United States ex rel. Ray Gains, Inc. v. Essential Construction Co.

261 F. Supp. 715, 1966 U.S. Dist. LEXIS 7976
CourtDistrict Court, D. Maryland
DecidedDecember 22, 1966
DocketCiv. A. No. 17071
StatusPublished
Cited by5 cases

This text of 261 F. Supp. 715 (United States ex rel. Ray Gains, Inc. v. Essential Construction Co.) is published on Counsel Stack Legal Research, covering District Court, D. Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
United States ex rel. Ray Gains, Inc. v. Essential Construction Co., 261 F. Supp. 715, 1966 U.S. Dist. LEXIS 7976 (D. Md. 1966).

Opinion

HARVEY, District Judge.

In this Miller Act suit, a subcontractor (“Gains”) is seeking to recover from the general contractor and its surety sums allegedly due under a written agreement covering a part of the work involved in the construction of enlisted men’s barracks and mess at the United States Naval Academy, Annapolis, Maryland. Essential Construction Co., Inc. (“Essential”), a New York corporation with its main office in New Jersey, was awarded the principal contract by the Bureau of Yards and Docks of the Department of the Navy. Essential entered into a written agreement dated August 6, 1954 with Gains, whereby the latter would do all the concrete and cement work required under the principal contract.. Pursuant to the provisions of the Miller Act, 40 U.S.C.A. §§ 270a and 270b, a payment bond was furnished by St. Paul Fire and Marine Insurance Company (“St. Paul”).

By its amended complaint, Gains is claiming $99,148.15 with interest and costs from Essential and St. Paul by virtue of work performed under the subcontract. The defendants have filed a motion to dismiss together with an attached affidavit and the subcontract itself, contending that under the provisions of Paragraph THIRTIETH of the subcontract Gains “has waived any and all rights to commence an action under Title 40, United States Code, § 270(b).”1 Affidavits in opposition have been filed by Gains, and the parties have likewise filed pertinent portions of the general contract, which were incorporated by reference in the subcontract. Pursuant to Federal Rule 12(b), defendants’ motion to dismiss is treated herein as one for summary judgment under Rule 56.

The subcontract of August 6, 1964, which forms the basis for this action, is a printed form contract prepared by Essential and consisting of thirteen pages together with a two page rider. Page 1 of the subcontract states that Essential has entered into a contract dated June 26, 1964 with the Department of the Navy for the construction of the enlisted men’s barracks and mess at the United States Naval Academy, and further provides as follows:

“ * * * and which contract, for all purposes under this agreement includes the advertisement for bids, instructions to bidders addenda, the CONTRACTOR’S proposal as accepted by the OWNER, the form of contract, general conditions, special conditions, specifications, drawings, plans and revisions thereof, alternates and amendments to any of the foregoing, all of which documents in their entirety are hereinafter called the ‘principal contract’ * * *

Under Paragraph FIRST, Gains agrees to do all the concrete and cement work required under the principal contract, at a price fixed at $241,750 by Paragraph TWENTY-SECOND.

Paragraph THIRTIETH of this agreement provides as follows:

“Any controversy or claim arising out of or relating to this agreement or the breach thereof, provision for the determination of which is not made elsewhere in this agreement, shall be' [717]*717settled by the Courts of the State of New York, New York County, which shall have exclusive jurisdiction over every party in connection with any such dispute, and the SUBCONTRACTOR agrees at any and all times to become a party to and be bound by the decision in any litigation with the CONTRACTOR and/or any other subcontractor or subcontractors as the CONTRACTOR may at any time and from time to time direct. The CONTRACTOR and the SUBCONTRACTOR hereby submit to such New York jurisdiction as herein provided. Service of a summons or of a notice of litigation hereunder shall be sufficient if made by registered mail directed to the party at its respective address given above. The cost of such suit shall be borne equally unless otherwise determined by the court. In that regard SUBCONTRACTOR hereby waives any right at law to file a lien of any kind whatsoever and agrees that litigation as herein set forth is its sole and exclusive remedy.”

There are thirty-nine numbered paragraphs in this agreement, and it should be noted that most numbered paragraphs have in the margin notations indicating the content of such paragraph, as for example, “DISPUTES”, “NOTICE”, “PAYMENT”, etc. The notation in the left-hand margin opposite the THIRTIETH Paragraph is “ARBITRATION”.

Defendants’ position is that under Paragraph THIRTIETH Gains may sue only in the courts of the State of New York and that the instant action in this Court, should, therefore, be dismissed. Defendants readily concede that the New York state courts cannot entertain an action on a Miller Act bond. The result would, therefore, be that any suit in New York would be a common law action against Essential only, since St. Paul could not be joined in such suit as a party defendant. Two questions are presented by the defendants’ motion: first, whether the contract in its entirety should be construed as requiring that any suit thereunder can be brought only in the New York courts; and secondly, if so construed, whether such a contractual provision is valid and would defeat the Miller Act jurisdiction of this Court.

I

[I] Under Paragraph THIRTIETH it is not every controversy or claim arising under the agreement which must be settled by the courts of New York, but only those “provision for the determination of which is not made elsewhere in this agreement * * * In finding the intention of the parties to a contract, a court should look to the entire agreement including portions of a principal contract which have been incorporated by reference in a subcontract. Frommeyer v. L. & R. Construction Co., 261 F.2d 879, 882, 69 A.L.R.2d 1040 (3d Cir. 1958).

The construction contract between Essential and the Department of the Navy dated June 26, 1964, which is expressly a part of the subcontract, contains the following provision on page 1:

“The contractor shall furnish a performance bond in the sum of $1,484,140 and a payment bond in the sum of $742,070.”

§ 1.5 of the specifications, also a part of the subcontract, further provides:

“Performance and payment bonds, executed on Standard Forms 25 and 25A revised November 1950, respectively, will be required.”

The contract papers further show that performance and payment bonds on Standard Forms 25 and 25A were in fact executed by Essential and St. Paul on July 1, 1964. Instruction No. 1 of such payment bond provides as follows:

“This form, for the protection of persons supplying labor and material, shall be used whenever a payment bond is required under the act of August 24, 1935, 49 Stat. 793, as amended (40 U.S.C. 270a-270e). It may also be used in any other case in which a payment bond is to be required. There shall be no deviation from this form except as authorized by the General Services Administration.”

[718]*718Under the provisions quoted above, Essential is required by the prime contract to furnish a payment bond on standard government forms. Such a bond was in fact supplied with St. Paul as the surety, and the bond itself indicates that such form should be used whenever a payment bond is required under the Miller Act. The provisions of 40 U.S.C.A. § 270a require a payment bond for this work being performed at the United States Naval Academy, since the contract exceeded $2,000 in amount.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
261 F. Supp. 715, 1966 U.S. Dist. LEXIS 7976, Counsel Stack Legal Research, https://law.counselstack.com/opinion/united-states-ex-rel-ray-gains-inc-v-essential-construction-co-mdd-1966.