United States ex rel. Sligh v. Fullerton Construction Co.

296 F. Supp. 518, 1968 U.S. Dist. LEXIS 9812
CourtDistrict Court, D. South Carolina
DecidedAugust 12, 1968
DocketCiv. A. No. 66-826
StatusPublished
Cited by4 cases

This text of 296 F. Supp. 518 (United States ex rel. Sligh v. Fullerton Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Sligh v. Fullerton Construction Co., 296 F. Supp. 518, 1968 U.S. Dist. LEXIS 9812 (D.S.C. 1968).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW AND ORDER

HEMPHILL, District Judge.

This action was instituted by the Use-Plaintiffs, Thomas D. Sligh and M. L. Shaw, d/b/a Sligh Plumbing and Heating Company, to recover of defendant pursuant to Title 40 U.S.C.A. Section 270a et seq., commonly referred to as the Miller Act. The complaint alleges that on or about December 28,1964, defendant entered into a written contract with Use-Plaintiff by the terms of which Use-Plaintiff was to perform that part of the contract described as Plumbing for the sum of Nine Thousand Four Hundred and No/100 ($9,400.00) Dollars and with additional work the total price was raised to Nine Thousand Six Hundred Fifty-Eight and 65/100 ($9,658.65) Dollars. That between December 14, 1964 and September 15, 1966, Sligh, at the special instance and request of the defendant did supply labor and installed plumbing supplies and materials, all of which were- used in the prosecution of the work described in the principal contract. The complaint further states that after allowing all credits that the balance remaining due and unpaid is the sum of Two Thousand Six Hundred Seventy-One and 24/100 ($2,671.24) Dollars, and that appropriate notices were served by plaintiff upon defendant in compliance with the statute.

Fullerton, in its answer pleads a general denial, denies any additions to the contract price of Nine Thousand Four Hundred and No/100 ($9,400.00) Dollars, and further alleges that the work performed by Sligh was only worth Six Thousand' Nine Hundred Eighty-Seven and 41/100 ($6,987.41) Dollars; and for a second defense alleges that Sligh did not furnish all of the labor and materials as agreed and as a result it had to spend the sum of Two Thousand Four Hundred Twelve and 59/100 ($2,-412.59) Dollars and alleges this amount as a recoupment by reason of breach of contract.

Prior to trial, the defendant conceded the amount of Two Hundred Fifty-Eight and 65/100 ($258.65) Dollars as an extra claimed by Sligh and abandoned an alleged back-charge of One Hundred Twenty-Seven and 35/100 ($127.35) Dollars for repairs to the sump pump, whereupon the court entered an Order awarding plaintiff these sums, and, in addition awarding plaintiff’s attorney a fee of Seventy-Five and No/100 ($75.00) Dollars, with interest thereon from September 15, 1966, together with costs and disbursements. The entire amount has been paid and satisfaction entered with the Clerk of Court.

The case was heard at Columbia, South Carolina, without a jury pursuant to Rule 39(b) F.R.Civ.P. The court now finds the facts specially and states conclusions of law thereon, in accordance with Rule 52(a) F.R.C.P., as follows:

FINDINGS OF FACT

1. On 30 October 1964 Fullerton Construction Co., Post Office Box 4216, Sacramento, California, entered into a contract with the U. S. Army Engineers for construction of a Central Heating and Refrigeration Plant at Fort Jackson, South Carolina. The contract price was $938,000.00. On the same day Continental Casualty Company entered [520]*520into agreement with the parties as surety and furnished its indemnity bond in the principal amount of $469,000.00.

2. Shortly after this contract was entered into defendant began work on the general contract and contact was had between Use-Plaintiff and defendant as to the “plumbing” which the parties agreed would be performed by Use-Plaintiff. Partner Shaw of plaintiff was shown two schematic record drawings 1 as representative of the work involved. One of these was labelled “Plumbing Plan” and another “Plumbing Details and Riser Diagrams.” Shaw thereupon made a “take-off” in which he calculated cost, etc. and came up with a figure of $9400.00.

3. It is uncontradicted that Shaw bid on the work before seeing or signing a contract. He bid on the work as shown on the two record drawings and his calculations 2 reflect:

Shower Pan. Foundation Drain 110.00
3"-1/11 1/11 11/1 111 4'll
Floor Drains-Type 216 w/clamp. device 2-7.70 3-11.50 4-20. 65 213.20
Shower Drains - " " 8.00
2"- 1/11 11/1
Hub Drains - C.I. Pipe 40.00
3"- 1111 11 4"-lll (261.00)
Roof Drains - Internal Exp. Joint-Cast Brass or Copper sleeve type 290.00
1 Sump Pumps: Duplex Non Clog-799.00
1111 Hose Faucetts: Type 65- 1/2" 4.00
1111 Wall-Hydrants-Type. 205 11.90 12.20 48.80
1 P-1- Water Closet - VS-14-38.60 38.60
1 P-2- Urinal-VU13W 62.50 62.50
1 P-3- Lav.-EL20B.Type. 108 "P" Trap.Fty type 14DW-Sup-Type TV. 35.35
P-4Service Sink 82.10 82.10
P-5-148.50 148.50
P-6 52.80 52.80
P-7 68.00 68.00
Labor:
170‘ Foundation Drainage - 70.00 255.00
Rough Rough Equip. 2,255.85
Sump-210.00 140.00 Rough 2,280.00
1 R.D. - 560.00 420.00 Labor 1,850.00
29 Drain - 1160.00 870.00 S.S. 185.00
7 F.X. 350.00 350.00 $6,570.00
$9 &00 0b

[521]*5214. After plaintiff had begun work on the basis of the record drawings and the oral bid of $9400.00, on December 22, 1964 plaintiff, over signature of Shaw wrote to' Fullerton:

Fullerton Construction Co.
Fort Jackson, S. C.
Re: Plumbing-Central Heating Plant
Gentlemen:
We propose to furnish and install the plumbing in the above referenced job, in accordance with plans and specifications, for the amount of $9,400.00 (nine thousand four hundred dollars).
Trust this will meet with your approval.
Yours very truly,
SLIGH PLUMBING & HEATING CO.
M. L. Shaw
This price does not include water meter, if required.
This price does not include excavation for foundation drainage.
Accepted:
Date-
By-
Title_

5. In reply to this letter Fullerton sent a written contract form to Use-Plaintiff, who signed the agreement on January 5, 1965. The trial file reflects that defendant Fullerton accepted Use-Plaintiff’s offer of December 22, 1964 on December 28, 1964.3 The record reflects also that Use-Plaintiff considered the written acceptance as of that date. Plaintiff did not participate with defendant as a sub-contractor in the preparation of the original bid on which the contract was awarded to defendant by the U. S.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

STANLAKE
13 I. & N. Dec. 517 (Board of Immigration Appeals, 1970)
Grayson v. Aetna Insurance
308 F. Supp. 922 (D. South Carolina, 1970)
United States v. Fullerton Construction Company
407 F.2d 1339 (Fourth Circuit, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
296 F. Supp. 518, 1968 U.S. Dist. LEXIS 9812, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-sligh-v-fullerton-construction-co-scd-1968.