United States of America, for the Use and Benefit of Capitol Electric Supply Co., Inc. v. C. J. Electrical Contractors, Inc., United States of America, for the Use and Benefit of Capitol Electric Supplyco., Inc. v. C. J. Electrical Contractors, Inc.

535 F.2d 1326
CourtCourt of Appeals for the First Circuit
DecidedMay 13, 1976
Docket75-1123
StatusPublished

This text of 535 F.2d 1326 (United States of America, for the Use and Benefit of Capitol Electric Supply Co., Inc. v. C. J. Electrical Contractors, Inc., United States of America, for the Use and Benefit of Capitol Electric Supplyco., Inc. v. C. J. Electrical Contractors, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the Use and Benefit of Capitol Electric Supply Co., Inc. v. C. J. Electrical Contractors, Inc., United States of America, for the Use and Benefit of Capitol Electric Supplyco., Inc. v. C. J. Electrical Contractors, Inc., 535 F.2d 1326 (1st Cir. 1976).

Opinion

535 F.2d 1326

UNITED STATES of America, For the Use and Benefit of Capitol
Electric Supply Co., Inc., Plaintiff, Appellant,
v.
C. J. ELECTRICAL CONTRACTORS, INC., et al., Defendants, Appellees.
UNITED STATES of America, For the Use and Benefit of Capitol
Electric SupplyCo., Inc., Plaintiff, Appellee,
v.
C. J. ELECTRICAL CONTRACTORS, INC., et al., Defendants, Appellants.

Nos. 75-1123, 75-1124.

United States Court of Appeals,
First Circuit.

Argued Jan. 8, 1976.
Decided May 13, 1976.

Edward L. Schwartz, Boston, Mass., with whom Lewis A. Sassoon, Boston, Mass., was on brief, for United States of America for the Use and Benefit of Capitol Electric Supply Co., Inc.

Joseph H. Killion, Boston, Mass., with whom MacPhee, Downey & Killion, Boston, Mass, was on brief, for C. J. Electrical Contractors, Inc., et al.

Jack R. Pirozzolo, Boston, Mass., with whom Willcox, Pirozzolo & McCarthy, Boston, Mass., was on brief, for Usen Associates, Inc. and Keene Corp., Inc.

John M. Reed, Boston, Mass., with whom Philip M. Cronin, Robert P. Baker, and Withington, Cross, Park & Groden, Boston, Mass, were on brief, for Travelers Indem. Co.

Before COFFIN, Chief Judge, McENTEE and CAMPBELL, Circuit Judges.

LEVIN H. CAMPBELL, Circuit Judge.

This Miller Act case involves a government contract for the furnishing and installation of lighting fixtures in a Department of Transportation parking lot. The government awarded the contract to the defendant C. J. Electrical Contractors, Inc. (C.J.), and C.J. in turn contracted with the plaintiff, Capitol Electric Supply Co. (Capitol), to obtain the fixtures. The fixtures supplied initially by Capitol included floodlights that did not conform to the government specifications, but C.J., without notifying Capitol, arranged with the manufacturer to exchange these for conforming floodlights at no extra cost. C.J. then installed the fixtures in the parking lot, received what it was due under the government contract, but failed to pay Capitol. This action was then brought by Capitol.

The Miller Act requires government contractors to provide a "payment bond" for the protection of subcontractors and materialmen. 40 U.S.C. § 270a(a). The bond that C.J. provided was in the amount of $12,500 (one-half of the amount payable under the government contract), with the defendant Travelers Indemnity Co. as surety. Capitol's complaint invoked the Miller Act and sought judgment against both C.J. and Travelers. As various other claims, cross-claims, and counter-claims proliferated, the district court referred the case to a magistrate sitting as a special master under Fed.R.Civ.P. 53. The magistrate ruled for Capitol on its Miller Act claims, granted Travelers' claim to indemnification from C.J., and dismissed all other claims. The district court, however, after hearing objections to the magistrate's report, reversed the finding of Miller Act liability, finding that Capitol had filed suit prematurely and was now time-barred from filing anew. The court nonetheless retained pendent jurisdiction over Capitol's underlying contract claim and confirmed the magistrate to the limited extent of allowing Capitol to recover from C.J. itself for the fixtures that were ultimately supplied. All other claims were dismissed.1

There is no dispute that C.J. agreed to pay Capitol for lighting fixtures, that Capitol in turn paid Stonco to furnish the fixtures C.J. wanted, that Stonco eventually supplied fixtures acceptable to all, and that C.J. has not yet paid Capitol. We need go no further to uphold the district court's findings that C.J. was liable on its contract with Capitol for the adjusted price of the fixtures.2 The question remains whether Capitol may alternatively recover against Travelers on the payment bond that C.J. provided under the Miller Act. The Act gives a right to sue and to recover on such a bond to:

"(e)very person who has furnished labor or material in the prosecution of the work provided for in such contract, in respect of which a payment bond is furnished under section 270a of this title and who has not been paid in full therefor before the expiration of a period of ninety days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which such claim is made. . . ."

40 U.S.C. § 270b(a). The act also provides that "no such suit shall be commenced after the expiration of one year after the day on which the last of the labor was performed or material supplied by (the person suing). . . ." Id. § 270b(b). We think the district court read these provisions too restrictively in denying any recovery to Capitol under the Miller Act. Whether or not Capitol's suit was instituted within the ninety-day waiting period, the circumstances require that Capitol now be given an opportunity to bring its action into compliance with § 270b(a) by filing a supplemental pleading, and we remand for that purpose.

The chronology of events is as follows:

November 2-5, 1971: The Government awarded to C.J. the contract for installation of lighting fixtures, specifying floodlights manufactured by Stonco Electric Products Co. as Catalog No. GD 8902.

November 5, 1971: C.J. ordered lighting fixtures from Capitol.

January 20, 1972: Floodlights manufactured by Stonco as Catalog No. CTC 1510 were delivered.

June 30, 1972: The other components of C.J.'s order from Capitol (allegedly) were delivered.

July 13, 1972: Without notifying Capitol, C.J. arranged with Stonco for substitution of the GD 8902 floodlights.

August 11, 1972: The GD 8902 floodlights were substituted by Stonco without charge to C.J.

October 16, 1972: Capitol filed its complaint, fixing June 30, 1972, as the last day on which it supplied material to C.J. in prosecution of the government contract, and alleging that ninety days had passed without payment.

February 28, 1975: The district court, reversing the magistrate, found that August 11, 1972, was in fact "the day on which the last of the . . . material was furnished" under the Act, and that the complaint was therefore premature.

In settling on the August date as the date from which the ninety-day period began to run, the district court took the view that conformity to the government contract, rather than to whatever contract existed between Capitol and C.J., determined whether the delivered goods were material furnished under the Act. Whether Capitol had fulfilled its obligations to C.J. by the earlier delivery of nonconforming floodlights was, in the court's view, simply irrelevant.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
535 F.2d 1326, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-capitol-electric-ca1-1976.