United States for the Use of Colorado Custom Rock v. G&C Fab Con LLC

Court of Appeals for the Third Circuit·Decided November 5, 2025·No. 24-3053·Unpublished

Opinion

NOT PRECEDENTIAL

UNITED STATES COURT OF APPEALS FOR THE THIRD CIRCUIT

No. 24-3053

THE UNITED STATES FOR THE USE OF COLORADO CUSTOM ROCK CORP.

v.

G&C FAB-CON, LLC; EVEREST REINSURANCE COMPANY, Appellants

On Appeal from the United States District Court for the District of New Jersey (District Court No. 3:20-cv-02968)

District Judge: Honorable Georgette Castner

Submitted Pursuant to Third Circuit L.A.R. 34.1(a)

October 24, 2025

Before: PORTER, FREEMAN, and CHUNG, Circuit Judges

(Filed: November 5, 2025)

OPINION *

CHUNG, Circuit Judge.

This appeal stems from a contract dispute between a general contractor and

*

This disposition is not an opinion of the full Court and pursuant to I.O.P. 5.7 does not constitute binding precedent.

subcontractor related to a federal construction project. The general contractor largely lost a jury trial and now challenges several of the District Court’s rulings on motions it made before, during, and after trial. We will affirm. I. BACKGROUND 1 This case arises from the construction of the Pikes Peak National Cemetery in Colorado Springs, Colorado (the “Project”) for the United States Department of Veterans Affairs (the “VA”). Defendant/Appellant G&C Fab-Con LLC (“G&C”) was the Project’s general contractor, while co-Defendant Everest Reinsurance Company provided a performance bond to G&C. Plaintiff/Appellee Colorado Custom Rock Corp. (“CCR”) performed the Project’s masonry work pursuant to a subcontract with G&C (the “Subcontract”). After CCR performed work, G&C alleged there was a plumbness 2 issue on one of the buildings CRR built. G&C sent CRR a notice to cure, asking CCR to tear down and rebuild the building. Three days later, G&C demolished the building on its own. CCR sued G&C in federal district court for breach of contract and G&C countersued on its own breach of contract claim.

The case went to trial. CCR retained Michael Schuller, a registered professional engineer, to serve as its expert witness. He was unable to inspect the building due to its destruction and thus based his opinions on “project documents, photographs taken by others, and measurements made by others under the direction of G&C.” A18. G&C filed

1 Because we write for the parties, we recite only the facts pertinent to our decision.

2 Plumbness refers to the quality or state of being vertical.

a motion in limine to preclude Schuller from testifying, which the District Court denied.

After CCR presented its case in chief, G&C unsuccessfully moved for a partial directed verdict on several categories of damages CCR sought. On March 7, 2024, the jury returned a unanimous verdict, finding that G&C breached the Subcontract and awarding CCR $589,000 in damages on its breach of contract claim. On G&C’s counterclaim, the jury found that CCR also breached the Subcontract, but awarded G&C just $1.00 in nominal damages.

On March 27, 2024, G&C moved for the District Court to award it attorneys’ fees and costs under the Subcontract. On April 10, 2024, G&C moved for judgment as a matter of law, to alter or amend the judgment, or, in the alternative, for a new trial. The District Court declined to award G&C attorneys’ fees and costs and denied the motions for judgment as a matter of law, to alter/amend the judgment, and for a new trial. This appeal followed. II. DISCUSSION 3

3 The District Court had jurisdiction under 28 U.S.C. § 1331 and the Miller Act, 40 U.S.C. § 3131. The case was initially filed under the Miller Act in the United States District Court for the District of Colorado. The parties later jointly moved to transfer the case to the United States District Court for the District of New Jersey due to the Subcontract’s forum selection clause. The Supreme Court has said that forum selection clauses should be given controlling weight “in all but the most exceptional cases,” Atl. Marine Constr. Co. v. United States Dist. Ct., 571 U.S. 49, 62 (2013) (forum selection clauses should be given controlling weight “in all but the most exceptional cases”); and all circuits to have considered the impact of a forum selection clause on the venue provision of the Miller Act have concluded that the Miller Act’s venue provision is subject to waiver. See FGS Constructors, Inc. v. Carlow, 64 F.3d 1230, 1233 (8th Cir. 1995); U.S. ex rel. Pittsburgh Tank and Tower, Inc. v. G&C Enter., Inc., 62 F.3d 35, 36 (1st Cir. 1995); U.S. ex rel. B&D Mech. Contractors v. St. Paul Mercury Ins. Co., 70 F.3d 1115, 1117 (10th Cir. 1995). We have jurisdiction under 28 U.S.C. § 1291.

