golden Construction Co., 105 Cal.App.2d 511, 233 P.2d 675 (1951).

In the instant case, the parties’ subcontract was a one-page, short-form document, which by its express terms, required appellant to furnish work in conformity with the plans and specifications of the prime contract. The record reflects appellant was acquainted with plans and specifications embodied in *346 the voluminous prime contract. In point of fact, appellant had to refer to the prime contract in order to formulate his bid.

Under the circumstances presented herein, we conclude that the parties intended to incorporate the prime contract into the subcontract.

A review of the pertinent provision of the subcontract, reflects that the risk of loss was to remain with the appellant until formal acceptance of the project by the Sanitation District. According to subsection two of the subcontract, appellant agreed “to do all work in a first-class and workmanlike manner and to the entire satisfaction of the owner, contractor, and architect.” Subsection five of the agreément goes on to state, “to take proper care of all building materials on the ground.” Additionally, section nine of the subcontract states, “Sub-Contractor hereby releases Rico Paving & Grading Co. of all liability on account of any accidents during performance of work in this contract.” The final clause of the parties’ agreement states, “the final payment of which the said Contractor will pay to the said Sub-Contractor, 30 days after final payment by owner provided the Sub-Contractor shall have completed his work to the full satisfaction of said contractor, owner and architect.”

Generally, “one who contracts unqualifiedly to erect a structure for a stipulated price enters into an entire contract to complete such work and must bear the losses resulting from its accidental destruction or damage before completion, unless the contract stipulates that he will not be responsible for losses occurring in such manner.” Mainland v. Alfred Brown Co., 85 Nev. 654, 461 P.2d 862 (1969); Collins v. Post, 227 Or. 229, 362 P.2d 325 (1961).

In the instant case, the subcontract, considered in its totality, suggests that the parties bargained with reference to the prime contract and with the expectation that appellant would bear the risk of loss to its work, until formal acceptance by the District. Additionally, the subcontract does not contain a risk shifting provision absolving appellant from bearing the risk of loss until the contract was completed to the satisfaction of the owner and architect.

In the factually similar case of Collins v. Post, 227 Or. 229, 362 P.2d 325 (1961), the general contractor in charge of building a state prison, subcontracted with plaintiff to build a steam tunnel.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arif v. Wells Fargo Bank, N.A.
D. South Dakota, 2025
Middendorf Sports v. Top Rank, Inc.
954 F.3d 1142 (Eighth Circuit, 2020)
MMAWC, LLC VS. ZION WOOD OBI WAN TR.
2019 NV 38 (Nevada Supreme Court, 2019)
Howard Hughes Co., LLC v. Comm'r
142 T.C. No. 20 (U.S. Tax Court, 2014)
Cayanan v. Citi Holdings, Inc.
928 F. Supp. 2d 1182 (S.D. California, 2013)
Scaffidi v. United Nissan
425 F. Supp. 2d 1159 (D. Nevada, 2005)
Siren Gaming, LLC v. Arviso
153 F. App'x 420 (Ninth Circuit, 2005)
Waggoner v. Town & Country Mobile Homes, Inc.
1990 OK 139 (Supreme Court of Oklahoma, 1990)
Hermann v. Varco-Pruden Buildings
796 P.2d 590 (Nevada Supreme Court, 1990)
Prichard v. Clay
780 P.2d 359 (Alaska Supreme Court, 1989)
Foley Co. v. L.G. Barcus & Sons, Inc.
660 S.W.2d 307 (Missouri Court of Appeals, 1983)

Cite This Page — Counsel Stack

Bluebook (online)
647 P.2d 381, 98 Nev. 342, 1982 Nev. LEXIS 469, Counsel Stack Legal Research, https://law.counselstack.com/opinion/lincoln-welding-works-inc-v-ramirez-nev-1982.