Ramona Equipment Rental, Inc. Ex Rel. United States v. Carolina Casualty Insurance

755 F.3d 1063, 2014 WL 2782200, 2014 U.S. App. LEXIS 11640
CourtCourt of Appeals for the Ninth Circuit
DecidedJune 20, 2014
Docket12-55156
StatusPublished
Cited by7 cases

This text of 755 F.3d 1063 (Ramona Equipment Rental, Inc. Ex Rel. United States v. Carolina Casualty Insurance) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ramona Equipment Rental, Inc. Ex Rel. United States v. Carolina Casualty Insurance, 755 F.3d 1063, 2014 WL 2782200, 2014 U.S. App. LEXIS 11640 (9th Cir. 2014).

Opinions

Dissent by Judge ERICKSON.

OPINION

PAEZ, Circuit Judge:

Candelaria Corporation (“Candelaria”), a prime contractor on a federal construction project, Carolina Casualty Insurance Company (“CCIC”), its surety, and Otay Group, Inc. (“Otay”), a subcontractor (collectively, “Defendants”), appeal the district court’s judgment in favor of Ramona Equipment Rental, Inc. (“Ramona”), Candelaria’s supplier of rental equipment, [1066]*1066in Ramona’s action under the Miller Act, 40 U.S.C. §§ 3131-3134. The suit involves Otay’s failure to pay for equipment rented from Ramona on an open book account. As required by the Miller Act, Ramona served Candelaria with notice of demand for payment within ninety days of the last day on which it furnished the equipment. The critical issue in this appeal is whether Ramona’s notice is timely as to rental equipment furnished more than ninety days before the notice. We hold that it is, and affirm the district court’s judgment.

I.

This dispute arises from a federal construction project known as ICE El Centro SPC — Perimeter Fence Replacement/Internal Devising Fence Replacement (the “Project”). Candelaria was the prime contractor on the Project and, in tandem with CCIC, provided a payment bond as mandated by the Miller Act. See 40 U.S.C. § 3131. In December 2007, Otay entered into a subcontract with Candelaria agreeing to supply certain labor and equipment for the Project. Shortly thereafter, Otay submitted, and Ramona approved, a credit application which established an open account for Otay to rent equipment from Ramona for use on the Project. Under the terms of the credit application, rentals would be documented by a rental agreement and invoice.

Between December 2007 and June 2008, Otay and Ramona entered into eighty-nine rental agreements on credit, totaling $235,446.84. On June 6, 2008, Candelaria terminated Otay’s subcontract for cause. At that time, Candelaria owed Otay over $500,000 for labor and equipment provided to the Project, and Otay had paid Ramona only $17,658.57 on the outstanding rental agreements.

On July 25, 2008, Ramona served a ninety-day notice of its claim for payment on Candelaria’s payment bond pursuant to 40 U.S.C. § 3133(b)(2).1 Following service of the notice, in September 2008, Ramona filed a complaint in district court under the Miller Act to recover $393,567.09 in unpaid equipment rentals plus monthly service charges. At trial, Defendants argued that Ramona’s ninety-day notice was untimely as to all rental equipment furnished to the project more than ninety days before service of the notice on July 25, 2008. Defendants also argued that Ramona failed to mitigate its damages and that Ramona was not entitled to recover compound prejudgment interest, which the credit application called “service charges.”

The district court rejected Defendants’ first argument and concluded that, in light of the open book account, the ninety-day notice covered all rental equipment furnished to the Project. The court, however, determined that Ramona’s duty to mitigate damages arose as of June 10, 2008 (four days after Otay’s termination by Candelaria) and barred recovery for invoices after that date. Finally, the court rejected Ramona’s claim for compound prejudgment interest and awarded simple interest at the contractual rate of 1.5%. Accordingly, on August 31, 2011, the district court entered judgment awarding Ramona $178,686.56 plus $106,516.64 in service charges and $114,081.28 in attorneys’ fees. Defendants timely appealed.2

[1067]*1067II.

The Miller Act “represents a congressional effort to protect persons supplying labor and material for the construction of federal public buildings in lieu of the protections they might receive under state statutes with respect to the construction of nonfederal buildings.” Mai Steel Serv. Inc. v. Blake Constr. Co., 981 F.2d 414, 416-17 (9th Cir.1992) (internal citation omitted). To accomplish this beneficial purpose, the Miller Act is entitled to a liberal interpretation. See United States ex rel. Sherman v. Carter, 353 U.S. 210, 216, 77 S.Ct. 793, 1 L.Ed.2d 776 (1957); see also United States v. W. Elec. Co., 337 F.2d 568, 572 (9th Cir.1964). The Miller Act requires that laborers and material-men with no direct relationship to the general contractor furnishing the payment bond, “giv[e] written notice to the contractor within 90 days from the date on which the person did or performed the last of the labor or furnished or supplied the last of the material for which the claim is made.” 40 U.S.C. § 3133(b)(2); see United States ex rel. Water Works Supply Corp. v. George Hyman Constr. Co., 131 F.3d 28, 31-32 (1st Cir.1997). This notice requirement “serves an important purpose: it establishes a firm date after which the general contractor may pay its subcontractors without fear of further liability to the materialmen or suppliers of those contractors.” Id. at 32. Failure to comply with the ninety-day notice requirement is fatal to a Miller Act claim.

We have not addressed the precise issue presented by this appeal.3 In the absence of controlling Ninth Circuit authority, the district court turned to Noland Co. v. Allied Contractors, Inc., 273 F.2d 917, 920 (4th Cir.1959), for guidance. In Noland, the Fourth Circuit considered a claim for six unpaid shipments sent by Noland, a supplier of electrical equipment, to a subcontractor on an open account. Id. at 919. Noland sent written notice under the Miller Act within ninety days of the last shipment. Id. at 918. The notice included claims for several shipments that were delivered more than ninety days before the notice. Id. The court held that the notice was timely as to all shipments, concluding that where there are multiple deliveries or contracts, “the measuring date will be the date when the last material is furnished under the last contract.” Id. at 920. Defendants acknowledge Noland, but argue that it is outdated and that we should adopt the reasoning of several more recent district court decisions that protect the prime contractor and surety from the risk of double payment. Several of our sister circuits, however, have agreed with No-land’s holding, as do we.

In United States ex rel. A & M Petroleum, Inc. v. Santa Fe Engineers, Inc., the Fifth Circuit concluded that notice within ninety days of the last delivery on a project involving multiple purchase orders— including orders made more than ninety days before the notice — was timely under the Miller Act. 822 F.2d 547, 548 (5th Cir.1987). Noting that this “seems to be [1068]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
755 F.3d 1063, 2014 WL 2782200, 2014 U.S. App. LEXIS 11640, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ramona-equipment-rental-inc-ex-rel-united-states-v-carolina-casualty-ca9-2014.