Central Contracting Co. v. Maryland Casualty Co.

242 F. Supp. 858, 1965 U.S. Dist. LEXIS 6298
CourtDistrict Court, W.D. Pennsylvania
DecidedMay 20, 1965
DocketCiv. A. 64-776
StatusPublished
Cited by9 cases

This text of 242 F. Supp. 858 (Central Contracting Co. v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering District Court, W.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Central Contracting Co. v. Maryland Casualty Co., 242 F. Supp. 858, 1965 U.S. Dist. LEXIS 6298 (W.D. Pa. 1965).

Opinion

MARSH, District Judge.

This is a diversity (?) 1 action arising out of a contractual dispute between the plaintiff, as painting subcontractor, and C. E. Youngdahl & Company, Inc.—Crump, Incorporated—Psaty & Fuhrman, Inc. (a joint venture), the prime contractor, involving plaintiff’s claim of $63,-405.87 as compensation for certain painting “extras” and/or corrective work required of it in the construction of the North View Heights housing project here in Pittsburgh. 2 Defendant is a surety for the prime contractor and in that capacity furnished both a “Performance Bond” and a “Labor and Materialmen’s Bond” to the project Owner (Housing Authority of the City of Pittsburgh). The complaint is drawn in two counts, the first count asserting third-party beneficiary rights under the “Performance Bond”, and the second count asserting such rights under the “Labor and Materialmen’s Bond”. Defendant has moved to dismiss, contending that neither count states any claim upon which relief can be granted; that by reason of express provision in the pertinent subcontract, plaintiff has agreed to commence any suit against the prime contractor or its sureties (including defendant) only in the courts of the County of New York, State of New York; and that, by yet another provision in the said subcontract, plaintiff is obliged as a condition precedent to litigation to join with the prime contractor in arbitration of all disputes arising out of the agreement, excepting such interpretations of its obligations “as fall within the province of the Owner under the General Contract”. Defendant has *860 also filed a motion to stay the within proceedings pending arbitration. 3

We are of the opinion that the provision of the subcontract whereby plaintiff agreed to sue only in New York is valid and its existence a proper reason for this court to decline to exercise jurisdiction over the pending litigation. For that reason, defendant’s motion to dismiss will be granted.

In National Equipment Rental, Ltd. v. Szukhent, 375 U.S. 311, 84 S.Ct. 411, 11 L.Ed.2d 354 (1964), the Supreme Court upheld the validity of a printed form provision inserted in a farm equipment lease by the lessor, a corporation with its principal place of business in New York, whereby the lessees, Michigan farmers, agreed to designate a New York resident as their agent for the purpose of accepting service of process in the State of New York. The following is an excerpt from the majority opinion (at pp. 315-316, 84 S.Ct. at p. 414):

“The purpose underlying the contractual provision here at issue seems clear. The clause was inserted by the petitioner and agreed to by the respondents in order to assure that any litigation under the lease should be conducted in the State of New York. The contract specifically provided that ‘This agreement shall be deemed to have been made in Nassau County, New York * * * and shall be interpreted, and the rights and liabilities of the parties here determined, in accordance with the laws of the State of New York.’ And it is settled * * * that parties to a contract may agree in advance to submit to the jurisdiction of a given court, to permit notice to be served by the opposing party, or even to waive notice altogether. See, e. g., Kenny Construction Co. v. Allen, 101 U.S.App.D.C. 334, 248 F.2d 656 (1957); Bowles v. J. J. Schmitt & Co., Inc., 170 F.2d 617 (C.A.2d Cir. 1948); Gilbert v. Burnstine, 255 N.Y. 348, 174 N.E. 706, 73 A.L.R. 1453 (1931).” (Emphasis ours.)

Here, too, a contracting party has agreed in advance to submit to the jurisdiction of a given court. Paragraph 45 of the subcontract provides as follows:

“45. The rights of the parties shall be construed pursuant to the Laws of the State of New York. The Subcontractor agrees that it will not commence any action, whether in law or in equity, against the Contractor or its sureties on bonds, if any, because of any matter whatsoever arising out of the alleged breach or performance of this subcontract agreement, in any Courts other than those in the County of New York, State of New York, and the Subcontractor expressly waives any and all rights the said Subcontractor might have by reason of the aforesaid bond provisions, if any, or by reason of any other cause whatsoever, to bring said action in any other court. The rights herein given the Contractor shall also be deemed for the direct benefit of the aforesaid sureties, if any, with the same force and effect as if they were parties hereto.”

The demise of Pennsylvania’s policy of absolute hostility toward such contractual provisions was signalled by the Supreme Court of Pennsylvania in Nippon Ki-Ito Kaisha v. Ewing-Thomas Corporation, 313 Pa. 442, 170 A. 286, 93 A.L.R. 1067 (1934). In that case the Court enforced a contractual provision requiring a Penn *861 sylvania corporation to arbitrate a dispute in New York, but the sweep of its language embraced equally a provision requiring a Pennsylvania corporation to sue only in New York. 4 So, too, the language of our Court of Appeals in Monte v. Southern Delaware County Authority, 335 F.2d 855 (3d Cir. 1964), at p. 857:

“It is beyond question that the parties to a contract may agree to submit disputes over that contract to arbitration and may also agree upon a particular tribunal for reviewing the arbitration award. Indeed, as we have noted in another context, an agreement that an arbitration award shall itself be final and binding upon the parties generally precludes judicial review. Bower v. Eastern Airlines, Inc., 214 F.2d 623, 625 (C.A.3), cert. denied, 348 U.S. 871, 75 S.Ct. 107, 99 L.Ed. 685 (1954).” (Emphasis ours.)

Within recent weeks, a suit by this selfsame plaintiff against the prime contractor in connection with the identical subcontract and controversy here at issue has prompted the Supreme Court of Pennsylvania to declare unequivocally that “a court in which venue is proper and which has jurisdiction should decline to proceed with the cause when the parties have freely agreed that litigation shall be conducted in another forum and where such agreement is not unreasonable at the time of litigation.” Central Contracting Company v. C. E. Youngdahl & Company, Inc. et al., 418 Pa. 122, 209 A.2d 810 (May 3, 1965).

Other authorities are in accord that, in the absence of a showing of unreasonablenss, the courts should give effect to an agreement limiting the choice of forums of the contracting parties. Wm. H. Muller & Co. v.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knecht, Inc. v. United Pacific Insurance Company
860 F.2d 74 (Third Circuit, 1988)
In Re Food Fair, Inc.
14 B.R. 46 (S.D. New York, 1981)
National Equipment Rental, Ltd. v. Sanders
271 F. Supp. 756 (E.D. New York, 1967)
Central Contracting Co. v. Maryland Casualty Co.
367 F.2d 341 (Third Circuit, 1966)
National Equipment Rental, Ltd. v. Centra Cast Co.
270 F. Supp. 999 (E.D. New York, 1966)
Barton v. Bechtel Corp.
253 F. Supp. 288 (N.D. California, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
242 F. Supp. 858, 1965 U.S. Dist. LEXIS 6298, Counsel Stack Legal Research, https://law.counselstack.com/opinion/central-contracting-co-v-maryland-casualty-co-pawd-1965.