United States of America, for the Use and Benefit of Burton Mill and Cabinet Works v. A. J. Rife Construction Company and Associates

224 F.2d 600
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 5, 1955
Docket15432_1
StatusPublished
Cited by3 cases

This text of 224 F.2d 600 (United States of America, for the Use and Benefit of Burton Mill and Cabinet Works v. A. J. Rife Construction Company and Associates) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America, for the Use and Benefit of Burton Mill and Cabinet Works v. A. J. Rife Construction Company and Associates, 224 F.2d 600 (5th Cir. 1955).

Opinion

TUTTLE, Circuit Judge.

Pursuant to 40 U.S.C.A. §§ 270-270d, this action was brought in the name of the United States for the use and benefit of Burton Mill and Cabinet Works, the materialman for certain millwork in buildings constructed at Carswell Air Force Base, against the prime contractor, A. J. Rife Construction Company and Associates, and the surety on its Miller Act bond, the Seaboard Surety Company. The subcontractor claimed it was due $2,-956.12 of the agreed price of the materials contracted for, and $447.25 for extras on the project, making a total of $3,403.-37. Defendants denied that any extras were furnished, and asserted that the subcontractor breached its contract by furnishing materials which did not meet specifications and were not suitable for the purpose supplied, alleging as damages therefor $3,000 for additional labor necessitated by the defective millwork, and $3,000 for liquidated damages which they claimed represented a fair proportion of the amount of $9,000 assessed by the Government against the prime contractor for 90 days’ delay, claiming that 30 days of this delay was caused by the subcontractor’s breach; so alleging, the prime contractor counterclaimed for $3,043.88, the difference between these damages and the $2,952.12 of the original contract price admittedly remaining unpaid.

The court, having tried the case without a jury, ordered entry of judgment for defendants on the plaintiff’s claim and for the plaintiff on the counterclaim. The plaintiff’s motion for a new trial was overruled, and this appeal followed. The appellant attacks the judgment on the ground that the uncontradicted evidence showed that it was entitled to recover and that the trial court erred in denying a new trial.

Since we believe that the trial court’s findings of fact were clearly erroneous and must be set aside, and that the judgment must therefore be reversed, we shall consider only this question, as it is determinative of the outcome here.

The trial court orally found the facts to be as follows:

“I find as facts, Gentlemen, that this millwork was not properly done, and, that the defendant was required to make certain repairs in it after, and before its rejection by the United States Engineers’ Inspectors. That this extra work that they had to do on these 355 cabinets, after such rejection, amounted to substantially, perhaps, a little more than the amount sued for here by the plaintiff.
“But, I find that the cross action [sic] of the defendant for an additional amount of recovery has no satisfactory proof of the amount, and that, therefore, judgment must go for the defendant upon the original suit, wherein the plaintiff seeks $3,-403.37; and, against the defendant on its cross action.”

The judgment was phrased somewhat differently :

“ * * * the Court having considered the pleadings, having heard the evidence and argument of counsel, was of the opinion that the facts were with the Defendants on Plaintiff’s action and that the facts were with the Plaintiff on the Cross-Action [sic] of the Defendants; *

Neither brief on this appeal contains any citations of legal authority, and as we see it, the only serious question raised is whether, in the light of the evidence, the findings of fact were not clearly erroneous. Rule 52(a), Federal Rules of Civil Procedure, 28 U.S.C.A. We have *602 found it necessary to examine the record with more care than is usually necessary, because the statements in the briefs of what the evidence showed are so completely different that one might almost think they pertained to different cases; and it is appropriate to discuss the evidence as we find it in the record, at some length.'

The evidence is clear that on December 18, 1955, the prime contractor sent the following notice, captioned “Back Charge” to the subcontractor; we have for convenience numbered the items:

“Back Charge
“Date 12-18-53
“A. J. Rife Construction Co.
Dallas, Texas
To: Burton Mill & Cabinet Works 514 Bonham Street Grand Prairie, Texas Job: Airmens Dormitories Carswell Air Force Base
“Description
“Reworking Millwork, prior to 10-1-53:
[1] Fitting doors and drawers on 355 bed room cabinets ; 2 hrs each: 710 hrs Carpt. at 2.50...... $1,775.00
[2] Rebuild 5 store Room Shelves; 8 hrs each; 40 hrs * Carpt. at 2.50 ............ 100.00
[3] Repair 15 Lounge Cabinets; 4 hrs each; 60 hrs Carpt. at 2.50 .............................. 150.00
[4] Rework Millwork in October, 1953, per attached statement .............. 640.00
[5] Wm. Cameron & Co. Invoice 10-21-53 (attached) .... 5.90
[6] 10-28-53 (attached)____ 9.28
[7] 11-5 -53 (attached) .... 9.44
2,689.62
[8] Insurance and Taxes (10% of Labor) .......... 266.50
“Total ................................ 2,956.12
“A. J. Rife Construction Co.
“By /s/ Gilbert (Illegible) * * * ”

It is admitted in the pleadings that the prime contractor, asserting a right to recoup the amount of this “back charge,” withheld $2,956.12 of the amount which it was to pay the subcontractor according to the terms of their contract. There was evidence also that millwork of the value of $447.25, in addition to that which was to be furnished under the contract, was delivered to the prime contractor at the request of his agent and accepted. These two amounts combined made up the subcontractor’s claim of $3,403.37. From the judgment it would seem that the court found that no extras were actually delivered on request as the appellant claimed, but no express finding was made on this point.

The counterclaim sought not only to recoup the items listed in the back charge, but also to recover from the subcontractor $3,000 damages for breach of contract, claiming that these damages had been suffered by reason, of an assessment of liquidated damages against the prime contractor by the Government, for delay in completing the prime contract.

*603 With respect to some of the items of the counterclaim, the appellees introduced very little if any evidence. The back charge document itself was introduced into evidence with no objection by appellant. That self-serving statement would of course not have been admissible to prove the items of damage, if it had been objected to as hearsay; it was clearly not an entry in the regular course of business under 28 U.S.C.A. § 1732. And yet appellees relied solely upon this document and the following testimony of A. J. Rife, president of the prime contractor, to prove items 5 through 8 of the back charge, totalling $291.12:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
224 F.2d 600, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-burton-mill-and-ca5-1955.