United States of America and Charles A. Bowsher, Comptroller General of the United States of America v. McDonnell Douglas Corporation

751 F.2d 220, 1984 U.S. App. LEXIS 15791
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 19, 1984
Docket83-2119
StatusPublished
Cited by52 cases

This text of 751 F.2d 220 (United States of America and Charles A. Bowsher, Comptroller General of the United States of America v. McDonnell Douglas Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States of America and Charles A. Bowsher, Comptroller General of the United States of America v. McDonnell Douglas Corporation, 751 F.2d 220, 1984 U.S. App. LEXIS 15791 (8th Cir. 1984).

Opinion

FAGG, Circuit Judge.

This is an appeal by McDonnell Douglas Corporation (MDC) from a district court order directing it to produce certain documents subpoenaed by the Comptroller General of the United States (CG). After a careful review, we affirm.

I. Background

In 1976 the United States Air Force entered into a contract with MDC for the purchase of aircraft ultimately destined for the Republic of Korea. The negotiated contract price of over $80,000,000 was arrived at on the basis of MDC’s cost projections plus a profit equal to 18% of the contract price.

In 1978, General Accounting Office (GAO) auditors initiated a review of the contract as part of a study of Department of Defense (DOD) procedures for awarding major procurement contracts. GAO auditors discovered that MDC’s cost projections for tooling and design engineering costs were far above the actual costs incurred in completing the contract. As a result, MDC’s profit amounted to 42% of the contract price rather than the contemplated 18%.

During the course of further investigations, GAO auditors were informed by MDC representatives that MDC’s manufacturing division had prepared for in-house use an estimate of the tooling hours required in manufacturing the aircraft. Believing that any in-house estimates of tooling and design engineering costs would be useful in discovering whether MDC was aware that it had misrepresented its projected costs to the Air Force, GAO auditors submitted a written demand for the in-house documents in September of 1978.

After negotiations between the CG and MDC proved unproductive, the CG served MDC with a subpoena for the documents in March of 1981. The CG’s subpoena enforcement proceeding was dismissed without prejudice in December of that year. 93 F.R.D. 360 (Mo.1981). In January of 1982, the CG again served MDC with a subpoena for the documents, and upon noncompliance with the subpoena, the CG commenced this action in district court. MDC then filed a notice of appeal with the Armed Services Board of Contract Appeals (ASBCA) contesting the CG’s subpoena. The ASBCA dismissed MDC’s appeal as premature because MDC had failed to present its dispute to the Contracting Officer, as required by the Contract Disputes Act of 1978, before seeking relief from the ASBCA.

MDC filed several motions opposing enforcement of the subpoena. In July of 1983, however, the district court ordered MDC to produce the subpoenaed docu *223 ments. It further ordered that execution of the order to produce be stayed pending resolution of this appeal. MDC challenges the district court’s order to produce on several grounds.

II. Jurisdiction

MDC contends that the district court was without jurisdiction to decide this case. It is MDC’s position that the Contract Disputes Act of 1978, 41 U.S.C. § 601 et seq., gives exclusive jurisdiction over this matter to the ASBCA. According to MDC, if this court finds the ASBCA to be without exclusive jurisdiction, we should invoke the doctrine of primary jurisdiction in favor of the ASBCA. Finally, MDC argues that 31 U.S.C. § 54(c) (Supp. IV 1980) (recodified at 31 U.S.C. § 716(c) (1982)), which grants the CG a narrow subpoena power and the right to seek enforcement of that power in district court, violates the constitutional doctrine of Separation of Powers.

A. Exclusive Jurisdiction

“[T]he Comptroller General may require by subpoena the production of books, records, correspondence, memoranda, papers, and documents of contractors * * * to which he has access by law or by agreement of the non-Federal person from whom access is sought.” 31 U.S.C. § 54(c)(1) (Supp. IV 1980). The CG claims access to the documents subpoenaed by virtue of an access to records clause (access clause) included in the parties’ contract. The access clause provides:

The Contractor agrees that the Comptroller General of the United States or any of his duly authorized representatives shall, until the expiration of three years after final payment under this contract * * *, have access to and the right to examine any directly pertinent books, documents, papers, and records of the Contractor involving transactions related to this contract.

MDC argues that, assuming the constitutionality of the subpoena enforcement power granted the CG under section 54(c), the CG must establish a right of access to the documents subpoenaed. The access clause incorporated in the parties’ contract provides the CG access to “directly pertinent” records involving transactions relating to the contract. MDC argues that whether the documents subpoenaed are documents falling within the “directly pertinent” language of the access clause is a legitimate contract dispute over the proper interpretation of the access clause. According to MDC, exclusive jurisdiction for resolving this contract dispute is vested in the ASBCA. We cannot agree.

The Contract Disputes Act of 1978 provides a comprehensive statutory system of remedies for resolving government contract disputes. The Act applies “to any express or implied contract * * * entered into by an executive agency for — (1) the procurement of property.” 41 U.S.C. § 602(a)(1). We need not decide the applicability of the Contract Disputes Act to the contract entered into by MDC and the Air Force for the procurement of aircraft for the Republic of Korea. The mere existence of the Contract Disputes Act does not alter the authority granted the district court in section 54(c)(2) of the General Accounting Office Act of 1980 to enforce subpoenas issued by the CG under section 54(c)(1). The power to enforce a subpoena issued under section 54(c)(1) necessarily carries with it the power to determine if enforcement is proper. In this regard, the district court must determine, among other things, whether the subpoena was issued for a lawful purpose and requests information relevant to that lawful purpose. Oklahoma Press Publishing Co. v. Walling, 327 U.S. 186, 208-09, 66 S.Ct. 494, 505-06, 90 L.Ed. 614 (1946). A determination as to whether the subpoena requests information relevant to the lawful purpose for which it was issued requires the district court to interpret the scope of the access clause of the contract. We disagree with MDC’s contention that the Contract Disputes Act of 1978 precludes the district court from interpreting the proper scope of the access clause under the authority of 31 U.S.C. § 54(c)(2) (Supp. IV 1980).

*224 B. Primary Jurisdiction

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kurtenbach v. Ravnsborg
D. South Dakota, 2018
Northern Valley Communications, L.L.C. v. AT & T Corp.
245 F. Supp. 3d 1120 (D. South Dakota, 2017)
Pacific Lightnet, Inc. v. Time Warner Telecom, Inc.
318 P.3d 97 (Hawaii Supreme Court, 2013)
Jamison v. First Credit Services, Inc.
290 F.R.D. 92 (N.D. Illinois, 2013)
Taradejna v. General Mills, Inc.
909 F. Supp. 2d 1128 (D. Minnesota, 2012)
United States v. Xcel Energy, Inc.
759 F. Supp. 2d 1106 (D. Minnesota, 2010)
Sancom, Inc. v. AT & T CORP.
696 F. Supp. 2d 1030 (D. South Dakota, 2010)
National Labor Relations Board v. Fortune Bay Resort Casino
688 F. Supp. 2d 858 (D. Minnesota, 2010)
Patrick Bohall v. United States
339 F. App'x 661 (Eighth Circuit, 2009)
Fresenius Medical Care v. United States
526 F.3d 372 (Eighth Circuit, 2008)
Grillasca-Palou v. United States Postal Service
573 F. Supp. 2d 493 (D. Puerto Rico, 2008)
United States v. Denise Marie Henderson
416 F.3d 686 (Eighth Circuit, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
751 F.2d 220, 1984 U.S. App. LEXIS 15791, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-of-america-and-charles-a-bowsher-comptroller-general-of-the-ca8-1984.