A. The District Court Did Not Abuse Its Discretion in Declining to Award Attorneys’ Fees and Costs to G&C

G&C’s first challenge on appeal is to the District Court’s denial of its motion for attorneys’ fees and costs. We review a district court’s denial of an award of attorneys’ fees and costs for abuse of discretion but review the applicable legal standards de novo. Perelman v. Perelman, 793 F.3d 368, 376 (3d Cir. 2015).

G&C argues the Subcontract entitles it to an award of fees and costs because the Subcontract provides in relevant part:

Contractor shall be entitled to recover from Subcontractor all … reasonable attorneys’ fees suffered or incurred by Contractor by reason or as a result of Subcontractor’s default.

A284. Applying New Jersey law, the District Court concluded that the “reasonable” amount of fees here was $0, even though G&C nominally prevailed on its claim that CCR breached the Subcontract, because “the overall outcome of this litigation heavily favors Defendants[.]” A47.

In New Jersey, “[t]he threshold issue in determining whether an attorneys’ fee award is reasonable is whether the party seeking the fee prevailed in the litigation.” N. Bergen Rex Transp., Inc. v. Trailer Leasing Co., 730 A.2d 843, 848 (N.J. 1999). 4 This

4 G&C does not challenge the District Court’s decision to apply New Jersey law.

Rather, it argues that the terms of the contract required the payment of fees without consideration of whether it prevailed at trial. However, New Jersey law provides that “even where attorney-fee shifting is controlled by contractual provisions, courts will strictly construe that provision in light of [New Jersey’s] general policy disfavoring the award of attorneys’ fees,” and reasonableness remains the inquiry. N. Bergen Rex Transp., Inc., 730 A.2d at 848.

analysis entails a two-part test whereby the party seeking fees must demonstrate that (1) “his lawsuit was causally related to securing the relief obtained” and (2) “the relief granted had some basis in law.” Id. at 849. The test is designed to measure “the ultimate results achieved” and the first prong, in particular, “requires a factual causal nexus between the pleading and the relief ultimately received.” Id. at 848–49. “[I]f a successful [prevailing party] has achieved only limited relief in comparison to all of the relief sought, the [trial] court must determine whether the expenditure of counsel’s time on the entire litigation was reasonable in relation to the actual relief obtained ... and, if not, reduce the award proportionately.” Id. at 850 (third and fourth alterations in original) (internal quotations and citations omitted).

Although G&C technically prevailed on its counterclaim against CCR, the jury awarded it only $1 out of more than $1.3 million in damages sought by G&C. In contrast, G&C asked to be awarded more than $700,00 in fees and costs—more, in fact, than the $589,000 in total damages the jury awarded to CCR. We cannot conclude that the District Court abused its discretion in deciding that the reasonable amount of fees to award G&C was $0 given the outcome at trial.

Free access — add to your briefcase to read the full text and ask questions with AI

United States for the Use of Colorado Custom Rock v. G&C Fab Con LLC, (3d Cir. 2025).

United States for the Use of Colorado Custom Rock v. G&C Fab Con LLC (United States for the Use of Colorado Custom Rock v. G&C Fab Con LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Daubert v. Merrell Dow Pharmaceuticals, Inc.
509 U.S. 579 (Supreme Court, 1993)
General Electric Co. v. Joiner
522 U.S. 136 (Supreme Court, 1997)
Blystone v. Horn
664 F.3d 397 (Third Circuit, 2011)
In Re Paoli Railroad Yard PCB Litigation
35 F.3d 717 (Third Circuit, 1994)
Johnson v. Campbell
332 F.3d 199 (Third Circuit, 2003)
North Bergen Rex Transport, Inc. v. Trailer Leasing Co.
730 A.2d 843 (Supreme Court of New Jersey, 1999)
Pomeranz v. McDonald's Corp.
843 P.2d 1378 (Supreme Court of Colorado, 1993)
Robert Addie v. Christian Kjaer
737 F.3d 854 (Third Circuit, 2013)
Jeffrey Perelman v. Raymond Perelman
793 F.3d 368 (Third Circuit, 2015)
Lightning Lube, Inc. v. Witco Corp.
4 F.3d 1153 (Third Circuit, 1993)
Dupree v. Younger
598 U.S. 729 (Supreme Court, 2023)