United States Fidelity & Guaranty Co. v. Cassel Bros. (In Re McNeil)

22 B.R. 408, 1982 Bankr. LEXIS 3548
CourtUnited States Bankruptcy Court, E.D. Tennessee
DecidedAugust 11, 1982
DocketBankruptcy No. 3-80-01159, Adv. No. 3-81-0046
StatusPublished
Cited by17 cases

This text of 22 B.R. 408 (United States Fidelity & Guaranty Co. v. Cassel Bros. (In Re McNeil)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, E.D. Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States Fidelity & Guaranty Co. v. Cassel Bros. (In Re McNeil), 22 B.R. 408, 1982 Bankr. LEXIS 3548 (Tenn. 1982).

Opinion

MEMORANDUM

CLIVE W. BARE, Bankruptcy Judge.

This Memorandum involves a determination of whether any liability for damages, in favor of the counterclaimants, Cassel Brothers, Inc., and Charles M. McNeil, and against plaintiff United States Fidelity and Guaranty Company (USF&G), exists as a result of events connected with the cessation of business by Cassel Brothers, Inc. (Cassel Bros.). A complaint requesting the appointment of a receiver, injunctive relief, exoneration, and indemnification was filed on behalf of USF&G on March 11, 1980, in Sullivan County Chancery Court. The defendants named therein were Cassel Bros., Charles M. McNeil, and numerous parties with interests of record against the real property owned by either Cassel Bros, or McNeil, who is the principal and sole shareholder of Cassel Bros. In their answer and counterclaim, McNeil and Cassel Bros, requested dismissal of the complaint of USF&G and alleged that USF&G was liable to them for wrongfully undertaking to complete construction projects of Cassel Bros, for which USF&G had issued performance bonds.

USF&G filed an involuntary petition in bankruptcy against Charles M. McNeil on September 8, 1980, pursuant to the provisions of 11 U.S.C. § 303(b). Although McNeil opposed that petition, an order for relief under Chapter 7 was entered following a trial. 11 U.S.C. § 303(h)(1). Thereafter, on January 15, 1981, an application for removal of the USF&G action in the Sullivan County Chancery Court to this court was filed by USF&G based on 28 U.S.C. § 1478(a).

I

Cassel Bros, commenced doing business in 1937 as a partnership, but the business was incorporated in 1958 as a Tennessee corporation. Cassel Bros, was a general contractor engaged in the construction of commercial, industrial, public, and residential buildings in Kingsport, Tennessee, and the surrounding area until January of 1980. Two of the larger projects completed by Cassel Bros, are Kingsport’s Dobyns-Bennett High School and Freedom Hall in Johnson City. A performance bond was required for numerous projects undertaken by Cassel Bros. There has been a long-standing principal-surety relationship between Cassel Bros, and USF&G.

Charles M. McNeil has been continuously associated with Cassel Bros, since 1965. McNeil became the only stockholder of the company in 1970. He was president of Cas-sel Bros, during the entire period involved herein. On August 1, 1973, McNeil, acting in his individual and official capacity, executed a Master Surety Agreement in favor of USF&G (Exhibit 2). By virtue of this *410 agreement, Cassel Bros, and McNeil agreed to indemnify USF&G, which acted as surety for Cassel Bros, construction projects, for any expenses or losses incurred by USF&G as a result of performance bonds provided on behalf of Cassel Bros. 1

On August 28, 1978, two separate contracts were executed by Cassel Bros, in connection with proposed projects on which Cassel Bros, had been the successful bidder. The first contract involved a rental housing project in St. Paul, Virginia, on which Cas-sel Bros, submitted a bid of $2,621,000.00 to the Wise County Redevelopment and Housing Authority. The subject of the second contract was a proposed nine-story structure to be built in Norton, Virginia, for a contract price of $4,165,000.00. This structure was to be built for the Norton Redevelopment & Housing Authority to provide satisfactory housing for elderly citizens. Each of these projects was to be funded by the Department of Housing and Urban Development (HUD). USF&G issued performance bonds on each project on behalf of Cassel Bros.

Construction commenced on the two projects during September of 1978. To some extent, adverse weather and excavation problems hampered progress on each project. Construction of the Norton project was further hindered by the malfunction of equipment, delays in the receipt of steel, delays attributable to the architect for the project, and a dispute about the proctor factor. 2 A letter dated August 30, 1979 (Exhibit 44), from James L. Bolling, Executive Director for Norton Redevelopment & Housing Authority, expressing concern over the lack of progress on the Norton project was submitted to USF&G. 3

The testimony reflects that disputes about the progress payments existed between Cassel Bros, and the respective project owners. In each case, the respective housing authority was not permitted to make progress payments in an amount in excess of the amount authorized by the HUD inspector. McNeil testified that the project owners seldom made progress payments on time and that they also failed to pay substantial sums to which Cassel Bros, was entitled, with the result that the cash flow of Cassel Bros, was adversely affected. (Tr. p. 52).

The architect for the Norton project notified McNeil by letter dated November 29, 1979 (Exhibit 29), that construction above the level of the second floor should cease until a determination could be made whether or not certain steel bands or stirrups 4 were installed in the columns at the juncture of the second floor when the columns and floor slab were poured. It was ultimately determined that the stirrups had in fact been omitted by a subcontractor. However, the parties failed to resolve the problem and no further construction work was performed by Cassel Bros, on the Norton project. It was, and continues to be, the contention of Cassel Bros, that it was impossible to install the stirrups as designed. 5

The difficulties experienced by Cassel Bros, in the construction of the St. Paul project were minor in comparison with the problems associated with the Norton project. For example, Charles McConnell, *411 Executive Director of the Wise County Redevelopment and Housing Authority, notified USF&G of a mechanic’s lien 6 against the St. Paul project, by a letter of December 31, 1979 (Exhibit 43). McConnell advised USF&G that he had previously informed Cassel Bros, of the existence of the mechanic’s lien.

On or before January 9, 1980, McNeil contacted Tom McCarley, a bonding agent for Crump Associates, to discuss the problems of Cassel Bros., particularly those associated with the Norton project. Thereafter, acting on McCarley’s advice, McNeil submitted the following letter dated January 9, 1980, to USF&G:

As you know we are presently experiencing some serious cash flow problems. Due to problems encountered on the housing project in Norton and to other problems we are at present unable to continue in business without some financial assistance.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
22 B.R. 408, 1982 Bankr. LEXIS 3548, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-fidelity-guaranty-co-v-cassel-bros-in-re-mcneil-tneb-1982.