United States of America for the Use and Benefit of Balboa Insurance Company, Assignee v. Algernon Blair, Inc.

795 F.2d 404, 33 Cont. Cas. Fed. 74,507, 1986 U.S. App. LEXIS 27573
CourtCourt of Appeals for the Fifth Circuit
DecidedJuly 25, 1986
Docket85-4571
StatusPublished
Cited by5 cases

This text of 795 F.2d 404 (United States of America for the Use and Benefit of Balboa Insurance Company, Assignee v. Algernon Blair, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America for the Use and Benefit of Balboa Insurance Company, Assignee v. Algernon Blair, Inc., 795 F.2d 404, 33 Cont. Cas. Fed. 74,507, 1986 U.S. App. LEXIS 27573 (5th Cir. 1986).

Opinion

JOHN R. BROWN, Circuit Judge:

This appeal arises out of a dispute between contractors on a federal construction project. Out of a rich Louisiana gumbo containing the Miller Act, the Small Business Association Surety Bond Guarantee Program, and state suretyship law, the District Court detected the bitterness of the ancient doctrine of champerty and dismissed the plaintiff’s case as violative of public policy. We have subjected the identical recipe to our appellate palate and have found the concoction to be both savory and nutritious. We therefore reverse.

Building Barracks

On a construction project, a contractor guarantees that it will perform its responsibilities by obtaining a performance bond in favor of its employer, either the owner if the contractor is a prime contractor, or another contractor if the contractor is a subcontractor. In turn, an unpaid supplier of labor or materials on a construction project can assure that it will ultimately be paid by securing a mechanic’s lien against the improved property. Such a lien, however, cannot be filed against property belonging to the United States. To provide an effective remedy for those who supply labor or material to a contractor on a federal construction project, Congress passed the Miller Act, 40 U.S.C. § 270a et seq. Under the Miller Act, a government contractor must post a payment bond, 40 U.S.C. § 270a(a)(2), and any person who furnishes labor or materials and who has not paid in 90 days may bring suit on the bond for the unpaid balance. 40 U.S.C. § 270b(a).

Keeping this background in mind, we come to the facts of the present case. In 1976, the United States Department of the Army, acting through the Corps of Engineers, awarded two large contracts for the construction of military housing facilities at Fort Polk, Louisiana. The two projects, referred to by the parties as Phase I and Phase II, respectively, were the construction of an Enlisted Men’s Barracks and the construction of an Enlisted Men’s/Enlisted Women’s Barracks.

*406 The successful bidder on the projects was Algernon Blair, Inc. (Blair). Blair, as prime contractor, subcontracted the mechanical portion of Phases I and II to Ball-Co Contractors, Inc. (Ball-Co) of Bay Mi-nette, Alabama. Ball-Co in turn subcontracted a portion of the mechanical work, the automatic temperature control system work, to Pre-Engineered Products Company, Inc. (Pre-Engineered) of Shreveport, Louisiana.

Consistent with the Miller Act, Blair furnished payment bonds with United States Fidelity and Guaranty Company (USF & G) as surety. Ball-Co furnished bonds guaranteeing both its performance and its payment of suppliers with eight individuals as sureties. Pre-Engineered furnished three different subcontract bonds securing its performance of the subcontracts and the payment of its suppliers with Balboa Insurance Company (Balboa) as surety. Pre-En-gineered’s bonds were executed in favor of Ball-Co and stated that if Pre-Engineered did not fulfill all the terms and conditions of its contracts or did not pay for all the labor and materials furnished, then Balboa would be liable to Ball-Co for the “penal sum” stated in the bonds.

To summarize in schematic form, the relationship between the owner, the contractors, and their sureties look like this:

Entity Surety

Corps

(owner)

Blair ........................ USP&G

(prime contractor)

Ball-Co ...................... 8 individuals

(mechanical

subcontractor)

Pre-Engineered .............. Balboa

(temperature control sub-subcontractor)

SBA Enters the Picture

As part of the consideration for Balboa’s bonds, Pre-Engineered entered into a typical indemnity agreement with Balboa by which Pre-Engineered agreed to indemnify Balboa for any loss which Balboa might suffer as the result of its surety agreement in favor of Ball-Co. In addition, Balboa entered into a guaranty agreement with the Small Business Administration (SBA) by which the SBA guaranteed 90% of Balboa’s losses incurred in connection with the bonds written for Pre-Engineered in favor of Ball-Co.

Balboa’s guaranty agreement with the SBA was executed pursuant to the SBA’s Surety Bond Guarantee Program. The purpose of this program is to enable small business concerns — typically minority-owned, as Pre-Engineered was — to participate in the construction industry through the SBA issuing partial guarantees on bid, performance, and payment bonds. The bonds themselves are furnished by private sector sureties such as Balboa who might be unwilling to issue the bonds in the absence of the SBA’s partial guarantee.

Under the program, the SBA is authorized to guarantee up to 90% of a participating surety’s loss sustained when an eligible small business principal breaches the terms of a bid, performance, or payment bond. “Loss” is defined by the program regulations to include all liability, damages, expenses, and attorney’s fees which the surety may incur as a consequence of having executed the guaranteed bonds. If the surety incurs a loss for which it is (partially) reimbursed by the SBA and subsequently recovers all or a portion of the loss, either from the principal or a third person, then the surety must turn over such “salvage proceeds” to the SBA up to the point that the SBA is fully reimbursed. 1

Controversy Sets In — Balboa Steps/Falls In

Work on Phases I and II of the Fort Polk project began at approximately the same *407 time. In April of 1978, a dispute arose between Ball-Co and Pre-Engineered, 2 and Pre-Engineered removed its workforce from the jobsite. Ball-Co notified Balboa that Ball-Co considered Pre-Engineered to be in default. Balboa investigated the status of the Fort Polk projects with the assistance of a consulting engineering firm, and a representative of Balboa met with Ball-Co to discuss completion of the projects.

What happened next is disputed. Ball-Co maintains that Balboa agreed to assume responsibility for both Phases I and II using Pre-Engineered as its labor force. Balboa asserts that Pre-Engineered returned to the job to complete its contract with Ball-Co and that Balboa merely monitored Pre-Engineered’s progress and advanced the necessary operating funds. In any event, Pre-Engineered returned to work under an agreement with Balboa whereby Balboa loaned to Pre-Engineered the necessary monies to continue work on the projects. In exchange, Pre-Engineered assigned its rights (but not its obligations) under the subcontracts to Balboa. Ball-Co acknowledged these assignments and forwarded all further payments of Pre-Engi-neered’s invoices to Balboa in its status as Pre-Engineered’s assignee.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Voiles v. Santa Fe Minerals, Inc.
911 P.2d 1205 (Supreme Court of Oklahoma, 1996)
Buckeye Cellulose Corp. v. Sutton Construction Co.
907 F.2d 1090 (Eleventh Circuit, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
795 F.2d 404, 33 Cont. Cas. Fed. 74,507, 1986 U.S. App. LEXIS 27573, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-for-the-use-and-benefit-of-balboa-insurance-ca5-1986.