United States Ex Rel. Salvino Steel & Iron Works, Inc. v. Safeco Insurance Co. of America

181 F. App'x 247
Court of Appeals for the Third Circuit·Decided May 23, 2006·No. 05-1449·Unpublished·Cited by 1 cases

Opinion

OPINION OF THE COURT

ALDISERT, Circuit Judge.

The United States District Court for the District of New Jersey held Appellant Structural Concepts, Inc. (“SCI”) in contempt for failure to comply with an order enforcing an arbitration award against SCI. On appeal, SCI disputes both the finding of contempt and the legality of the contempt decree issued against it. We have jurisdiction to hear this appeal pursuant to 28 U.S.C. § 1291. We will vacate and reverse.

I.

The parties are familiar with the facts and proceedings in the District Court, so we will only briefly revisit them here. The present action arose from a payment dispute between SCI and Salvino Steel & Iron Works, Inc. SCI had hired Salvino to provide steel and steel erection services for construction of a golf clubhouse for the U.S. Army Corps of Engineers at McGuire Air Force Base. The parties entered into the contract in 2000, and Salvino performed its work in 2000 and 2001.

On February 26, 2002, Salvino filed a complaint alleging breach of contract and bond claims pursuant to the Miller Act, 40 U.S.C. § 270, against SCI and surety Safe-co Insurance Company of America in the United States District Court for the District of New Jersey. 1 On May 9, 2003, the parties agreed to binding arbitration of them dispute. An arbitration award was *249 later issued on June 22, 2004, in favor of Salvino.

The arbitration award had two different requirements. First, it ordered SCI to pay Salvino $63,597.61 within 30 days of the award’s issuance date. Second, it mandated that SCI submit four specific monetary claims to the U.S. Army Corps of Engineers. Pursuant to that directive, any recovery made on the claims mentioned in paragraphs 2A, 2C and 2D of the award (hereinafter referred to as claims “2A”, “2C” and “2D”) would be the property of Salvino, and any recovery upon the claim mentioned in paragraph 2B (hereinafter referred to as claim “2B”) would be the property of SCI. The submission of these claims was to occur within 30 days of the issuance of the arbitration award. The award, however, provided an exception to this 30-day time requirement, stating that: “if [SCI] is actively negotiating a settlement with the U.S. Army Corps of Engineers, the claims ... may be incorporated in those negotiations, provided that such claims can be identified (for payment purposes) in any final settlement.”

On September 8, 2004, the District Court issued an order (the “September 8 order”) entering and confirming the arbitration award. Aside from ordering SCI to pay Salvino $63,597.61, the Court also awarded attorney’s fees to Salvino for the costs of bringing the motion for confirmation of the arbitration award. On October 12, 2004, the Court amended the September 8 order to include those attorney’s fees, which totaled $2,047.65, bringing the full amount owed by SCI to $65,645.26.

On October 27, 2004, Salvino filed a petition for contempt against SCI. Therein, Salvino alleged that (1) SCI “has failed to make any payment in compliance with the Order issuing a monetary judgment against them,” and (2) SCI “has also failed to submit the claims ordered by the arbitrator and confirmed [by the District Court].” (Petition for Contempt, app. at 59a-60a.) In support of the latter allegation, Salvino stated that it had been in contact with the District Counsel for the Department of the Army and the counsel for the U.S. Army Corps of Engineers and that it had not received confirmation from either party that SCI had submitted the required monetary claims. Finally, Salvino requested an award of reasonable attorney’s fees pursuant to N.J. Stat. Ann. § 2A:23B-25 to compensate it for the cost of bringing the petition.

On November 12, 2004, the District Court acknowledged receipt of this petition and gave SCI until November 19, 2004 to file a response. It indicated that if no response was received by that date, “the Court will assume that there is no opposition.” The Court also stated that if no response was received by November 19, “Plaintiff [Salvino] is directed to submit by November 24, 2004, an affidavit setting forth the monetary amount [SCI] would recover from the U.S. Army Corps of Engineers were it to pursue the four claims described in the Arbitrator’s Award, dated June 22, 2004, and in this Court’s Order Confirming the Arbitration Award and Entering Judgment, dated September 8, 2004.”

SCI let the November 19, 2004 deadline pass without filing a response. 2 On November 23, 2004, however, it submitted an affidavit from its president, George Moutis, in which Moutis outlined the status of claims 2A-2D. As for claim 2A, he indicated that SCI had forwarded that claim to the U.S. Army Corps of Engineers and that negotiations with the Corps on this *250 claim had not concluded. As for claim 2B, he indicated that SCI had settled this claim. As for claim 2C, he indicated that SCI had already submitted this claim, but that the Corps rejected it. He further stated that SCI had retained counsel to prosecute this claim before the U.S. Court of Claims. Finally, as for claim 2D, he indicated that “Salvino’s lawsuit did not include such a claim, [but that SCI] is still in negotiations with the U.S. Corps of Engineers regarding this claim.”

On December 10, 2004, the District Court entered an order granting Salvino’s petition for contempt. Although it noted that SCI’s affidavit response was not timely made by the November 19, 2004 deadline, the District Court nonetheless considered and rejected the contentions made in the affidavit. In addressing SCI’s response regarding claim 2A, the Court held that it was “vague” and “tells the court very little about the status of the claim and SCI’s efforts in pursuing it.” (December 10, 2004 order, app. at 16a-17a.) It similarly described SCI’s depiction of the status of claim 2D as being “a vague reference to ongoing negotiations with the U.S. Corps of Engineers” and that SCI provided “no real information regarding its efforts to pursue this claim.” (Id. at 17a.) Consequently, the Court found SCI to be in contempt of the Court’s September 8 order. 3 The Court also awarded a monetary judgment of $15,600 to cover the amount of potential recovery for claims 2A and 2D and attorney’s fees, with the amount to be determined later, as compensation to Salvino for its costs of bringing the petition for contempt.

On January 7, 2005, the Court entered an order amending the monetary judgment of $15,600 to include $1,182 in attorney’s fees. In this order, the Court also rejected SCI’s motion for reconsideration, stating that SCI has “not alleged any new facts or decisions of law that were previously ‘overlooked’ and that ‘might reasonably have resulted in a different conclusion.’ ” This appeal followed.

II.

“The imposition of contempt is reviewed under an abuse of discretion standard and will only be disturbed if there is an error of law or a clearly erroneous finding of fact.” Harris v. City of Philadelphia,

Free access — add to your briefcase to read the full text and ask questions with AI

United States Ex Rel. Salvino Steel & Iron Works, Inc. v. Safeco Insurance Co. of America, 181 F. App'x 247 (3d Cir. 2006).

181 F. App'x 247 (United States Ex Rel. Salvino Steel & Iron Works, Inc. v. Safeco Insurance Co. of America) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related